Hawkinsville · Ordenanza de zonificación
Appendix A - UNIFIED LAND DEVELOPMENT REGULATIONS / Article VI - PLANS AND PROCEDURES / Division 8 - BUILDING CONSTRUCTION
Sec. 6.8.3. Construction in flood area.
Sobre este texto
- As published by Municode, retrieved 2026-11-11
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.
Construction of a building for which a flood area permit was issued as part of a development permit shall be governed by the following:
a. Upon placement of the lowest floor, or floodproofing by whatever construction means, or upon placement of the horizontal structural members of the lowest floor, whichever is applicable, it shall be the duty of the development permit holder to submit to the Building Inspector a certification of the elevation of the lowest floor, floodproofed elevation, or the elevation of the lowest portion of the horizontal structural members of the lowest floor, whichever is applicable, as built, in relation to mean sea level.
b. Certification shall be prepared by or under the direct supervision of a registered land surveyor or professional engineer and certified by such registered land surveyor or professional engineer. When floodproofing is utilized for a particular building, the certification shall be prepared by or under the direct supervision of a professional engineer or architect and certified by the professional engineer or architect.
c. Any work undertaken prior to submission of the certification shall be at the development permit holder's risk.
d. The Building Inspector shall review the floor elevation survey data submitted.
Deficiencies detected by such review shall be corrected by the development permit holder immediately and prior to further progressive work being permitted to proceed.
Failure to submit the survey or failure to make the corrections shall be cause to issue a stop-work order for the project.
Historia
(Ord. of 5-10-96)
Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.