Sec. 16-258. Sewer.
Sobre este texto
- As published by Municode, current through 2020-02-10
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.
(a) Installation.
(1) Sanitary sewers must be laid in all streets, service connections installed to property lines, and connections made to trunk line sewers in all subdivisions, including
subdivisions with private disposal systems.
(2) The developer of a property adjacent to undeveloped and unserved land lying upgradient from the subject property, must extend the sewer main to the outside boundary of the property being developed in order to allow for the future provision of sewer service to such
unserved adjacent property unless waived by the community development director.
(3) In all developments with private disposal systems, lines must be laid and temporarily plugged or capped at the points of service connections to the proposed trunk
sewer line and individual lot lines in accordance with county requirements and specifications.
(4) Corresponding service connections must be installed and temporarily plugged or capped from each principal structure in such a manner that a proper service connection can be made when permanent sewer service is available. This requirements may be waived by the community development director based upon service feasibility to the principal structure as determined by the elevation of the structure with reference to the elevation of the proposed sewer line.
(b) Design. Design of the proposed sewer system within a development must conform to the specifications prepared and approved by the department of community development in effect at the time a development permit application is received by the department of community development.
(c) Filing of plans. Filing of plans must conform to the specifications prepared and approved by the department of community development in effect at the time a development permit application is received by the department
of community development. The lowest minimum finished floor elevation must be noted for each lot.
(d) Materials. Materials must conform to the specifications prepared and approved by the department of community development in effect at the time a development permit application is received by the department of community development.
(e) Construction. Construction must conform to the specifications prepared and approved by the department of community develLAND DEVELOPMENT REGULATIONS § 16-258 opment in effect at the time a development
permit application is received by the department of community development.
(f) Comments on plat. Upon receiving the preliminary plat, the community development director must compare the proposed subdivision in relation to existing and proposed sewer systems. Comments, recommendations and
changes deemed advisable will be marked on the preliminary plat and returned to the community development director.
(g) Certification on plat. The community development director must place certification upon the final plat after the applicant has complied
with the sewer system requirements of the county.
Such certification is required prior to final approval by the city manager.
(h) Acceptance. The city or its designated wastewater services provider may not accept the subdivision sewer project until the applicant has complied with all applicable requirements of the city and the county.
(i) Maintenance.
(1) The owner/applicant must maintain all sewer lines, appurtenances, trenches and other disturbed surfaces for a period of 12 months after approval and acceptance by the city manager and/or the city's wastewater services provider.
(2) The owner/applicant must be responsible for repairs to sewer system. Should any trenches settle, the owner/applicant
must promptly furnish and place fill to original grade. Should any leaks or trench settlement occur under any pavement, the contractor will be held responsible for the cost of replacing pavement.
Historia
(Ord. No. 2013-10-14, 1(Exh. A § 16-15.30), 10-14-2013; Ord. No. 2015-01-04, § 1, 1-26- 2015)