Sec. 16-259. Streets.
Sobre este texto
- As published by Municode, current through 2020-02-10
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.
(a) Standards.
(1) Generally. Street improvements must be provided in each subdivision in accordance with the city's standards and specifications and the regulations of this chapter.
(2) Grading. The construction limits must be cleared of all trees, stumps, brush and rubbish before grading operations are begun. No trees, stumps, brush or rubbish must be placed in fill sections within the construction limits. Such debris must
be disposed of in a manner satisfactory to the community development director.
Fill sections must be placed in six-inch layers with each layer thoroughly compacted with a sheep foot roller or by other approved methods before the next
layer is placed, compaction to be not less than 95 percent as determined by ASTM D 698 Streets must be graded to the width required to accommodate street, curb and sidewalk improvements.
(3) Curbing. Header curbs or standard curb and gutter is required on all streets and must be furnished and installed by the applicant unless grassed swales are used for water quality control and approved by the community development director. The minimum classes and types of curbing permitted will be as follows:
a. Granite curbing, class D or better.
b. Other as approved by the community development director. All curbing must be placed in firm, wellcompacted subgrade, and curbing displaced prior to acceptance for
maintenance by the city must be reset or replaced. Specifications for the granite curbing are available from the city department of community development.
(4) Base and paving. All roadways must be paved in accordance with city standards and specifications.
(5) As-built drawings. As-built drawings for all new streets must be submitted to the department of community development depicting a street profile based on the centerline and 50-foot stations.
(6) Third-party inspections. Before acceptance by the city, street improvements must be inspected by a qualified third
party for compliance with all applicable city standards and specifications.
(b) Street signs.
(1) Traffic control devices. Street signs, traffic control signs, and devices such as striping and signalization, shall be provided by the developer at no cost to the city. All devices shall be installed prior to
the approval of a final plat, or where no final plat is required, prior to the issuance of a certificate of occupancy.
(2) Signing.
a. All signing and pavement marking must be designed and installed in conformance with the latest edition of the "Manual on Uniform Traffic Control Devices."
b. All signposts to be placed within concrete area must have six-inch wide diameter space through substructure.
c. The signs shall be new die cut anodized aluminum (at least .080 inches thick) with a corner radius
no smaller than one and one-half inches and installed on a single square post with standard hardware. This post should be installed to break-away standards with a slip
base. Should the applicant wish to use decorative poles, a custom permit will need to be applied for in the public works department.
d. As part of the land disturbance permit process, the developer shall identify the type, number and location of signs.
e. The applicant will be responsible for maintaining the signs from installation to final inspection. The city reserves the right to replace
stop or yield signs if they have been down for more than 12 hours, to replace any regulatory signs if they have been down for more than seven days, and to replace any other signs if they have been down for more than 14 days. The developer will be responsible for any costs incurred.
f. The sign inspection shall be done by the department of community development prior to acceptance of the final plat or as established by the director of community development. The signs shall be included in the right-of-way surety at the same
time as the pavement. If the city needs to replace any signs at the time of the final inspection, the value would be forfeited.
g. The street name sign should be two-sided and constructed on flat, not extruded, blades.
(c) Road hazards. Subdivision signs, planter boxes, and other similar permanent structures may not be located on street rights-of-way and may not be constructed in a manner which, in the opinion of the city, obstructs driveway sight distance or creates a traffic hazard; detailed plans for these structures must be submitted to the community development director.
(d) Surface drainage.
(1) The size, length and location of all surface drainage pipes or structures must be shown on the final subdivision plats
and subject to the approval of the public works department. All storm drain pipes or culverts carrying stormwater from the street and adjacent property between or through lots must be extended to at least 30 feet behind the rear of the house.
Stormwater must be released into a channel without causing scouring, erosion or resulting sedimentation to the receiving
channel. When necessary, the outlet channel must include structural and vegetative measures to ensure non-erosion velocities. This requirement for pipe extension only applies to the discharge ends of piped systems.
a. An exception to extending pipes 30 feet behind the rear of the house may be made for pipes 54 inches and larger where the house site is proposed to be more than 30 feet from the center of the drainageway.
b. An exception to extending pipes 30 feet behind the rear of the house may be granted by the city when soil conditions prohibit erosion.
c. An exception to extending pipes 30 feet behind the rear of the house may be granted by the city where lots are at least one acre in size, open channels are provided, and neither ponding nor erosion control will result.
