Coweta County · Código de ordenanzas

Part II - CODE OF ORDINANCES / Chapter 78 - UTILITIES

Sec. 78-3. Pre-construction application procedures.

Sobre este texto

  • As published by Municode, current through 2026-05-19
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

(a) Administration. The director of the Coweta County Public Works Department shall have the authority to administer the requirements, standards and restrictions of this chapter within county road rights-of-way, and in accordance with any requirements, standards and restrictions that the Coweta County Public Works Department may establish thereafter.

(b) Permit fees. The director of Public Works of Coweta County shall be authorized to charge permit fees to applicable utility companies proposing utility work within county rights-of-way. The amount (and any future changes) of the utility installation/right-of-way encroachment permit fee shall be approved by the Coweta County Board of Commissioners.

Fees may be waived for work conducted on behalf of municipal or governmental utilities.

(c) Application for permit, notifications, and exemptions.

(1) Utility work, with the exception of emergency repair work, within Coweta County rights-of-way, shall require a completed utility permit application and scaled drawings showing the location and scope of the work. Only utility companies may obtain permits. Any contractor(s) and subcontractor(s) must be identified on the permit application. 24-hour contact information shall be provided for each contractor or subcontractor that is proposed to perform work within the county rights-of-way.

Utility work in a Coweta County right-of-way without a permit, for any type of work for which a permit is required, shall be a violation of this article. Performance of work within the county rights-of-way prior to approval of the permit by the public works department shall be a violation of this article. Exempt activities, as specified in section (e) require neither a utility permit nor written notification.

(2) The Coweta County Public Works Department has written procedures for applying for a utility permit, and for providing advance notification. Such procedures are incorporated herein by reference, and are available from the department, along with necessary forms. The department may require such information as it deems necessary prior to issuance of a utility permit.

(d) Utility permits required. Utility permits shall be required in the following situations:

(1) Installation of new utilities within county rights-of-way for new commercial, residential or industrial developments, or subdivisions.

(2) Work involving underground burial of utilities and overhead placement of lines along or across county roadways.

(3) Any new utility pole installation or replacement, unless such replacement is necessary to complete emergency-related damage.

(4) Utility tie-ins or work that require cutting any roadway pavement. Alternate routes, configurations, or locations for tie-ins that would prevent, eliminate, or minimize the need for a pavement cut must be utilized, when possible.

(5) Work that requires blocking any portion of a travel lane for a period of time exceeding 15 minutes.

(e) Exemptions. The following activities shall not require a utility permit or written notification, provided they do not also include any activity specifically listed as requiring a utility permit or written notification:

(1) Routine or periodic maintenance, inspection, and/or testing of utilities (including replacement of parts necessary due to damage, deterioration or obsolescence) that would not:

a. Require blocking any portion of a travel lane for more than 15 minutes in one day; or

b. Require excavation of more than cubic yard of soil or earthen embankment.

(2) Installation of additional appurtenances or attachments to existing facilities that would not:

a. Affect vertical or horizontal clearances from the traveled way:

b. Change the rated capacity or transmittance of the facility for which a permit was issued;

c. Required blocking any portion of a travel lane for more than 15 minutes in one day; or

d. Require excavation of more than � cubic yard of soil or earthen embankment.

(3) Potholing for utility locates beyond the edges of pavement, meaning excavating small holes no larger than 18 inches square, by hand or using vacuum excavation. Such holes must be filled in before the end of each workday.

(4) Utility damage repairs.

(5) Utility work being performed in a new development within the construction limits of the new development prior to the development's roads, rights-of-way, and easements being deeded to the public works department.

(6) Emergency damage repairs.

Historia

La línea de historia que la fuente imprime al final de la sección.

(Ord. No. 009-26, 4-21-26)

Leer este código donde se publica (Municode) La fuente es el código del condado tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:coweta-county/code/78-3@2026-05-19-0fc8d33293