Sec. 86-126. Dams.

Sobre este texto

  • As published by Municode, current through 2025-05-06
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

(a) Any land disturbing activity that involves a property that is proposed to contain a dam shall comply with the provisions of these regulations.

(1) New dams which become subject to the requirements of the Georgia Safe Dams Act and Rules for Dam Safety, which are proposed to be 25' or more in height or proposed to have an impounding capacity of 100 acre-feet or more at maximum water storage elevation or otherwise defined by the Georgia Safe Dams Act shall be subject to the following:

If a developer proposes the construction of any new dam where development exists within the proposed breach zone, the new dam shall be subject to the requirements of the Georgia Safe Dams Act and Rules for Dam Safety adopted by the state department of natural resources. The developer shall obtain necessary approvals and permits from the environmental protection division of the state department of natural resources for the project and the dam prior to securing a land disturbance permit from the department. If no development exists within the proposed breach zone, the developer shall submit four copies of the construction plans to the department for review prior to securing a land disturbance permit.

(2) If the developer elects to construct the new dam in accordance with the design standards for new dams as contained in the Rules of Dam Safety, then new development shall be permitted within the dam breach zone. If, however, development currently exists or is proposed in the dam breach zone, the dam shall meet the design standards for new dams as contained in the Rules for Dam Safety.

(3) If the developer elects not to construct the new dam to the design standards for new dams as contained in the Rules for Dam Safety, then four copies of a dam breach analysis for the dam shall be submitted along with four copies of the construction plans for review prior to securing a land disturbance permit from the department. The design engineer shall utilize the computer model entitled "DAMBRK" or approved equivalent thereof for the dam breach analysis.

(4) Should the new dam not meet the design standards for new dams as contained in the Rules for Dam Safety, then only the following uses and structures shall be permitted within the dam breach easement:

a. Agriculture that requires no structures for human habitation within the dam breach zone including forestry, livestock raising, and agricultural and forestry access roads.

b. Fences.

c. Outdoor advertising signs provided the signs meet the minimum requirements as specified under the county sign ordinance (chapter 78).

d. Roads, driveways and parking areas.

e. Utility poles, towers, pipelines, water treatment outfalls and facilities, or other similar facilities and structures.

(5) For any new dam proposed that does not to meet the design for new dams as contained in the Rules for Dam Safety, the developer shall obtain a dam breach easement, recorded with the Clerk of Superior Court, from any off-site property owner where it is proposed for the dam breach zone to extend off the property where the dam is being constructed.

(6) The developer shall also cause a dam breach easement to be recorded upon the property being developed.

(7) Prior to recording of a final plat or at completion of a building foundation, as appropriate, an as-built certification from a registered professional engineer shall be submitted to the department. The certification shall state that the dam is constructed in accordance with the provisions of these regulations as well as the authorized construction plans.

(8) The dam owner(s) shall provide the name and address of the person or persons owning the dam, the person having direct responsibility for the operation of the dam, and a plan for inspection and maintenance to be put into effect by the owner(s) or operator of the dam.

(b) Quality assurance plan. Because of the safe dams program, when an existing category II dam is reclassified to a category I dam because of proposed development downstream of the dam, the developer shall provide for review to the state the following information:

(1) Location of the category II dam and the proposed development; and

(2) A surveyed cross-section as required by the Georgia Safe Dams Act of the stream valley at the location of the proposed development including proposed finished floor elevations; and

(3) A dam breach analysis using the dambreak computer model to establish the height of the floodwave in the downstream floodplain. The dambreak modeling shall be completed in accordance with the safe dams program quality assurance program by a qualified registered engineer.

(4) Inventory information regarding the category II dams within the county may be obtained through the Georgia Safe Dams Program.

Historia

La línea de historia que la fuente imprime al final de la sección.

(Ord. of 10-16-01, § 1)

Leer este código donde se publica (Municode) La fuente es el código del condado tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:carroll-county/code/86-126@2025-05-06-c75bf1fd76

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Carroll County Code of Ordinances, Sec. 86-126. Dams | Georgia Commons