Sec. 22-97. Fees.

Sobre este texto

  • As published by Municode, retrieved 2026-11-23
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

(a) Payment. A permit shall not be issued under this article until the fees prescribed by the board of commissioners have been paid, nor shall an amendment to a permit be released until the additional fee, if any, due to an increase in the estimated cost of the building, structure or electrical, plumbing, mechanical or gas system, etc., has been paid.

(b) Penalty for commencing work before obtaining permit. Any person who commences any work on a building, structure or electrical, gas, mechanical, plumbing, etc., system before obtaining the necessary permits shall be subject to a penalty of 100 percent of the usual permit fee in addition to the required permit fees.

(c) Records. The building official shall keep a permanent and accurate accounting of all permit fees and other money collected and the names of all persons upon whose account the fee or other money was paid, along with the date and amount thereof.

(d) Amount of fees. For all buildings, structures, and electrical, plumbing, mechanical, and gas systems, or alterations requiring a permit, a fee for each permit, in amounts as established and amended from time to time by the building official, upon the written approval of the chairman of the board of commissioners and the chief of operations, shall be paid at the time of filing application for such permit; provided, however, that the amount of such fees shall be presented within the annual budget approved by the board of commissioners. In the event that the position of building official is vacant, the amount of the fees may be established and amended from time to time by the chief of operations, upon the written approval of the chairman of the board of commissioners; provided, however, that the amount of such fees shall be presented within the annual budget approved by the board of commissioners.

(e) Valuations. If, in the opinion of the building official, the valuation of a building, alteration, structure, or electrical, gas, mechanical or plumbing system appears to be underestimated on the application, the permit shall be denied, unless the applicant can show detailed estimates to meet the approval of the building official. Permit valuations shall include the total cost, including electrical, gas, mechanical, plumbing equipment and other systems, including materials and labor.

Historia

La línea de historia que la fuente imprime al final de la sección.

(Ord. of 11-25-1997(2), att. A, § 3.7; Ord. of 5-10-2005)

Leer este código donde se publica (Municode) La fuente es el código del condado tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:barrow-county/code/22-97@2026-11-23-fb94c8d1cd

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Barrow County Code of Ordinances, Sec. 22-97. Fees | Georgia Commons