(a) All utilities locating their facilities in new residential, commercial, and industrial developments shall locate their facilities pursuant to all applicable Coweta County development standards and specifications, and as those may be amended from time to time.
All work authorized by any permit issued under this article shall be in accordance with all applicable Coweta County specifications and requirements. All utility work within Coweta County rights-of-way shall comply with the provisions of this article.
(b) Prohibited activities. The use of pneumatic boring equipment for utility installations beneath paved county roadways is prohibited. The cutting or removal of curb and gutter or pavement is prohibited unless such work is explicitly noted or shown in the permit application and/or plans for work.
(c) Repairs and corrective work. Repairs to Coweta County rights-of-way and any roadway components, including drainage pipes, drainage structures, pavement, or appurtenant roadway items shall be performed or reconstructed in accordance with Coweta County Public Works Department requirements. Though the public works department does not have jurisdiction over private streets or drives in Coweta County, the utility company and its contractor(s) shall be responsible for rectifying any disturbance or damage related to the utility work that may occur incidentally beyond the rights-of-way of Coweta County to a minimum standard equal to existing conditions prior to construction activities (sod for sod, concrete for concrete, etc.). Utility companies and their contractors shall first make every effort to avoid disturbance or damage to private property wherever possible during construction activities. Utility companies and their contractors, failing to fully repair disturbances or damages on private property within a specified timeframe determined by the Coweta County Public Works Department, may be denied future permit approval.
(d) Safety procedures; securing the work site. The use of the right-of-way shall be minimized to the greatest possible extent. No materials or equipment shall be stored on the right-of-way or along the roadway that interferes with the normal operation of traffic. No work shall restrict the sight distances for motorist exiting adjacent streets or driveways unless a flagman is provided. The use of flagmen is required on all road and right-of-way utility work involving partial or full blockages of travel lanes. Closure of lanes and traffic control to provide for the protection of the work crews shall be conducted in accordance with the current edition of the Manual on Uniform Traffic Control Devices. Debris shall not be placed on the right-of-way but will be hauled away as the excavation occurs. All trenches opened each day must be backfilled and compacted to 95 percent standard proctor using appropriate tamping or vibratory equipment unless otherwise approved by the public works department. The public works department reserves the right to require compaction testing from the utility, at the utility's expense, for any work involving cutting, trenching, or backfilling in the roadbed. All work areas must be secured at the end of each workday to protect the general public that may enter the work area. In the event that steel plates are utilized in areas of pavement, the plates must be secured prior to opening the paved area to traffic. Plates must be secured so that there is no possibility that the plates can move or shift because of traffic flow.
(e) Indemnification. The utility receiving the permit and the utility's contractor and/or subcontractors shall indemnify and hold harmless Coweta County, the public works department and all Coweta County employees and agents from any and all liability resulting from any work performed under the permit. The utility shall also indemnify the county from any claims, suits or causes of action resulting from any work under the permit. Such indemnification shall include the costs of attorneys' fees and litigation expenses to enforce this indemnification provision.
(f) Warranty. The utility shall provide a one year warranty for any work conducted under authority of this article, including any new installation and any repair work. The one-year warranty shall commence upon the completion of the work. The utility shall repair any defects in the work or repair or correct any deficiencies that are not up to the standards and regulations of the public works department.
(g) Surety shall be required for work under this article, as specified herein, to ensure satisfactory completion and performance of any necessary repairs in accordance with the requirements of Coweta County Public Works. Surety shall be in the form of a performance and/or maintenance bond, certified check, or irrevocable letter of credit.
(1) Form. The surety shall only be issued in a form approved by Coweta County. The language of the surety and the term of the surety must be approved by Coweta County prior to issuance. Coweta County has forms it prefers that surety companies use, and those can be provided upon request; otherwise, the form of the surety shall be approved by the county prior to acceptance of the surety. Any surety bond shall be issued by a company or financial institution authorized to do business in the state of Georgia. Escrow shall mean deposit of good funds in a bank of Coweta County's choosing pursuant to escrow instructions issued by Coweta County.
(2) Amount. Surety shall be in an amount determined by the public works department based on the size of the project. The public works department may use its discretion when setting the amount of the bond and should consider potential damage to public property or facilities and the relationship to the cost of installation, as well as the factors used in determining whether a project is complex.
(3) Prerequisite; calling surety. No permit shall be issued by the public works department until the surety has been furnished to the county, in a form acceptable to the county. If the utility or the utility contractor does not comply with these regulations, other applicable Coweta County ordinances and regulations, or with the conditions of the permit after issuance, the county may call the surety, or any part thereof, to be forfeited and may use the proceeds to complete the work or hire a contractor to remedy the defects.
(4) Waiver. The public works department shall be authorized, but not required, to reduce or waive the surety requirement for projects undertaken by a municipal government in the county.
(5) Transfer. Any surety shall be transferable from one site to another within this county. When a permit is secured for right-of-way utility work at a new site, if the party seeking the permit is no longer conducting work on any other site, the surety may be transferred to the new site.
(6) Multiple sites. Any party applying for a permit under this chapter and working multiple sites shall file a surety in the proper amount for each site or in an amount to cover multiple sites, said surety shall be made payable to the Coweta County Board of Commissioners and release of surety is conditioned upon the successful completion of operations with a satisfactory examination of all county maintained roads and rights-of-way used during the performance of operations.
(7) Effect. The surety shall remain in effect following the cessation of operation until the public works director has made an inspection of the permitted site and certified that the operator has complied with all of the requirements of this chapter. The board of commissioners of Coweta County may draw on said surety at any time upon certification by the public works director that:
a. Damage or wear and tear to county maintained pavements, roadbeds, rights of-way, bridges, signage, or property of any type has been detected that is clearly attributable to operations covered under this chapter and under the operator's specific permit;
b. Utility or contractor has been notified of any such damage and has been requested to replace or repair damaged property;
c. Utility or contractor has failed to commence repair or replacement of damaged property within ten days of notice from the public works director that such damage has occurred or been discovered.
(h) Insurance. All utilities operating in Coweta County rights-of-way shall also provide proof of liability insurance in a sufficient amount of coverage that shall also cover the actions of the contracts and subcontractors. In lieu of the foregoing, the utility may self-insure for the above-referenced coverage. The utility shall present valid proof of self-insurance upon the public works department's request. The utility shall also require equivalent insurance from their contractors or subcontractors.
Historia
(Ord. No. 009-26, 4-21-26)
Leer este código donde se publica (Municode) La fuente es el código del condado tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.