Jackson County · Código de ordenanzas
Jackson County Code of Ordinances
Este documento se muestra completo, como un solo texto: su fuente no lo divide en secciones.
Sobre este texto
- As published by Municode, current through 2025-06-16
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.
Parte 7 de 10. Este texto es largo, así que su página lo muestra en partes, en el orden de la fuente. Un enlace a uno de sus párrafos lleva a la parte que lo contiene.
(c) Grading. Upon completion of street grading, if applicable, inspection and approval shall be required prior to trenching or continuation with subgrade preparation.
(d) Street curbing and gutter (if provided). After grading is completed and approved, the curb lines shall be staked by the developer's registered land surveyor. Inspection shall be requested after the subgrade is compacted and forms or string line have been set. Street width and vertical and horizontal alignment may be spot checked.
(e) Sub-grade of streets. After the earth work has been completed, all storm drainage and other underground utilities have been installed under the roadbed, and the backfill in all such ditches thoroughly compacted, the subgrade shall be brought to the lines, grades and cross section shown on the plans. If any sections of the subgrade are composed of unsuitable or unstable material, such material shall be removed to the depth directed by the inspector and replaced with suitable, thoroughly compacted material. Prior to placement of the street base, the subgrade shall be compacted to 95 percent density. Testing for sub-grade compaction will be required, including two tests at each sanitary sewer manhole.
(f) Utilities. Before any street base is applied, all of the underground utilities—water mains, sewer mains, gas mains, or any other underground utilities, and all service connections related thereto, that will be located under the street base shall be installed completely and provided throughout the length of the street and across the flat section. If a public water system is to be installed, the improvements are to be reviewed, approved and inspected by the water provider.
(g) Street base. The base shall be string-lined for depth and crown. The street base shall be roll-tested with an 18-ton tandem dump truck and shall pass to the satisfaction of the inspector.
When testing is required by the inspector, it is the responsibility of the developer to ensure that all required tests are made and reported to the inspector. The cost of all testing and quality control shall be performed at the expense of the developer by qualified testing laboratories. If deemed necessary by the inspector, additional tests will be required.
(h) Paving. The Inspector shall be on site during the paving process to check consistency, depth, and workmanship, as applicable. For asphalt paving, the temperature of the material will be monitored and the street will be cored after completion to check thickness and density.
Satisfactory test results of the cores shall be delivered to the public development department and the Jackson County Water and Sewerage Authority (where utilities are involved) prior to approval of a final subdivision plat or certificate of completion.
(i) Tree protection and landscaping. Inspections for tree protection measures and the installation of landscaping shall be as specified in article 12 of this UDC.
(j) Final. A final inspection of the development, once complete, shall be required.
(Ord. No. 17-003, § 1, 10-2-2017; Ord. No. 22-004, § 1, 5-16-2022) Sec. 852. Field changes.
(a) After issuance of a development permit, if changes are desired or made necessary as a result of field conditions, the design engineer must contact the public development department to coordinate the review and approval of the requested revision.
(b) All field changes shall be documented as revisions to the approved development plans and correctly shown on as-built surveys.
(c) Discrepancies between as-built surveys and approved development plans may result in delays in approving final plats, building permits or certificates of occupancy.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 853. Reference to specifications.
Where this UDC establishes specifications to be followed, said specifications shall be met, including but not limited to standard drawings established in article 23 of this UDC, specifications for streets and sidewalks in article 16, as well as other articles and sections of this UDC, where applicable. The following regulations and manuals are hereby adopted (as may be amended from time to time), and development shall be consistent with them, as applicable, unless otherwise approved by the director of public development.
(a) On-site sewage management. Georgia Department of Public Health, Environmental Health Section, Manual for On-Site Sewage Management Systems, revised January 2016.
(b) Soil erosion control. Manual for Erosion and Sediment Control in Georgia published by the Georgia Soil and Water Conservation Commission.
(c) Stormwater management. Inside urbanized areas of Jackson County only, Georgia Stormwater Management Manual: Volume 1: Local Government Guide (2016 Editions); Volume 2: Technical Handbook (2016 Edition); and Volume 3; Pollution Prevention Guidebook (2012).
(d) Surveys. Georgia Administrative Code Department 180, State Board of Registration for Professional Engineers and Land Surveyors, chapter 180-7, Technical Standards for Property Surveys.
(e) Access management. Georgia Department of Transportation Regulations for Driveway and Encroachment Control, Revision 4.0, dated March 15, 2016.
(f) Traffic control. Manual on Uniform Traffic Control Devices, latest edition, published by the Federal Highway Administration of the U.S. Department of Transportation.
(g) Landscaping. ANSI 300 standards: The generally accepted (consensus) industry standards for tree care practices, developed by the Tree Care Industry Association (TCIA) and written by a committee called the Accredited Standards Committee (ASC) A300. These standards are based on current research and sound practice for writing specifications to manage trees, shrubs, and other woody plants.
(h) Airspace encroachment. With regard to development around the Jackson County Airport only, United States Code of Federal Regulations, title 14: Aeronautics and Space, chapter I—Federal Aviation Administration, Department of Transportation, subchapter E—Airspace, part 77— Safe, Efficient Use, and Preservation of the Navigable Airspace.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 854. Disclaimers.
(a) No transfer of responsibility. Approval of development plans by the public development department shall not imply or transfer acceptance of responsibility for the application of the principles of engineering, architecture, landscape architecture or any other profession, from the professional, corporation or individual under whose hand or supervision the development plans were prepared. The completion of inspections and authorization for work continuation shall not transfer responsibility for the quality of the work performed or materials used from the owner, nor imply or transfer acceptance of responsibility for project design or engineering from the professional, corporation or individual under whose hand or supervision the development plans were prepared.
(b) No waiver of compliance. No development permit issued by the department shall be interpreted to relieve any owner of the responsibility of maintaining full compliance with all applicable codes, ordinances and other regulations. Any development permit issued in error or in contradiction to the provisions of this UDC shall be considered to have been null and void upon its issuance.
(c) No liability for damage. The approval of plans under the provisions of this article and the issuance of a development permit shall not relieve any person from the responsibility for damage to any person or property otherwise imposed by law, nor shall such plan approval or development permit issuance impose any liability upon the Jackson County Board of Commissioners for damage to any person or property.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 855. Certification and as-built plans.
(a) Upon completion of the project, the applicant or other responsible party shall submit a final hydrological study and all required as-built plans of the project in electronic format. All plans must be in the Georgia Coordinate System West Zone NAD 83. If the project is within 1,000 feet of a Jackson County geodetic monument the plans must use the monument as a control/tie point. In addition, the applicant shall submit electronic (DWG/DXF and PDF) file copies of information as specified by the Public Development Director and the director of geographic information services. Building permits may be withheld pending receipt of the electronic files.
(b) In addition to as-built plans, the development applicant shall submit electronic file copies of lot boundaries of subdivisions and related information as specified by the public development director and the director of geographic information services.
(c) A certificate of completion will be issued by the department of public development upon satisfactory completion of the development project.
(Ord. No. 17-003, § 1, 10-2-2017) Secs. 856—860. Reserved.
ARTICLE 9. UTILITY ENCROACHMENT
DIVISION I. IN GENERAL
Sec. 901. Purpose and intent.
