Sec. 14-45. Minimum distances from curb and street centerline of underground lines and poles.

Sobre este texto

  • As published by Municode, current through 2026-03-31
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

(a) Gas. All gas lines must be installed at a minimum of thirty-six (36) inches from the curb and seventeen (17) feet from the centerline of a county road, highway, street, etc., and must be installed a minimum of eighteen (18) inches from any other public utility line, pipe, etc.

(b) Water. All waterlines must be installed a minimum of sixty (60) inches from the curb or eighteen and one-half (18.5) feet from the centerline of any county road, highway, street, etc., and must be installed a minimum of eighteen (18) inches from any other public utility line, pipe, etc.

(c) Telephone. All telephone lines must be installed a minimum of eighteen (18) inches from the curb or fifteen and one-half (15.5) feet from the centerline of a county road, highway, street, etc., and must be installed a minimum of twelve

(12) inches from any other public utility line, pipe, etc.

(d) Electrical. All electrical lines must be installed a minimum of ninety-six (96) inches from the curb or twenty-two (22) feet from the centerline of any county road, highway, street, etc., and must be installed a minimum of twentyfour (24) inches from any other public utility line, pipe, etc.

(e) Cable television. All cable television lines must be installed a minimum of six (6) inches from the curb or fourteen and one-half (14.5) feet from the centerline of any county road, highway, street, etc., and must be installed a minimum of twelve (12) inches from any other public utility line, pipe, etc.

(f) Sanitary sewer. All sanitary sewer main lines must be installed a minimum of six (6) feet deep in any county right-of-way. All sanitary sewer service lines must be a minimum of five (5) feet deep in any county right-of-way.

(g) Poles. All poles for overhead utilities must be installed with pole centerline a minimum of twenty (20) feet from the centerline of any county road, highway, street, etc.

(h) Small wireless facilities. CSP equipment and connecting lines must be located at a depth and within a distance from the centerline of any county street so as to be consistent with the standards set forth in section 14-105 and so as to prevent conflict with any other allocated above or underground facilities.

Historia

La línea de historia que la fuente imprime al final de la sección.

(Ord. of 9-17-19, § 1(Exh. A))

Leer este código donde se publica (Municode) La fuente es el código del condado tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:douglas-county/code/14-45@2026-03-31-e3bb33da65

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.