(a) General requirements. Subdivision plans receive their second official consideration as improvement plans. These improvement plans shall be approved by the county engineer and road superintendent who shall certify that the improvement plans are in conformance with this chapter, official county specifications, and with the requirements of the approved preliminary plan. No developer shall proceed with any construction work in the proposed subdivision before obtaining this approval from the road superintendent and/or county engineer, which must be in writing.
(b) Professional engineer required. Should certain design calculations be required to resolve flow problems, possible erosion or drainage problems, or other detailed engineering problems which might be encountered in the process of preparing the required improvement plan, the county engineer shall be authorized to require the developer to obtain services of a qualified registered land surveyor or a professional engineer in the improvement plan design process.
Should such services be required, such plans shall reflect his registration. All professional surveying or engineering service costs shall be the sole responsibility of the applicant.
(c) Filing. To secure formal review and approval of his improvement plans, the developer shall file with the building and zoning official three certified (signed and sealed by the developer's registered surveyor or professional engineer) white background prints of the improvement plans, the building and zoning official will then distribute the improvement plans to the county engineer and road superintendent who shall jointly review the proposed improvement plans and shall approve or deny the proposed improvement plans. The building and zoning official shall notify the planning commission of the action in writing. The review of the improvement plan shall include the review of plans for compliance with the county erosion and sedimentation control chapter, as amended.
(1) Approval means the developer is now authorized to proceed with the physical improvements in the subdivision, after securing any required construction permits, and may proceed with the preparation of the final subdivision plat.
(2) Conditional approval means the developer may proceed as outlined in subsection (c)(1) of this section, but only after he submits three certified copies of the corrected improvement plans to the county engineer and road superintendent of their review and approval.
(3) Denial means disapproval of the improvement plans. For further consideration, the developer must rework his plans to conform to the requirements of this chapter, and then submit the reworked plans to the building and zoning official as though they were a completely new set of plans.
(d) Plans and data required for submission. The plans for the required minimum improvements shall be prepared and approved by the county engineer and road superintendent prior to construction and only after approval of the preliminary plan. Such improvement plans shall show the proposed locations, sizes, types, grades and general design features of each facility or improvement, and shall be based on reliable field data. Improvement plan approvals are good for 24 months. If the subdivision is sold prior to completion and final platting, a mandatory review by the county engineer and road superintendent is required. Failure to comply may result in revocation of construction permit after notice and hearing before the planning commission. The developer shall receive a minimum of ten days' written notice of the hearing.
The improvement construction drawing shall be submitted on white background prints. The sheet size shall be 24 inches by 36 inches unless another size is approved by the county engineer. The drawing shall include the following information:
(1) Construction plans. The developer shall provide the plan and profile of each proposed street (indicating the existing ground surface elevation and proposed street grade surface elevation including extensions for a distance of 100 feet to 300 feet beyond the tract boundary) as required by the county engineer. Design shall be in accordance with good engineering practices.
(2) Street; typical sections. A typical section of each proposed street shall be submitted, showing the width of pavement and the rights-of-way.
(3) Water supply and stormwater drainage. The plan and profile of proposed utility distribution systems and storm drainage sewers or other drainageways, with grade and sizes indicated, is required. Stormwater drainage shall be consistent with applicable county or city ordinances and other applicable governmental agencies.
Water and sewer systems shall be approved by the local jurisdiction providing services and all relevant state agencies. Final approval of the improvement plans shall not be made until the developer submits to the county engineer all final permits required for the construction of all improvements from other state, local jurisdictions providing utility services or federal agencies.
(4) Utility service agreement. A developer's agreement for utilities service shall be required before final development plan approval is granted.
(5) Other public improvements. A plan shall be prepared for parks, recreation or other public use areas and improvements if included in the approved preliminary plan.
(6) As-built plans. The designing surveyor or engineer shall submit to the county engineer three sets of white background prints of certified as-built plans prior to recording of the final plat.
(e) Approval of construction drawings; time duration. Upon approval of the preliminary plat and before preparation of the final construction drawings for the minimum improvements required by this chapter, the subdivider shall receive conditional approval of such engineering plans from the county engineer as follows:
(1) The design of all minimum improvements shall be under the direction of a registered professional engineer or registered land surveyor in the state, with all plans bearing his professional seal;
(2) A letter of approval shall accompany all water and sewer plans from the county health department or the appropriate municipal utility official, if applicable;
(3) If construction has not commenced within one year of the construction plan approval, such approval shall become invalid, at which time a new preliminary plan must be submitted per current regulations at the time of resubmission.