Appendix A - UNIFIED DEVELOPMENT CODE / Chapter 7 - INFRASTRUCTURE IMPROVEMENTS / Article 4 - STREET CONSTRUCTION STANDARDS

Sec. 4.5. Base.

Sobre este texto

  • As published by Municode, current through 2026-03-26
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

(a) All contractors must contact the geotechnical engineer prior to beginning the base operation. This is imperative or the work may not be accepted.

(b) Before placing base material, the subgrade shall be proof-rolled in the presence of the geotechnical engineer.

(1) Proof-rolling shall be performed using a fully-loaded, dual-tandem dump truck.

(2) The subgrade shall be trafficked by parallel passes of the truck starting at one side of the roadway. Each pass shall overlap the preceding pass to ensure complete coverage of the roadway cross-section.

(3) Two complete proof-rolling coverages are required.

(4) Any areas that deflect or yield, in the opinion of the geotechnical engineer, shall be corrected before base material is placed.

(c) Base material shall be a dense-graded mineral aggregate base meeting the requirements of the Georgia Department of Transportation Section 815 of the "Standard Specifications Construction of Transportation Systems" for graded aggregate base.

(1) The contractor shall provide a letter of certification from the base material supplier that the materials meet these requirements.

(2) Other types of base material may be used, if included in a design by a professional engineer and approved by the geotechnical engineer and the director of public works.

(3) The base material shall be compacted to at least 98 percent of the standard proctor maximum dry density.

(d) The base will be tested for thickness and compaction by the geotechnical engineer.

Tests will be conducted at a maximum spacing of 200 feet, staggered right and left of the centerline.

(e) Tolerances for base thickness.

(1) The minimum base design thickness shall be six inches.

(2) The average of all measurements shall be greater than or equal to the design thickness.

(3) Any test that is less than the design thickness, but no more than 0.5 inches less than the design thickness, may be evaluated by the geotechnical engineer for acceptance or for corrective actions.

(4) Any test that is more than 0.5 inches below the design thickness will require corrective actions.

Historia

La línea de historia que la fuente imprime al final de la sección.

(Ord. No. 2021-10, § 1, 6-28-2021)

Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:fort-oglethorpe/zoning/appendix-a-chapter-7-article-4-4.5@2026-03-26-d55d3329eb

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Fort Oglethorpe Zoning Ordinance, Sec. 4.5 (Appendix A, Chapter 7, Article 4). Base | Georgia Commons