Sec. 50-106. Exemptions from stormwater management standards.

Sobre este texto

  • As published by Municode, current through 2025-11-20
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

The following development activities are exempt from the provisions of this article and the requirements of providing stormwater management:

(1) Land disturbing activity conducted by local, state, authority, or federal agencies, solely to respond to an emergency need to protect life, limb, or property or conduct emergency repairs;

(2) Land disturbing activity that consists solely of cutting a trench for utility work and related pavement placement.

(3) Land disturbing activity conducted by local, state, authority, or federal agencies, whose sole purpose is to implement stormwater management or environmental restoration.

(4) Residential developments consisting of singlefamily dwellings, each on a lot of 80,000 square feet or more, so long as the total

impervious area on each lot is less than 5,000 square feet.

(5) Repairs to any stormwater management facility or practice deemed necessary by the county manager;

(6) Agricultural practices as described O.C.G.A.

12-7-17(5) within areas zoned for these activities with the exception of buildings or permanent structures that exceed the

threshold in section 50-105(b)(1) or (2);

(7) Silvicultural land management activities as described O.C.G.A. 12-7-17(6) within areas zoned for these activities with exception of buildings or permanent structures that exceed the threshold in section 50-105(b)(1) or (2)

(8) Installation or modifications to existing structures solely to implement Americans with Disabilities Act (ADA) requirements, including but not limited to elevator shafts, handicapped ramps and parking, and enlarged entrances or exits; and

(9) Linear transportation projects being constructed by the county to the extent the administrator determines that the stormwater management standards may be infeasible to apply, all or in part, for any portion of the

linear transportation project. For this exemption to apply, an infeasibility report that is compliant with the county linear feasibility

program shall first be submitted to the administrator that contains adequate documentation to support the evaluation for the applicable portion(s) and any resulting infeasibility determination, if any, by the administrator.

Historia

La línea de historia que la fuente imprime al final de la sección.

(Ord. of 9-28-93; Code 1977, § 3-22.5A-5; Ord. of 4-13-04; Amd. of 2-9-21)

Leer este código donde se publica (Municode) La fuente es el código del condado tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:cobb-county/code/50-106@2025-11-20-316fd97fa1

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Cobb County Code of Ordinances, Sec. 50-106. Exemptions from stormwater management standards | Georgia Commons