Ir al contenido
Georgia Commons
Menú

Dunwoody · Ordenanza de zonificación

Part II - CODE OF ORDINANCES / Chapter 16 - LAND DEVELOPMENT REGULATIONS / Article IV - DESIGN AND IMPROVEMENT STANDARDS / Division 3 - IMPROVEMENTS

Sec. 16-257. Water.

Sobre este texto

  • As published by Municode, current through 2020-02-10
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

(a) Certification of final plat. Compliance with the improvement standards of this section must be certified by an authorized representative of the services provider.

(b) Water mains.

(1) The city, or its designated water service provider, has the right and privilege to design water mains and appurtenances of the right size and materials in subdivisions. The design will include necessary improvements to the water system, including extensions along the entire

roadway frontage of the development.

(2) Sizes of water mains in subdivisions will be determined by the city to ensure adequate domestic supply and fire protection for the subdivision.

(3) All materials for water mains in subdivisions will conform to specifications of the American Water Works Association.

(4) Water mains will be laid a minimum distance of four feet back of the curb line.

(c) Fire hydrants. Fire hydrants must be installed in subdivisions so that all residential property will comply with the requirements of the applicable fire prevention code. The location of

fire hydrants must be reviewed and approved by the public works director. Additional fire hydrant locations may be required to ensure water quality and air release standards.

(d) Water valves. Water valves must be installed in subdivisions to affect a minimum cutoff of mains in case of shutdowns.

(e) Stub-out services. Stub-out services must be installed when the city determines them necessary to avoid cutting of pavement or sidewalks. Stub-out services must be placed on lots as specified by the city.

(f) Water service data.

(1) The applicant must furnish data on the final subdivision plat in digitized form, as required by the community development director.

(2) The city is authorized to determine the location and size of all pipe, valves, fire hydrants, fittings and stubs to lots, consistent with design regulations promulgated by the community development director in conjunction with the city's water services provider. The city must furnish to the owner/applicant copies of the final plat with a list of materials that will

include the total linear feet of main to be extended.

(3) With this information the applicant will take bids from contractors and when the contract is awarded, furnish the city with a copy of the contract.

(g) Certification. The applicant's engineer or surveyor must furnish the city with an engineer's certificate.

(h) Prerequisites to materials delivery to contractor.

(1) No materials to be used for subdivision water improvements will be delivered to the job site until the requirements of subsections (f) and (g) have been met.

(2) No work will commence on the water improvements until the water services provider has inspected and approved all materials on the site for compliance with the materials specifications as published by the water services provider.

(3) Any water line material or appurtenances found not to meet specifications must be removed from the job site by the contractor prior to commencement of any water line construction activity.

(i) Final inspection. Upon completion of the job of installing water improvements in a subdivision, the owner/applicant's engineer and the city's water services provider will measure the

work done showing station numbers to all valves, fire hydrants and other pertinent fittings including stub locations. The owner/applicant must furnish the city a copy of this report showing the

work done. The owner/applicant must furnish the city with a final cost of the labor to install the materials.

(j) Material storage. It is the contractor's responsibility to acquire, properly handle, store and protect all materials. The city may not be

held responsible for loss or damage to any materials. No damaged material must be utilized in the water line construction.

(k) Excavation.

(1) Depth. Trenches must be excavated to a depth sufficient to provide a minimum of three feet of cover over subdivision water mains, and two and one-half feet over subdivision water service lines. In

rock cuts, the excavation must be of sufficient depth and width to provide a minimum of six inches' earth cushion below and along the sides of the mains.

(2) Sheeting. The contractor must install sheeting and bracing where necessary to prevent caving, to protect new work and to protect adjacent utility lines, and public and private property.

(3) Blasting. Blasting is permitted only with the written approval of the city for each location. The contractor must provide adequate protection, such as mats, and permit only qualified, experienced personnel to supervise blasting. Approval by the city in no way relieves the contracLAND DEVELOPMENT REGULATIONS § 16-257 tor from any liability for any damages

whatsoever resulting from the blasting operations.

(l) Pipe-laying. Pipe-laying must conform to the specifications prepared and approved by the community development department in effect at the time a development permit application is received by the community development department. The community development director is authorized to promulgate specifications and regulations to govern and implement this provision.

(m) Backfilling.

(1) All backfilling in subdivisions must be done with material free from roots, stumps and other foreign material. No rock will be permitted within a distance of six inches from the pipe or ground surface.

Rock larger than 12 inches in greatest dimension will not be allowed in any part of the trench. All rock larger than 12 inches must be disposed of by the contractor.

(2) The placing and compaction of all backfill material must comply with all applicable standards and specifications of the service provider/governing authority.

(3) The contractor must restore to the original condition as at the start of the job, all shrubbery, grass, sod, fences, etc., disturbed during the contractor's operations.

(n) Pavement replacement. Cuts in existing street pavement and driveways will be patched by the applicant/owner. The applicant/owner must maintain the cuts in good condition until a permanent patch is made. When necessary to abate dust, mud or potholing, the contractor must furnish and install crushed rock or cold patch asphaltic concrete to the surface of the trench.

Appropriate utility permits must be obtained from the public works director prior to work being initiated.

(o) Barricades and lights.The contractor must furnish and place sufficient barricades and lights to adequately protect the work on subdivision water improvements, and to protect all motorized and nonmotorized traffic. No street may be completely blocked, without the permission of

the public works department.

(p) Testing. Testing of required improvements must be conducted in accordance with standards and specifications of the service provider/governing authority.

(q) Sterilization of mains. The contractor will furnish all chemicals, feeding equipment and manpower for the sterilization of water mains.

The contractor is responsible for the disposal of dose water in accordance with environmental protection division regulations. The contractor must employ a hydric meter to record the quantity of water used and reimburse the city's water services provider for the appropriate amount.

(r) Cleanup. A thorough cleanup must be made before final acceptance of subdivision water improvements. All excess rock must be removed; private and public property must be restored to original condition, and all excess water line materials removed from the job site.

(s) Service laterals. The contractor must submit an as-built drawing showing the location, lot number and street address for each service

lateral installed in a subdivision.

(t) Maintenance.

(1) The owner/applicant must maintain all water mains, appurtenances, trenches and other disturbed surfaces for a period of 12 months after approval and acceptance by the city.

(2) The contractor is responsible for repairs to any leaking pipe, fittings, etc. Should any trench settle, the contractor must promptly furnish and place fill to original grade. If any leak or trench settlement occurs under any pavement, the contractor will be held responsible for the cost of replacing the pavement.

Historia

La línea de historia que la fuente imprime al final de la sección.

(Ord. No. 2013-10-14, 1(Exh. A § 16-15.20), 10-14-2013; Ord. No. 2015-01-04, § 1, 1-26- 2015)

Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:dunwoody/zoning/16-257@2020-02-10-f331b9b69b

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Dunwoody Zoning Ordinance, Sec. 16-257. Water | Georgia Commons