Section 4.9. Subgrade preparation.

Sobre este texto

  • As published by Municode, retrieved 2026-11-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

(a) Clear and grub entire street right-of-way before commencing street earthwork construction. For specific technical requirements reference is made to Georgia DOT Specifications Section 201-Clearing and Grubbing Right-of-Way. Combustible material generated from

clearing and grubbing operations may be burned when authorized by the Fire Chief.

(b) Conduct street earthwork construction in accordance with Georgia DOT Specification Sections 205 - Roadway Excavation and 208 - Embankments. For purposes of these Regulations, the maximum density of soil material shall be determined by ASTM D 698 (Standard Proctor) test procedures.

(c) Complete utility and drainage earthwork before starting street subgrade construction.

(d) Perform subgrade construction in accordance with Georgia DOT Specification section 209 - Subgrade Construction.

(e) The developer shall provide quality control testing during earthwork and subgrade construction as necessary to assure the entire earthwork, including all fill layers and subgrades, meet the minimum requirements of these Regulations. The minimum quality control testing to be provided consists of the following:

(1) Moisture-density relationship curve for each type soil encountered.

(2) One in-place density test (ASTM D 1556 or other recognized method) per 1200 square yards of street subgrade. If development containing less than 1200 square yards of subgrade, provide at least one in-place density test.

(3) One in-place density test (ASTM) D1556 or other recognized method) per 1000 cubic yards or fraction thereof of fill placed.

(f) Earthwork which falls below specified minimum quality control limits shall be removed, reconstructed and retested until compliance with specified requirements is achieved.

(g) After completing street earthwork operations and before beginning street base construction, the developer shall file a copy of the quality control test results demonstrating compliance with these requirements with the Cordele Department of Community Development. At any

time during the construction process, representatives of the City may request to review and the developer shall provide quality control test results.

Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:cordele/zoning/4.9@2026-11-11-29db55b6fe

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Cordele Zoning Ordinance, Section 4.9. Subgrade preparation | Georgia Commons