(2) Installation, backfilling and compaction must be in accordance with state transportation department specifications, sections 106 and 520. All pipes must have a minimum cover of one foot and headwalls
or inlet basins constructed at the end of each pipe.
(3) The design of drainage structures must be based on recognized hydrological formulas as outlined in the Stormwater Management Manual.
(4) A contour map with an interval of two feet must be submitted as part of preliminary plats. As determined by the community development director, any lots within the subdivision which are undesirable for building due to bad drainage conditions must be excluded, and no
building is permitted thereon until these conditions have been corrected as specified by the community development director.
(e) Plans and profiles. Three copies and one electronic/digital copy of the complete plans and profiles for subdivision street improvements must be submitted for review and recommendation of approval or denial by the public works department prior to approval of the final plat.
(f) Financial guarantees.
(1) If, at the time the final plat is submitted for approval, the construction of the street improvements has not been accomplished, then the final plat must be disapproved. No performance bonds may be allowed or authorized except the community development director may require a performance bond to be filed with the city to ensure that all final road
improvements required by this Code are made by the owner or applicant. The city may not accept a road until such time as all road improvements required by the city are made.
(2) After the work has been completed in accordance with the city specifications and duly inspected by the city, then a maintenance bond is required, equal to ten percent of the estimated construction cost. The proposed maintenance bond must be reviewed and approved as
to form by the city attorney prior to acceptance by the city. The maintenance bond must cover the street improvements, drainage system, water system and sewer system. Funds may be placed
in escrow with the city in lieu of maintenance bonds.
(3) The applicant must sign a maintenance agreement with the city, by which the applicant must agree to maintain the streets, drainage, water quality BMPs, water and sewer systems, and rights-ofway for a period of 12 months. During the applicant maintenance period, the
city must make inspections and instruct the applicant by letter as to what correction must be made.
(4) In case of emergency repairs, which must be made immediately, or required corrections, which are not made within 30 days of notice, the city must have the authority to make these corrections and recover costs from the applicant. In cases where funds are being held in escrow by the city, the cost of making these corrections must be deducted from these funds, and the applicant charged with any costs
above the amount of escrow funds.
(5) At the end of the 12-month applicant maintenance period, the city must make a final inspection and notify the applicant and the bonding company of any corrections to be made. If the work is acceptable, the community development director must recommend to the city attorney that all remaining escrow funds be released; provided, however, in the discretion of the community development director, based upon:
a. Weather conditions;
b. Labor market;
c. Material market; or
d. Circumstances beyond the control of the applicant or the city unforeseen by either party.
(6) The maintenance period may be extended for a definite period of time sufficient to make the necessary corrections by an agreement in writing executed by the city, the applicant and his surety.
Provided, further, that the applicant is responsible for any damages done to work already completed by him to the time of the extension agreement whether or not the city had accepted it.
(7) Maintenance bonds and acceptance by the city of any dedicated improvements must be as one package upon compleLAND DEVELOPMENT REGULATIONS § 16-259 tion of all improvements, even though
the final plat may have been approved prior to completion.
(g) Standard plans and specifications. Standard city plans and specifications referred to in this part are on file and may be obtained from
the community development department.
(h) Sidewalks and bicycle lanes.
(1) Sidewalks are required on all sides of all new street frontages and on the subject side of all improved streets in all subdivisions and as set forth in subsection 16-223(j), unless the community development director determines that a deferral or fee in lieu is approved in accordance with section 16-221.
(2) At a minimum continuous sidewalks are required on at least one side of all new and improved local residential streets.
No other variances or exceptions are allowed.
(3) The community development director may require that sidewalks be extended to the nearest arterial or collector street.
(4) A grassed, planted or landscaped strip, as set forth in this article, must separate all sidewalks from adjacent curbs, bridges excepted. The community development director may approve a variable sidewalk location and landscape strip width based on site conditions and future road
expansions. Where sidewalks currently exist, new sidewalk construction or reconstruction must be continuous with existing sidewalks.
(5) Sidewalks must be installed at the same time as the building construction, unless an alternative method is approved by the community development director. Sidewalks must be completed prior to the issuance of certificate of occupancy for
property on which the sidewalk fronts.
