Sec. 32.26. Standards for Development Within

Sobre este texto

  • As published by Municode, retrieved 2026-11-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

Future Conditions Floodplain.

Any development within the future-conditions floodplain allowed under Section 32.25 above, if permitted, shall meet the following conditions:

(a) Compensation for storage capacity shall occur between the average ground water table elevation and the base flood elevation for

the base flood, and between the average ground water table elevation and the futurecondition flood elevation for the future-conditions flood, and lie either within the boundaries of ownership of the property being developed and shall be within the immediate

vicinity of the location of the encroachment.

Acceptable means of providing required compensation include lowering of natural ground elevations within the floodplain, or lowering

of adjoining land areas to create additional floodplain storage. In no case shall any required compensation be provided via bottom storage or by excavating below the elevation

of the top of the natural (pre-development) stream channel unless such excavation results from the widening or relocation of the stream channel;

(b) Cut areas shall be stabilized and graded to a slope of no less than 2.0 percent;

(c) Effective transitions shall be provided such that flow velocities occurring on both upstream and downstream properties are not increased or decreased;

(d) Verification of no-rise conditions (0.01 foot or less), flood storage volumes, and flow characteristics shall be provided via a stepbackwater analysis meeting the requirements of this Article;

(e) Public utilities and facilities, such as water, sanitary sewer, gas, and electrical systems, shall be located and constructed to minimize or eliminate infiltration or contamination from flood waters; and

(f) Any significant physical changes to the base flood floodplain shall be submitted as a Conditional Letter of Map Revision (CLOMR) or Conditional Letter of Map Amendment

(CLOMA), whichever is applicable. The CLOMR submittal shall be subject to approval by the Zoning Administrator using the Community Consent forms before forwarding the submittal package to FEMA for final approval. The responsibility for forwarding

the CLOMR to FEMA and for obtaining the CLOMR approval shall be the responsibility of the applicant. Within six months of the completion of construction, the applicant shall submit as-built surveys for a final Letter of Map Revision (LOMR).

Historia

La línea de historia que la fuente imprime al final de la sección.

(Ord. No. 578, § 1, 8-1-2019)

Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:flowery-branch/zoning/32.26@2026-11-11-98f708ebc6

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Flowery Branch Zoning Ordinance, Sec. 32.26. Standards for Development Within | Georgia Commons