Jackson County (the "county") is vitally concerned with the use, construction within, and occupancy of all rights-of-way in the county as such rights-of-way are a valuable and limited resource which must be utilized to promote the public health, safety, welfare, economic development of the county and to protect public works infrastructure. Therefore, the county, under the authority of the laws and Constitution of the State of Georgia, including but not limited to article 9, section 1, paragraphs 2 and 3 of the Georgia Constitution, O.C.G.A. § 36-1-20 and O.C.G.A. § 32-4-42(6), adopts this UDC for the purpose of regulating public and private entities which use the county rights-of-way.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 902. Scope.
The provisions of this article shall apply to all utilities and facilities occupying the rights-of-way as provided herein.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 903. Definitions.
For the purposes of this article, the following terms, phrases, words, and their derivations have the meanings set forth herein. The words "shall" and "will" are mandatory and "may" is permissive. Words not defined shall be given their common and ordinary meaning.
Construct: To, dig, bore, tunnel, trench, excavate, obstruct, install or remove signs, or facilities, other than landscaping or ornamental plantings, in, on, above, within, over, below, under, or through any part of the rights-of-way. Construct shall also include the act of opening and/or cutting into the surface of any paved or improved surface that is any part of the right-of-way.
Construction: The act or process of digging, boring, tunneling, trenching, excavating, obstructing, installing or removing signs or facilities, other than landscaping or ornamental plantings, in, on, above, within, over, below, under, or through any part of the rights-of-way. "Construction" shall also include the act of opening, boring and/or cutting into the surface of any part of the right-of-way.
Director: The director of the Department of Public Development of Jackson County, Georgia, or his or her designee.
Emergency: A condition that poses a clear and immediate danger to life, health, or safety of a person, or of significant damage or loss of real or personal property.
Facility or facilities: Any tangible thing, including but not limited to pipes, mains, conduits, cables, wires, poles, towers, traffic and other signals, and other equipment, appurtenances, appliances and future technology of any utility in, on, along, over, or under any part of the rights-of-way within the county;
Facilities representative(s): The specifically identified agent(s)/employee(s) of a utility who are authorized to direct field activities of that utility and serve as official notice agent(s) for facilities-related information.
FCC: The Federal Communications Commission or any successor thereto.
Permit: An authorization which grants permission to conduct specific regulated activities on, in, over, under or within any public right-of-way, and which may be subject to conditions specified in a written agreement with the county or in a related provision of the County's Code of Ordinances.
Right(s)-of-way: The surface and space in, on, above, within, over, below, under or through any real property in which the county has an interest in law or equity, whether held in fee, or other estate or interest, or as a trustee for the public, including, but not limited to any public street, boulevard, road, highway, freeway, lane, alley, court, sidewalk, parkway, or any other place, area, or real property owned by or under the legal or equitable control of the county, now or hereafter, that consistent with the purposes for which it was dedicated, may be used for the purposes of constructing, operating, repairing or replacing facilities.
Service(s): The offering of any service by a utility for a fee directly to the public, or to such classes of users as to be effectively available directly to the public, or alternatively, the provision of any service by a utility between two or more points for a proprietary purpose to a class of users other than the general public.
Service agreement: A valid license agreement, service agreement, franchise agreement, or operating agreement issued by the county or state pursuant to law and accepted by a utility or entered into by and between the county and a utility, which allows such utility to operate or provide service within the geographic limits of the county.
Street or streets: The surface of, as well as the spaces above and below, any and all the streets, alleys, avenues, roads, bridges, tunnels and public places of the county within the corporate limits of the county, as the same now exist or may be hereafter extended or altered, and any location thereon, thereover or thereunder, and any portion thereof.
Transfer: The disposal by the utility, directly or indirectly, by gift, assignment, sale, merger, consolidation, or otherwise, of more than 50 percent at one time of the ownership or controlling interest in the facilities, or of more than 50 percent cumulatively over the term of a written approval of registration of such interests to a corporation, partnership, limited partnership, trust, or association, or person or group of persons acting in concert.
Unused facilities: Facilities located in the rights-of-way which have remained unused for 12 months and for which the utility is unable to provide the county with a plan detailing the procedure by which the utility intends to begin actively using such facilities within the next 12 months, or that it has a potential purchaser or user of the facilities who will be actively using the facilities within the next 12 months, or, that the availability of such facilities is required by the utility to adequately and efficiently operate its facilities.
Utility or utilities: All privately, publicly, or cooperatively owned systems for producing, transmitting, or distributing communication, data, information, telecommunication, cable television, video services, power, electricity, light, heat, gas, oil, crude products, water/sewer, steam, fire and police signals, traffic control devices, and street lighting systems, and housing or conduit for any of the foregoing, which directly or indirectly serve the public or any part thereof. The term "utility" may also be used to refer to the owner, operator, utility, service, contractor or subcontractor, or any agent thereof, of any utility or utility facility.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 904. Utility encroachment permit required.
(a) It shall be unlawful for any utility to excavate or to construct, install, maintain, renew, remove or relocate facilities in, on, along, over or under the public rights-of-way of the county without a utility encroachment permit from the department of public development in accordance with the terms of this article.
(b) The requirement to obtain a utility encroachment permit may be waived by the director of public development in cases where utility work contemplated within the public rights-of-way of the county is shown on construction plans for a private development that has been reviewed and approved by the department of public development and a development permit has been issued in accordance with applicable provisions of this UDC.
(c) This section shall not be construed as requiring a separate utility encroachment permit for a driveway or for installation of a storm drainage culvert if such driveway or storm drainage culvert is authorized by the director of public development under a separate permit or authorization pursuant to this UDC.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 905. Utility encroachment permit procedure.
Utility encroachment permits shall be obtained from the department of public development upon application made on forms prescribed by the department of public development. The written application shall include the following:
(a) The name and address of the utility;
(b) The nature, extent, and location of any work proposed to be done, along with satisfactory plans as attachments showing in detail the location of the proposed facility or operations as described in the permit application. The plans shall show the size or capacity of facilities to be installed;
their relationship to street features such as right-of-way lines, pavement edge, structures, etc., horizontal and vertical clearance to critical elements of the roadway and any other information necessary by the department of public development to evaluate the impact on the street and its operation;
(c) The name and address of the person or firm who is to do such work;
(d) The name, street address, email address if applicable and telephone and facsimile numbers of one or more facilities representative(s).
(e) The projected starting and finishing dates for the work;
(f) An indemnity bond or other acceptable security in an amount to be set by the county to pay any damages to any part of the county road system or other county property or to any county employee or member of the public caused by activity or work of the utility performed under authority of the permit issued;
(g) A copy, if requested, of the registrant's certificate of authority (or other acceptable evidence of authority to operate) from the Georgia Public Service Commission and/or the FCC and any other similar approvals, permits, or agreements;
(h) A copy, if requested, of the service agreement, if applicable or other legal instrument that authorizes the utility to use or occupy the right-of-way for the purpose described in the application;
(i) The application shall be accompanied by a permit review fee, as established by resolution of the Jackson County Board of Commissioners.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 906. Incomplete permit application.