The sidewalk plan must be recorded on the final plat and all sidewalks completely installed prior to approval of the final plat.
(6) Sidewalks may not be cut, removed or closed temporarily without a permit from the public works department. Such permit may not be issued unless safe, adequate, and convenient provision is made for nonmotorized travel through the area
that is disrupted. Damage to sidewalks caused during construction or development activity must be repaired at no cost to the city within 30 days or prior to
issuance of a certificate of occupancy, whichever is earlier.
(7) All sidewalk construction and repairs must provide for wheelchair ramps to and from sidewalks at the intersection of each street corner and crosswalk. Access ramps must be constructed pursuant to standards approved by the public works department.
a. All driveways with sidewalks and sidewalk crosswalk installations are required to be constructed in accordance with the accessible sidewalk standards published by the U.S. Department of Transportation, Federal Highway Administration, in FHWA-SA-03-01 as amended.
(8) Sidewalks may not be constructed on any street in the city without first obtaining a permit to do so from the public works department.Any person construct-
ing a sidewalk on a street, without first obtaining a permit, is in violation of this Code, and the public works department is authorized to condemn the sidewalk and have it removed and replaced at no cost to the city.
(9) Bicycle lanes are required on new or substantially improved arterials or collector streets where the posted speed limit is 35 miles per hour or greater. Bicycle
lanes may also be required by the community development director where necessary to provide connections to bikeways identified on the comprehensive transportation plan or other adopted plan.
Bicycle lanes must be constructed as follows:
a. Bicycle lanes, where required, must be at least four feet wide and placed in the outside lane of a roadway, adjacent to the curb and gutter or shoulder. Curb and gutter areas may not be counted in calculating the width of a bicycle lane. When onstreet parking is permitted, bicycle lanes must be at least four feet in
width and located between the parking lane and the outer travel lane.
Bicycle pavement widths are in addition to the minimum pavement width required for the road.
b. Bicycle lanes must be delineated with signs and striping consistent with the latest edition of the manual for uniform traffic control devices, and approved by the community development director.
c. Bikeways and bicycle lanes must be constructed in accordance with the most recent specifications set forth in American Association of State Highway and Transportation Officials (AASHTO) guidelines.
d. The design, striping and sign system for bicycle lanes must be coordinated with that of the vehicular road system to provide a safe and
continuous route for bicycles. Deceleration lanes must be striped so that bicycles can safely remain in a
lane marked between the deceleration lane and the through traffic lane.
(10) No wall, fence, sign or other structure may obstruct passage along a sidewalk or bicycle lane.
(i) Parking on right-of-way.
(1) For residential projects constructed under the provisions of the zoning ordinance as single-family attached residential projects, wherein title to the singlefamily unit is held by fee simple ownership, the city may assume maintenance responsibility one year after the release of the subdivision bonds for parking constructed on public rights-of-way, in accordance with minimum city standards. A special parking maintenance district, as authorized by Georgia Constitution article IX, § II, ¶ VI, comprised of all property within such single-family
attached residential subdivision, may be established by resolution of city council for the maintenance of such parking constructed on the public right-of-way at the time the subdivision plat is finally recorded, provided the plat is so noted.
(2) Final subdivision plats for single-family attached residential projects must have the following notation when a special district is to be established for city maintenance of parking within the public rightof-way:
"All single-family residential lots on this plat are included in a special taxing district for funding the maintenance of parking provided in the development."
(3) If the city creates a special parking district, as authorized by Georgia Constitution article IX, § II, ¶ VI, revenue to fund city parking maintenance will be obtained by an ad valorem tax levied on all properties within such parking district.
Such ad valorem millage will be set annually by the city council when other ad valorem millage rates are set. No assessment will be made in a special parking district in the calendar year in which it is
established.
(j) Underground utilities. All utilities are required to be placed underground unless the community development director determines that
underground utilities are infeasible due to shallow rock, high water table, or other similar geologic or hydrologic conditions.
(k) Streetlights. Streetlights consistent with Georgia Power specifications are required in all new subdivisions of two or more lots except where no utility improvements are required by this chapter. Streetlights must be provided on the same side of the street as sidewalks.
Historia
(Ord. No. 2013-10-14, 1(Exh. A § 16-15.40), 10-14-2013; Ord. No. 2015-01-04, § 1, 1-26- 2015)