Fort Oglethorpe · Ordenanza de zonificación
Appendix A - UNIFIED DEVELOPMENT CODE / Chapter 7 - INFRASTRUCTURE IMPROVEMENTS / Article 4 - STREET CONSTRUCTION STANDARDS
Sec. 4.4. Fill and embankments.
Sobre este texto
- As published by Municode, current through 2026-03-26
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.
(a) Any roadway embankment steeper than a three to one (3:1) slope shall be specially designed by a geotechnical engineer and then built to design specifications.
(b) The embankment shall be protected from erosion using stormwater best management practices.
(c) Areas requiring two feet or more of fill shall be observed and tested by the geotechnical engineer.
(1) Fill shall be placed in level lifts, thickness of loose lifts shall not exceed eight inches, and compacted to at least 95 percent of the standard proctor maximum dry density, with the final 12 inches compacted to 98 percent of a standard proctor maximum dry density.
(2) The moisture content shall be within three percent of the optimum moisture content.
(3) The geotechnical engineer shall conduct field density tests for each one-foot layer of fill placed.
a. Testing frequency shall be at least one test per 10,000 square feet, or one test every 200 feet along the roadway centerline, staggered left and right of the centerline.
b. A minimum of three tests is required for each one-foot layer.
c. Any areas that do not meet compaction requirements shall be re-compacted and retested.
Historia
(Ord. No. 2021-10, § 1, 6-28-2021)
Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.