If a permit application is incomplete, the department of public development shall notify the applicant and shall provide a reasonable period of time in which to revise the application.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 907. Permit review and decision.
(a) Unless the permit application is extraordinarily complicated and extensive, in which case more time may be taken, the department of public development shall have 30 calendar days from the posted application submission deadline to review the permit application for compliance with the requirements of this article and to evaluate the application in terms of the impact of work proposed in the permit with regard to the following: impacts on safety, visual quality of streets, traffic flow, other users of the right-of-way; and the difficulty and length of time of the project.
(b) The department of public development shall issue the requested permit if there are no concerns with regard to the criteria of this section. The department may place conditions of approval on any permit issued. If there are concerns with issuing the requested permit, the department shall indicate those concerns or objections in writing to the applicant and deny the requested permit.
(c) Any applicant aggrieved of a decision of the department of public development to deny a utility encroachment permit under the provisions of this article may file in writing and sent via certified mail an appeal with the director of public development, who shall schedule the appeal for the next available meeting of the Jackson County Board of Adjustment for decision on the appeal. The board of adjustment in acting on appeal may affirm or overturn the decision of the director and to that end may issue the requested permit, with or without conditions, and with or without modifications from the original permit requested.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 908. Permit commencement, expiration and extension.
(a) Each permit issued by the department of public development shall have a set commencement and expiration date based on information provided in the applicant's permit application. When the construction under any permit is completed, the utility shall notify the department of public development. The permit shall remain in place until construction or activity authorized under the permit is completed or until its expiration date unless the utility is in default.
(b) If work is not begun within six months of the date of permit issuance, the permit will automatically expire.
(c) The director of public development is authorized but shall not be obligated to grant an extension to a permit prior to expiration, upon application, and provided that a permit review fee required for a permit application is paid.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 909. Permit default.
The director of public development may find a utility in default and give written notice of default to a utility if it is determined that a utility has:
(a) Violated any provision, requirement, or condition of a utility encroachment permit, or any law of the county, state, or federal government;
(b) Attempted to evade any provision or requirement of this article;
(c) Practiced any fraud or deceit upon the county; or
(d) Made a material misrepresentation or omission of fact in its permit application.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 910. Termination of permit.
If a utility fails to cure a default within 20 calendar days after such notice is provided to the utility by the county, then such default shall be a material breach and the county may exercise any remedies or rights it has at law or in equity to terminate the permit. If the director of public development decides there is cause or reason to terminate, the following procedure shall be followed:
(a) The director or designee shall serve a utility with a written notice of the reason or cause for proposed termination and shall allow a utility a minimum of 15 calendar days to cure its breach;
and
(b) If the utility fails to cure within 15 calendar days, the county may declare the permit terminated.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 911. Utility accommodation policy and standards.
(a) The document known as "Utility Accommodation Policy and Standards," promulgated and published by the Georgia Department of Transportation Division of Operations, Office of Utilities, dated 2016, and as may be amended from time to time, is hereby adopted in its entirety as if fully set forth in this article, as minimum required standards.
(b) A copy of the "Utility Accommodation Policy and Standards" shall be maintained at the offices of the department of public development and open for public inspection.
(c) References in the "Utility Accommodation Policy and Standards" to state personnel, agencies, and fees shall be interpreted, where required, as meaning the Jackson County equivalents.
(d) Any conflicts between the provisions of this article and the "Utility Accommodation Policy and Standards" shall be resolved in favor of the "Utility Accommodation Policy and Standards."
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 912. Protection of traffic and roadway.
Unless specifically stated otherwise in a utility encroachment permit, no utility may occupy any county right-of-way unless sufficient space is available so that the free flow and safety of traffic and other capacity considerations are not unduly impaired and the installation does not prevent the county roads department or any employees thereof from reasonably maintaining the streets, structures, traffic control devices and other appurtenant facilities, and further provided that maintenance and operations of the facilities do not jeopardize the traffic, street structure, other users of the right-of-way or the right-of-way itself.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 913. Grading.
(a) If the grades or lines of any street within a county right-of-way are changed at any time by the county during the term of the permit and such change involves an area in which the utility's facilities are located, then the utility shall, at its own cost and expense and upon the request of the county upon reasonable notice, protect or promptly alter or relocate the facilities, or any part thereof, so as to conform with such new grades or lines.
(b) In the event the utility refuses or neglects to so protect, alter, or relocate all or part of the facilities, the county shall have the right to break through, remove, alter, or relocate all or any part of the facilities without any liability to the utility and the utility shall pay to the county the costs incurred in connection with such breaking through, removal, alteration, or relocation.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 914. Installation of poles and other wireholding structures and relocation.
Unless otherwise provided in a valid service agreement, no placement of any pole or wireholding structure of the utility is to be considered a vested interest in the right-of-way, and such poles or structures are to be removed, relocated underground, or modified by the utility at its own expense whenever the county determines that the public convenience would be enhanced thereby. The facilities shall be so located and installed as to cause minimum interference with the rights and convenience of property owners.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 915. Blasting or excavating.
As provided in O.C.G.A § 25-9-6 (The Georgia Utility Facility Protection Act) and other applicable state law currently in place or as amended, no utility shall commence, perform, or engage in blasting or in excavating with mechanized excavating facilities unless and until the utility intending to engage in the blasting or excavating has given 48 hours' notice by submitting a locate request to the utility protection center, beginning the next working day after such notice is provided, excluding hours during days other than working days.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 916. Restoration of property.
(a) Each utility shall be responsible for the cost of repairing any facilities in the rights-of-way and adjoining property or other facilities which it or its facilities damage.
(b) A utility shall be liable, at its own cost and expense, to replace, restore or repair, any street, facilities or property or structure thereon, thereunder, thereover or adjacent thereto that may become disturbed or damaged as a result of the construction or installation, operation, upgrade, repair or removal of facilities to a condition as good as or better than its condition before the work performed by the utility that caused such disturbance or damage.
(c) If the utility does not commence such replacement or repair after 20 calendar days following written notice from the county, the county or the owner of the affected structure or property may make such replacement or repair and the utility shall pay the reasonable and actual cost of the same.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 917. Inspection.
The utility shall make the construction site available to the director of public development or designee and to all others as authorized by law for inspection at all reasonable times during the execution and upon completion of the construction.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 918. Orders.
At any time, including the time of inspection, the director of public development may order the immediate cessation of any work which poses a serious threat to the health, safety, or welfare of the public, violates any law, or which violates the terms and conditions of the permit and/or this division or issue an order to correct work which does not conform to the permit and/or applicable standards, conditions or codes.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 919. Additional permits required.
The utility shall obtain all construction, building or other permits or approvals required by county ordinance, state and federal law. In addition, a permittee shall comply with all requirements of laws, shall complete work in a way as to not cause any unnecessary or unauthorized obstructions of sidewalks, streets, waterways or railways, and is responsible for all work done in the rights-of-way regardless of who performs the work. No rights-of-way obstruction or excavation may be performed when seasonally prohibited or when conditions are unreasonable for such work, except in the case of an emergency as provided in this division.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 920. Penalties.
Every utility convicted of a violation of any provision of this division shall be punished by a fine not exceeding $1,000.00 per violation. Each act of violation and each day upon which any such violation shall occur shall constitute a separate offense. In addition to the penalty prescribed above, the county may pursue other remedies such as abatement of nuisances, injunctive relief and revocation of licenses or permits.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 921. Compliance.
