Article 6. CONSTRUCTION SCHEDULE

Sobre este texto

  • As published by Municode, current through 2026-03-26
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

(a) No construction activity of any kind, including grading, installation of improvements shall begin on any land within the jurisdiction of these regulations without prior approval of the construction plans.

(b) Grading or land disturbing activities may commence only after a land disturbance permit has been issued.

(c) Utility installation shall not occur until the public works department has approved the rough grade of the street and shoulder.

(d) Periodic inspection during the installation of the required improvements in a development may be made by the public works department to ensure conformity with the approved plans and specifications. Such inspections will be made at the following stages of construction:

(1) At the completion of clearing and stump removal.

(2) Beginning of grading operation to ensure proper compaction.

(3) During the installation of storm sewer cross drains.

(4) During the construction of curb and gutter, lateral storm drains, and storm drainage structures.

(5) Beginning of subgrade preparation and after subgrade preparation.

(6) Beginning of base installation and at the completion of base installation.

(7) Beginning of asphalt installation.

(8) At the completion of all grading and stabilization of shoulders through the following methods:

a. Hydroseeding.

b. Wheat/Rye straw at 75 percent minimum coverage.

c. Wood mulch at a minimum of six inches thick.

d. Sod.

(9) During the life of the project for proper erosion and sedimentation control.

Historia

La línea de historia que la fuente imprime al final de la sección.

(Ord. No. 2021-10, § 1, 6-28-2021)

Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:fort-oglethorpe/zoning/article-6@2026-03-26-607429caca

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Fort Oglethorpe Zoning Ordinance, Article 6. CONSTRUCTION SCHEDULE | Georgia Commons