10.4.7. Stream Buffer and Setback Requirements

Sobre este texto

  • As published by Municode, current through 2026-05-28
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

All land development activity subject to this section shall meet the following requirements:

A. An undisturbed natural vegetative buffer shall be maintained for 50 feet, measured horizontally, on both banks (as applicable) of the stream as measured from the top

of the stream bank. This buffer shall not be altered or reduced by any method in

this section.

B. An additional setback shall be maintained beyond the natural vegetative buffer, in which all impervious cover shall be

prohibited. Stormwater management structures shall be allowed within this setback however, all other grading, filling and earthmoving shall be minimized.

The setback shall be either of the following dimensions:

1. For a uniform distance of 25 feet, measured horizontally, from the undisturbed natural vegetative buffer boundary.

2. For a variable distance, measured horizontally, from the undisturbed natural vegetative buffer boundary, provided that the total area encompassed by this impervious setback on the land development activity is equal to, or greater than, the total area that would be encompassed by the uniform distance of 25 feet.

C. On properties between 10 acres and 49.9 acres, the impervious setback area may

be reduced such that the sum of the undisturbed buffer area and the impervious setback area do not exceed 12 percent of the total property area of the development activity. However, in no case shall the 50-foot undisturbed buffer be reduced or altered to achieve this percentage.

D. On properties of 50 acres or larger, the impervious setback area may be reduced

such that the sum of the undisturbed buffer area and the impervious setback area do not exceed eight percent of the total property area of the development activity. However, in no case shall the 50-foot undisturbed buffer be reduced or altered to achieve this percentage.

E. No septic tanks or septic tank drain fields shall be permitted within the buffer or the setback, except that existing septic systems constructed prior to the effective date of this section may be maintained or replaced, but not enlarged within the

required buffer and setback area.

F. For water supply watershed districts subject to the requirements of Sec. 6.5 of this UDC, the minimum stream buffer

setbacks shall be the greater of the applicable requirements of this section or those in Sec. 6.5.

Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:hall-county/zoning/10.4.7@2026-05-28-5e78958a40

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Hall County Zoning Ordinance, 10.4.7. Stream Buffer and Setback Requirements | Georgia Commons