No person shall be relieved of its obligation to comply with any of the provisions of this article by reason of any failure of the county to enforce compliance.
(Ord. No. 17-003, § 1, 10-2-2017)
DIVISION II. SMALL WIRELESS FACILITIES AND ANTENNAS
Sec. 931. Purpose and intent.
(a) O.C.G.A. § 32-4-42(6) authorizes Jackson County, Georgia (the "County") to establish reasonable regulations for the installation, construction, maintenance, renewal, removal, and relocation of pipes, mains, conduits, cables, wires, poles, towers, traffic and other signals, and other equipment, facilities, or appliances in, on, along, over, or under the public roads of the county. Further, 47 U.S.C. § 253(c) provides that the County has authority to manage its public rights-of-way. Finally, the Georgia Streamlining Wireless Facilities and Antennas Act., O.C.G.A. tit. 36, ch. 66C (the "SWFAA"), addresses the placement of small wireless facilities in the public rights-of-way of the county.
(b) The county finds it is in the best interest of the county and its residents and businesses to establish requirements, specifications reasonable conditions regarding placement of small wireless facilities, poles in the public rights-of-way. These requirements, specifications and conditions are adopted in order to protect the public health, safety and welfare of the residents and businesses of the county and to reasonably manage and protect the public rights-of-way and its uses in the county.
(c) The objective of this division is to:
1. Implement the SWFAA; and
2. Ensure use of the public rights-of-way is consistent with the design, appearance and other features of nearby land uses, protects the integrity of historic, cultural and scenic resources and does not harm residents' quality of life.
(Ord. No. 19-003, § 1(Exh. A), 10-21-2019) Sec. 932. Definitions.
As used in this division, the following terms have the following meanings:
Antenna:
(a) Communications equipment that transmits, receives, or transmits and receives electromagnetic radio frequency signals used in the provision of wireless services or other wireless communications; or
(b) Communications equipment similar to equipment described in part (i) used for the transmission, reception, or transmission and reception of surface waves. Such term shall not include television broadcast antennas, antennas designed for amateur radio use, or satellite dishes for residential or household purposes.
Applicable codes: Uniform building, fire, safety, electrical, plumbing, or mechanical codes adopted by a recognized national code organization to the extent such codes have been adopted by the State of Georgia or the county or are otherwise applicable in the county.
Applicant: Any person that submits an application.
Application: A written request submitted by an applicant to the county for a permit to:
(a) Collocate a small wireless facility in a right-of-way; or
(b) Install, modify, or replace a pole or decorative pole in a right-of-way on which a small wireless facility is or will be collocated.
Authority pole: A pole owned, managed, or operated by or on behalf of the county. Such term shall not include poles, support structures, electric transmission structures, or equipment of any type owned by an electric supplier.
Collocate or collocation: To install, mount, modify, or replace a small wireless facility on or adjacent to a pole, decorative pole, or support structure.
Communications facility: The set of equipment and network components, including wires and cables and associated equipment and network components, used by a communications service provider to provide communications services.
Communications service provider: A provider of communications services.
Communications services: Cable service as defined in 47 U.S.C. § 522(6); telecommunications service as defined in 47 U.S.C. § 153(53); information service as defined in 47 U.S.C. Section 153(24), as each such term existed on January 1, 2019; or wireless services.
Consolidated application: An application for the collocation of multiple small wireless facilities on existing poles or support structures or for the installation, modification, or replacement of multiple poles and the collocation of associated small wireless facilities.
Decorative pole: An authority pole that is specially designed and placed for aesthetic purposes.
Electric supplier: Any electric light and power company subject to regulation by the Georgia Public Service Commission, any electric membership corporation furnishing retail service in this state, and any municipality that furnishes such service within this state.
Eligible facilities request: An eligible facilities request as set forth in 47 C.F.R. § 1.40001(b) (3), as it existed on January 1, 2019.
FCC: The Federal Communications Commission of the United States.
Fee: A one-time, nonrecurring charge based on time and expense.
Historic district: Includes, but is not limited to:
(a) Any district, site, building, structure, or object included in, or eligible for inclusion in, the National Register of Historic Places maintained by the secretary of the interior of the United States in accordance with section VI.D.1.a.i-v of the Nationwide Programmatic Agreement codified by 47 C.F.R. Part 1;
(b) Any area designated as a historic district under article 2 of chapter 10 of title 44, the Georgia Historic Preservation Act; or
(c) Any area designated as a historic district or property by law prior to April 26, 2019.
Law: Any and all federal, state, or local laws, statutes, common laws, codes, rules, regulations, orders, or articles.
Micro wireless facility: A small wireless facility not larger in dimension than 24 inches in length, 15 inches in width, and 12 inches in height that has an exterior antenna, if any, no longer than 11 inches.
Permit: A written authorization, in electronic or hard copy format, required to be issued by the county to initiate, continue, or complete the collocation of a small wireless facility or the installation, modification, or replacement of a pole or decorative pole upon which a small wireless facility is collocated.
Person: An individual, corporation, limited liability company, partnership, association, trust, or other entity or organization, including an authority.
Pole: A vertical pole such as a utility, lighting, traffic, or similar pole made of wood, concrete, metal, or other material that is lawfully located or to be located within a right-of-way, including without limitation a replacement pole and an authority pole. Such term shall not include a support structure, decorative pole, or electric transmission structure.
Rate: A recurring charge.
Reconditioning work: Activities associated with substantially painting, reconditioning, improving, or repairing authority poles.
Replace: To replace a pole or decorative pole with a new pole or a new decorative pole, similar in design, size, and scale to the existing pole or decorative pole consistent with 47 C.F.R. § 1.40001(b)(7) as it existed on January 1, 2019, in order to address limitations of, or change requirements applicable to, the existing pole to structurally support the collocation of a small wireless facility.
Replacement work: Activities associated with replacing an authority pole.
Right-of-way: Generally, property or any interest therein, whether or not in the form of a strip, which is acquired for or devoted to a public road; provided, however, that such term shall apply only to property or an interest therein that is under the ownership or control of the county and shall not include property or any interest therein acquired for or devoted to an interstate highway or the public rights, structures, sidewalks, facilities, and appurtenances of buildings for public equipment and personnel used for or engaged in administration, construction, or maintenance of public roads or research pertaining thereto or scenic easements and easements of light, air, view and access.
Small wireless facility: Radio transceivers; surface wave couplers; antennas; coaxial, fiber optic, or other cabling; power supply; backup batteries; and comparable and associated equipment, regardless of technological configuration, at a fixed location or fixed locations that enable communication or surface wave communication between user equipment and a communications network and that meet both of the following qualifications:
(a) Each wireless provider's antenna could fit within an enclosure of no more than six cubic feet in volume; and
(b) All other wireless equipment associated with the facility is cumulatively no more than 28 cubic feet in volume, measured based upon the exterior dimensions of height by width by depth of any enclosure that may be used. The following types of associated ancillary equipment are not included in the calculation of the volume of all other wireless equipment associated with any such facility: electric meters; concealment elements; telecommunications demarcation boxes;
grounding equipment; power transfer switches; cut-off switches; and vertical cable runs for connection of power and other services.
Such term shall not include a pole, decorative pole, or support structure on, under, or within which the equipment is located or collocated or to which the equipment is attached and shall not include any wireline backhaul facilities or coaxial, fiber optic, or other cabling that is between small wireless facilities, poles, decorative poles, or support structures or that is not otherwise immediately adjacent to or directly associated with a particular antenna.
State: The State of Georgia.
Support structure: A building, billboard, water tank, or any other structure to which a small wireless facility is or may be attached. Such term shall not include a decorative pole, electric transmission structure, or pole.
Wireless infrastructure provider: Any person, including a person authorized to provide telecommunications services in this state, that builds, installs, or operates small wireless facilities, poles, decorative poles, or support structures on which small wireless facilities are or are intended to be used for collocation but that is not a wireless services provider.
Wireless provider: A wireless infrastructure provider or a wireless services provider.
Wireless services: Any services provided to the public using licensed or unlicensed spectrum, including the use of Wi-Fi, whether at a fixed location or mobile.
Wireless services provider: A person that provides wireless services.
Wireline backhaul facility: An aboveground or underground wireline facility used to transport communications data from a telecommunications demarcation box associated with small wireless facility to a network.
(Ord. No. 19-003, § 1(Exh. A), 10-21-2019) Sec. 933. Small wireless facilities, generally.
Small wireless facilities and new, modified, or replacement poles to be used for collocation of small wireless facilities may be placed in the right-of-way as a permitted use subject to applicable codes and the following requirements:
(a) Each such new, modified, or replacement pole installed in the right-of-way in a historic district and in an area zoned primarily for residential use shall not exceed 50 feet above ground level;
(b) Each such new, modified, or replacement pole installed in the right-of-way not in historic district or in an area zoned primarily for residential use shall not exceed the greater of:
1. Fifty feet above ground level; or
2. Ten feet greater in height above ground level than the tallest existing pole in the same authority right-of-way in place as of January 1, 2019, and located within 500 feet of the new proposed pole; and
(c) New small wireless facilities in the right-of-way shall not exceed:
1. For a collocation on an existing pole or support structure, more than ten feet above the existing pole or support structure; or
2. For a collocation on a new, modified, or replacement pole under paragraph (a) or (b) of this subsection, the height limit provided in such paragraphs.
(Ord. No. 19-003, § 1(Exh. A), 10-21-2019) Sec. 934. Permit required.
A permit is required to collocate a small wireless facility in the public right-of-way or to install, modify, or replace a pole or a decorative pole in the public right-of-way unless specifically exempted by this division.
(a) Any person seeking to collocate a small wireless facility in the public right-of-way or to install, modify, or replace a pole or a decorative pole in the public right-of-way shall submit an application to the Jackson County Public Development Department for a permit. Applications are available from the Jackson County Public Development Department. Any material change to information contained in an application shall be submitted in writing to the Jackson County Public Development Department within 30 days after the events necessitating the change.
(b) Any person who intends to submit an application to the county pursuant to this division shall meet with the Jackson County Public Development Department at least 30 days prior to submitting an application for a permit. The purpose of such meeting shall be to inform the county, in good faith, when the applicant expects to commence deployment of small wireless facilities and poles within the county, the number of small wireless facilities and poles it expects to deploy during the 24 months after commencement, and the expected timing of such deployments.
(Ord. No. 19-003, § 1(Exh. A), 10-21-2019) Sec. 935. Exemptions.
A permit is not required to perform the following activities:
(a) An application shall not be required for the following activities, provided that a wireless provider may be required to obtain permits for such activities, such as electrical permits or street opening permits, if otherwise required by generally applicable law:
1. Inspections, testing, repairs, and modifications that maintain functional capacity, aesthetic, and structural integrity of poles or decorative poles used for collocation of small wireless facilities. Any modifications are limited by the structural load analysis supplied by the applicant in its prior application to the county; and
2. Inspections, testing, repairs that maintain functional capacity or the replacement or upgrade of antennas, or other components of the small wireless facility such as swap out or addition of antennas and other components as required by the applicant, with antennas and other components substantially similar in color, aggregate size, and other aesthetics to the small wireless facility previously issued a permit by the county. To qualify for this exemption any upgrade or repair shall be subject to the height and volume limits for small wireless facilities under this chapter.
(b) An application or permit is not required for the installation, placement, maintenance, operation, or replacement of micro wireless facilities that are suspended on cables that are strung between poles or support structures in the right-of-way in compliance with applicable codes;
provided, however, that an authority may require a wireless provider to obtain permits for any additional activities such as electrical work, excavation, or closure of sidewalks or vehicular lanes within the right-of-way if otherwise required by generally applicable law. Such permits shall be issued on a nondiscriminatory basis upon terms and conditions applied to any other person's similar activities in the right-of-way.
(Ord. No. 19-003, § 1(Exh. A), 10-21-2019) Sec. 936. Application requirements.
The applicable wireless provider or its duly authorized representative shall submit each application, and shall contain the following:
(a) The applicant's name, address, telephone number, and email address, including emergency contact information for the applicant;
(b) The names, addresses, telephone numbers, and email addresses of all consultants, if any, acting on behalf of the applicant with respect to filing the application;
(c) A general description of the proposed work and the purposes and intent of the proposed facility.
The scope and detail of such description shall be appropriate to the nature and character of the physical work to be performed, with special emphasis on those matters likely to be affected or impacted by the physical work proposed;
(d) Detailed construction drawings regarding the proposed use of the right-of-way;
(e) To the extent the proposed facility involves collocation on a pole or support structure, a structural report performed by a duly licensed engineer evidencing that the pole or support structure will structurally support the collocation (or that the pole or support structure may and will be modified to meet structural requirements) in accordance with applicable codes;
(f) For any new aboveground facilities, visual depictions or representations if not included in the construction drawings;
(g) Information indicating the horizontal and approximate vertical location, relative to the boundaries of the right-of-way, of the small wireless facility for which the application is being submitted;
(h) If the application is for the installation of a pole, a written certification from the wireless provider that after diligent investigation the service objectives of the permit cannot be met by colocation on an existing pole, or support structure where the wireless provider has the right to collocate, subject to reasonable terms and conditions, and collocation would not impose technical limitations or significant additional costs. The wireless provider shall certify that it has made such a determination in good faith, based on the assessment of a licensed engineer, and shall provide a written summary of the basis for such determination.
(i) If the small wireless facility will be collocated on a pole or support structure owned by a third party, a certification that the wireless provider has permission from the owner to collocate on the pole or support structure; and
(j) If the applicant is not a wireless services provider, a certification that a wireless services provider has requested in writing that the applicant collocate the small wireless facilities or install, modify or replace the pole or decorative pole at the requested location.
(Ord. No. 19-003, § 1(Exh. A), 10-21-2019) Sec. 937. Application fees and annual increases.
Each application for a permit shall include the following application fees:
(a) For each application for the collocation of each small wireless facility on an existing pole a fee of $100.00 per small wireless facility;
(b) For each application for each replacement pole with an associated small wireless facility $250.00 per pole with and associated small wireless facility;
(c) For each application for each new pole with an associated small wireless facility a fee of $1,000.00 per pole with an associated small wireless facility;
(d) The fees for each application type described above in this section shall increase by two and one-half percent annually beginning January 1, 2021.
(Ord. No. 19-003, § 1(Exh. A), 10-21-2019) Sec. 938. Application review procedures.
Within 20 days of receipt of a written application, the public development department shall:
(a) Notify the applicant in writing of the commencement and completion dates of any widening, repair, reconstruction, or relocation of the applicable right-of-way that is scheduled to commence, or is anticipated in good faith to commence, within 24 months after the application is filed;
(b) Notify the applicant, based on the county's good faith preliminary review of the information provided in the application, of any aspect of the application that appears to be grounds for denial of the application pursuant to this code section; and
(c) Determine whether the application is complete and inform the applicant of its determination in writing.
1. If the county determines that an application is incomplete, it shall specifically identify to the applicant in writing all missing information within such 20-day period; otherwise, the application is deemed complete.
2. If the county identifies missing information to the applicant as provided in this paragraph, the applicant may submit missing information to the county within 20 days of receipt of notification in writing from the county that the application is incomplete without paying any additional application fee, and any subsequent review of the application by the county for completeness shall be limited to the previously identified missing information.
3. If the county determines that an application remains incomplete, or if the county determines that the applicant has made material changes to the application other than to address the missing information identified by the county, the county shall notify the applicant of such determination in writing within ten days of receipt of the resubmission of the written application, and absent an agreement to the contrary between the county and the applicant that is confirmed by email or other writing, such notice shall constitute a denial of the application. If the county does not provide such written notification to the applicant within this ten-day period, the application shall be deemed complete.
(Ord. No. 19-003, § 1(Exh. A), 10-21-2019) Sec. 939. Decision to approve or deny permit application.
(a) The county shall make its final decision to approve or deny the application:
1. Within 30 days of the written determination that the application is complete or when the application is deemed complete whichever is earlier, for a collocation; and
2. Within 70 days of the written determination that the application is complete or when the application is deemed complete under subsection [938(c)3.], whichever is earlier, for the installation, modification, or replacement of a pole or decorative pole.
(b) A decision to deny an application pursuant to this code section shall be in writing, shall identify all reasons for the denial, and shall identify the provisions of applicable codes or other standards on which the denial was based. The decision to deny shall be sent to the applicant contemporaneously. The review period shall run until the written decision is delivered to the applicant in a manner described below in subsection (e).
(c) If the county fails to act on an application within the review period provided for in subsection [938(c)3.], the applicant may provide the county written notice that the time for acting has lapsed, and the county shall then have 20 days after receipt of such notice to render its written decision. The application shall be deemed approved by passage of time and operation of law if the county does not render its written decision within such 20 days.
(d) An applicant may, at their discretion and subject to the consolidated application requirements and processes file a consolidated application.
(e) All decisions and notices required by this division shall be sent by registered or certified mail, statutory overnight delivery, hand delivery, or email transmission. The decision or notice shall be deemed delivered upon email transmission, deposit into overnight mail or regular mail receptacle with adequate postage paid, or actual receipt if delivered by hand.
(f) Applications for permits shall be approved unless the requested collocation of a small wireless facility or the requested installation, modification, or replacement of a pole or decorative pole:
1. Interferes with the operation of traffic control equipment;
2. Interferes with sight lines or clear zones for transportation or pedestrians;
3. Fails to comply with the Americans with Disabilities Act, 42 U.S.C. section 12101, et seq., or similar laws of general applicability regarding pedestrian access or movement;
4. Requests that ground-mounted small wireless facility equipment be located more than seven and a half feet in radial circumference from the base of the pole, decorative pole or support structure to which the small wireless facility antenna would be attached, provided that the county shall not deny the application if a greater distance from the base of the pole, decorative pole or support structure is necessary to avoid interfering with sight lines or clear zones for transportation or pedestrians or to otherwise to protect public safety;
5. Fails to comply with applicable codes;
6. Fails to comply with the limitations set forth by section 933 of this division.
7. Interferes with the widening, repair, reconstruction, or relocation of a public road or highway by a county or the department of transportation that has been advertised for bid and scheduled for completion within six months after the application is filed;
8. Interferes with a public works construction project governed by chapter 91 of title 36 which is advertised for bid and scheduled for completion within six months after the application is filed;
9. Fails to comply with laws of general applicability addressing pedestrian and vehicular traffic and safety requirements; or
10. Fails to comply with laws of general applicability that address the occupancy or management of the right-of-way and that are not otherwise inconsistent with this division.
(g) For applications for new poles in the public right-of-way in areas zoned for residential use, the Jackson County Public Development Department may propose an alternate location in the public right-of-way within 100 feet of the location set forth in the application, and the wireless provider shall use the Jackson County Public Development Department proposed alternate location unless the location imposes technical limits or significant additional costs. The wireless provider shall certify that it has made such a determination in good faith, based on the assessment of a licensed engineer, and it shall provide a written summary of the basis for such determination.
(Ord. No. 19-003, § 1(Exh. A), 10-21-2019) Sec. 940. Consolidated applications.
An applicant may submit a single consolidated application, if such a consolidated application shall be for a geographic area no more than two miles in diameter and shall comply with this code section. The denial of one or more small wireless facilities or poles in a consolidated application shall not delay the processing of any other small wireless facilities or poles in the same application. An authority may issue a single permit or multiple permits for the small wireless facilities and poles in a consolidated application.
(a) A consolidated application for the placement of new poles and the collocation of one or more small wireless facilities on such new poles may include no more than two poles and any associated small wireless facilities. While an applicant has applications, including consolidated applications, pending before the county for review of 15 or more new poles and the collocation of associated small wireless facilities, the county may, but shall not be required to, toll the processing requirements for any application subsequently submitted by the same applicant for the placement of new poles and the collocation of associated small wireless facilities; and
(b) A consolidated application for the collocation of small wireless facilities on existing poles or support structures may include no more than six sites. While an applicant has applications, including consolidated applications, pending before the county for review of 45 or more sites for the collocation of small wireless facilities on existing poles or support structures, the county may, but shall not be required to, toll the processing requirements for any application subsequently submitted by the same applicant for the collocation of small wireless facilities on existing poles or support structures.
(c) Small wireless facilities and poles that a wireless services provider applicant has requested a third party to deploy and that are included in a pending application by the third party shall be counted as pending requests by the wireless services provider applicant; and
(d) When the processing of an application is tolled, the application is no longer counted as pending.
As processing of applications is completed, the authority shall begin processing previously tolled applications in the order in which they were submitted, unless the applicant specifies a different order.
(Ord. No. 19-003, § 1(Exh. A), 10-21-2019) Sec. 941. Permits.
(a) A permit issued under this division shall authorize such person to occupy the public rights-of-way to:
1. Collocate a small wireless facility on or adjacent to a pole or a support structure that does not exceed the limitations set forth in subsection [939(f)(4)], above; and
2. Install, modify, or replace a pole or decorative pole for collocation of a small wireless facility that does not exceed the limitations set forth in subsection [939(f)(4)], above.
(b) Upon the issuance of a permit under this division, and on each anniversary of such issuance, every person issued a permit shall submit to the county $100.00 for each small wireless facility collocated on any existing or replacement pole, or $200.00 for each new pole; provided, however, that if such person removes its small wireless facilities form the public rights-of-way then such person shall be responsible for the pro rata portion of the annual payment based on the number of days of occupation since the last annual payment. Upon making such pro rata payment and removal of the small wireless facilities, the person's annual payment obligations under this section shall cease as of the date of the actual removal.
The maximum annual payments shall automatically increase by two and one-half percent on January 1 of each year beginning January 1, 2021.
(c) The county may revoke a permit issued pursuant to this division if the wireless provider or its equipment placed in the public right-of-way under that permit subsequently does not comply with any provision of this division or the Georgia Streamlining Wireless Facilities and Antennas Act. Upon revocation, the county may proceed according to (d).
(d) If a wireless provider occupies the public rights-of-way without obtaining a permit required by this division or without complying with the SWFAA, then the county may, at their sole discretion, restore the right-of-way, to the extent practicable in the reasonable judgment of the county, to its condition prior to the unpermitted collocation or installation and to charge the responsible wireless provider the reasonable, documented cost of the county in doing so, plus a penalty not to exceed $1,000.00. The county may suspend the ability of the wireless provider to receive any new permits from the county under this division until the wireless provider has paid the amount assessed for such restoration costs and the penalty assessed, if any; provided, however, that the county may not suspend such ability of any applicant that has deposited the amount in controversy in escrow pending an adjudication of the merits of the dispute by a court of competent jurisdiction.
(e) All accepted applications for permits shall be publicly available. The applicant may designate portions of its application materials confidential where it reasonably believes they contain trade secrets according to applicable code.
(f) An applicant may file a consolidated application related to multiple small wireless facilities, poles or decorative poles for no more than.
(g) Activities authorized under a permit shall be completed within six months after issuance. A written request for an extension for up to an additional six months may be submitted to the County before the end of the initial six month period if a delay in completing the authorized work is the result of circumstances beyond the reasonable control of the applicant.
(h) Issuance of a permit authorizes the applicant to:
1. Undertake the collocation, installation, modification or replacement approved by the permit and ;
2. Operate and maintain the small wireless facilities and any associated pole covered by the permit for a period of ten years.
(i) If an application for a permit seeks to collocate small wireless facilities on authority poles in the public rights-of-way, then the county shall, within 60-days of receipt of the completed application:
1. Provide a good faith estimate for any make-ready work necessary to enable the county pole to support the proposed facility; or
2. Notify the wireless provider that the wireless provider will be required to perform the makeready work.
3. If the county opts to perform the make-ready work itself, the county shall complete the work, including any pole replacement, within 90 days of receipt of written acceptance of the good faith estimate by the wireless provider. Such acceptance shall be signified by payment via check or other commercially reasonable and customary means specified by the county. The county may require that the replacement authority pole have the same functionality as the pole being replaced. If the county pole is replaced, the county shall operate fixtures on the pole, and absent an agreement to the contrary between the county and the wireless provider that is confirmed in writing, the county shall take ownership of the new pole.
(Ord. No. 19-003, § 1(Exh. A), 10-21-2019) Sec. 942. Removal, relocation, reconditioning, replacement, abandonment.
(a) The applicant, or the person that owns or operates the small wireless facility collocated in the right-of-way, may remove its small wireless facilities at any time from the right-of-way upon not less than 30 days' prior written notice to the county and may cease paying to the county any applicable fees and rates for such use, as of the date of the actual removal of the small wireless facilities. In the event of such removal, the right-of-way shall be, to the extent practicable in the reasonable judgment of the county, restored to its condition prior to the removal. If the applicant fails to return the right-of-way, to the extent practicable in the reasonable judgment of the county, to its condition prior to the removal within 90 days of the removal, the county may, at the sole discretion of the county, restore the right-of-way to such condition and charge the applicant the county's reasonable, documented cost of removal and restoration, plus a penalty not to exceed $500.00. The county may suspend the ability of the applicant to receive any new permits from the county until the applicant has paid the amount assessed for such restoration costs and the penalty assessed, if any; provided, however, that the county shall not suspend such ability of any applicant that has deposited the amount in controversy in escrow pending an adjudication of the merits of the dispute by a court of competent jurisdiction.
(b) If, in the reasonable exercise of police powers, the county determines:
1. A pole or support structure unreasonably interferes with the widening, repair, reconstruction, or relocation of a public road or highway, or
2. Relocation of poles, support structures, or small wireless facilities is required as a result of a public project, the wireless provider shall relocate such poles, support structures, or small wireless facilities pursuant to and in accordance with the following:
a. By the date designated in a written notice from the county that contains a good faith estimate of the date by which the county intends to commence work in or upon the right-of-way so long as the same time frames are applied to all utilities in the right-of-way;
provided, however, that the date designated for relocation shall be at least 45 days after the County provides the written notice to the wireless provider; or
b. Within the time frame that the wireless provider estimates in good faith is reasonably needed to complete the relocation, so long as the wireless provider provides the county written notice of its good faith estimate within 30 days following receipt of the written notice provided by the county this subsection and explains in detail why such wireless provider cannot reasonably complete the relocation by the date designated in the county's written notice.
3. If the wireless provider fails to relocate a pole, support structure or small wireless facility or fails to provide a written good faith estimate of the time needed to relocate the pole, support structure or small wireless within the time period prescribed in this subsection the county shall have the right and privilege, ten days or more after the wireless provider receives written notice from the county, to cut power to or move any support structure or pole located within the right-of-way, as the county may determine to be necessary, appropriate, or useful in order to commence work on the public project.
(c) The wireless provider shall reasonably cooperate with the county to carry out reconditioning work activities in a manner that minimizes interference with the wireless provider's approved use of the facility.
1. The county shall use reasonable efforts to provide the wireless provider with written notice of reconditioning work at least 120 days before such reconditioning work begins. Upon receiving such notice, it shall be the wireless provider's sole responsibility to provide adequate measures to cover, remove, or otherwise protect the wireless provider's communications facility from the consequences of the reconditioning work, including but not limited to paint and debris fallout.
The county reserves the right to require the wireless provider to remove all of the wireless provider's communications facilities from the pole and surrounding premises during reconditioning work, provided that the requirement to remove such is contained in the written notice required by this code section. All costs associated with the protection measures, including temporary removal, shall be the sole responsibility of the wireless provider. If the county fails in good faith to give notice within at least 120 days, it shall not affect the county's rights under this subsection. In all cases, as much notice as possible shall be provided, but less than 30 days' notice shall be prohibited. The county shall provide the wireless provider with a date by which its equipment must be protected or removed.
2. The wireless provider may request a modification of the county procedures for carrying out reconditioning work in order to reduce interference with the wireless provider's operation of its communications facility. If the county agrees to the modification, the wireless provider shall be responsible for all reasonable incremental costs related to the modification.
3. The county shall provide the wireless provider with at least 120 days' written notice of any replacement work before the county may remove the wireless provider's communications facilities. The county shall also promptly notify the wireless provider when the poles have been replaced and the wireless provider can reinstall its equipment. During the replacement work, the wireless provider may maintain a temporary communications facility on the property, or after approval by an authority on any land owned or controlled by an authority in the vicinity of the property. If the property will not accommodate the wireless provider's temporary communications facility or if the parties cannot agree on a temporary location, the wireless provider, at its sole discretion, shall have the right to suspend the applicable permit until the replacement pole is installed, upon 30 days' written notice to the county.
(d) A wireless provider must notify the county of its decision to abandon any small wireless facility, support structure or pole pursuant to the following provisions:
1. If a wireless provider decides to abandon any small wireless facility, support structure, or pole, it shall notify the county in writing as soon as practicable, but no later than 30 days prior to the abandonment.
2. Following receipt of such notice, the authority shall instruct the wireless provider in writing to remove all or any portion of the small wireless facility, support structure, or pole if the authority determines that such removal will be in the best interest of public safety and welfare.
3. If the wireless provider fails to remove the abandoned small wireless facility, support structure, or pole within 90 days after such notice, the authority may do so and recover the actual and reasonable expenses of doing so from the wireless provider, its successors, or its assigns, plus a penalty not to exceed $500.00.
4. The county may suspend the ability of the wireless provider, its successors, or its assigns, as applicable, to receive any new permits from the authority until the wireless provider, its successors, or its assigns, as applicable, have paid the amount assessed for such removal costs and the penalty assessed, if any; provided, however, that the authority shall not suspend such ability of any applicant that has deposited the amount in controversy in escrow pending an adjudication of the merits of the dispute by a court of competent jurisdiction.
5. A small wireless facility that is not operated or a support structure or pole that is not utilized for a continuous period of 12 months shall be considered abandoned, and the owner of such small wireless facility, support structure, or pole shall remove such within 90 days after receipt of written notice from the county notifying such owner of such small wireless facility, support structure, or pole of the abandonment.
6. The county shall send the notice by certified or registered mail, return receipt requested, to such owner at the last known address of such owner of the small wireless facility, support structure, or pole.
7. If the owner does not provide written notice that the small wireless facility has not been out of operation or the support structure or pole has in fact been utilized for a continuous period of 12 months or does not remove such small wireless facility, support structure, or pole within the 90 day period, the authority may remove or cause the removal of such small wireless facility, support structure, or pole pursuant to the terms of its support structure or pole attachment (Ord. No. 19-003, § 1(Exh. A), 10-21-2019)
Sec. 943—950. Reserved.
ARTICLE 10. FLOOD DAMAGE PREVENTION
DIVISION I. GENERAL PROVISIONS
Sec. 1001. Authority.
Article IX, section II of the Constitution of the State of Georgia and O.C.G.A § 36-1-20(a) have delegated the responsibility to local governmental units to adopt regulations designed to promote the public health, safety, and general welfare of its citizenry.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1002. Findings.
(a) The flood hazard areas of Jackson County, Georgia are subject to periodic inundation which results in loss of life and property, health and safety hazards, disruption of commerce and governmental services, extraordinary public expenditures for flood relief and protection, and impairment of the tax base, all of which adversely affect the public health, safety and general welfare.
(b) These flood losses are caused by the occupancy in flood hazard areas of uses vulnerable to floods, which are inadequately elevated, flood-proofed, or otherwise unprotected from flood damages, and by the cumulative effect of obstructions in floodplains causing increases in flood heights and velocities.
(c) The degree of flood protection required by this article is considered reasonable for regulatory purposes and is based on scientific and engineering considerations. Larger floods can and will occur;
flood heights may be increased by man-made or natural causes. This article does not imply that land outside the areas of special flood hazard or uses permitted within such areas will be free from flooding or flood damages. This article shall not create liability on the part of Jackson County, or by any officer or employee thereof for any flood damages that result from reliance on this article or any administrative decision lawfully made hereunder.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1003. Purposes.
It is the purpose of this article to promote the public health, safety and general welfare and to minimize public and private losses due to flood conditions in specific areas by provisions applicable in the unincorporated areas of Jackson County designed to:
(a) Require that uses vulnerable to floods, including facilities, which serve such uses, be protected against flood damage at the time of initial construction;
(b) Restrict or prohibit uses which are dangerous to health, safety and property due to water or erosion hazards, or which increase flood heights, velocities, or erosion;
(c) Control filling, grading, dredging and other development which may increase flood damage or erosion;
(d) Prevent or regulate the construction of flood barriers which will unnaturally divert flood waters or which may increase flood hazards to other lands; and
(e) Control the alteration of natural floodplains, stream channels, and natural protective barriers, which are involved in the accommodation of floodwaters.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1004. Objectives.
The objectives of this article are to:
(a) Protect human life and health;
(b) Minimize damage to public facilities and utilities such as water and gas mains, electric, telephone and sewer lines, streets and bridges located in floodplains;
(c) Help maintain a stable tax base by providing for the sound use and development of flood prone areas in such a manner as to minimize flood blight areas;
(d) Minimize expenditure of public money for costly flood control projects;
(e) Minimize the need for rescue and relief efforts associated with flooding and generally undertaken at the expense of the general public;
(f) Minimize prolonged business interruptions; and
(g) Insure that potential homebuyers are notified that property is in a flood area.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1005. Applicability.
This UDC shall apply to all areas of special flood hazard within unincorporated Jackson County, Georgia.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1006. Definitions.
Unless specifically defined below, words or phrases used in this section shall be interpreted so as to give them the meaning they have in common usage and to give this section its most reasonable application.
Accessory structure: A structure having minimal value and used for parking, storage and other non-habitable uses, such as garages, carports, storage sheds, pole barns, hay sheds and the like.
Addition (to an existing building): Any walled and roofed expansion to the perimeter of a building in which the addition is connected by a common load-bearing wall other than a firewall. Any walled and roofed addition, which is connected by a firewall or is separated by an independent perimeter loadbearing wall, shall be considered "new construction."
Administrator: The director of Public Development for Jackson County, Georgia.
Appeal: A request for a review of the public development director's interpretation of any provision of this article.
Area of shallow flooding: A designated AO or AH zone on a community's flood insurance rate map (FIRM) with base flood depths from one to three feet, and/or where a clearly defined channel does not exist, where the path of flooding is unpredictable and indeterminate, and where velocity flow may be evident.
Area of special flood hazard: The land in the floodplain within a community subject to a one percent or greater chance of flooding in any given year. In the absence of official designation by the Federal Emergency Management Agency, areas of special flood hazard shall be those designated by the local community and referenced in this article.
Base flood: The flood having a one percent chance of being equaled or exceeded in any given year.
Base flood elevation (BFE): The elevation shown on the flood insurance rate map for zones AE, AH, A1-A30, AR, AR/A, AR/AE, AR/A1-A30, AR/AH, AR/AO, V1-V30, and VE that indicates the water surface elevation resulting from a flood that has a one percent chance of equaling or exceeding that level in any given year.
Basement: That portion of a building having its floor sub grade (below ground level) on all sides.
Building: Any structure built for support, shelter, or enclosure for any occupancy or storage.
Critical facility: Any public or private facility, which, if flooded, would create an added dimension to the disaster or would increase the hazard to life and health. Critical facilities include: structures or facilities that produce, use, or store highly volatile, flammable, explosive, toxic, or water-reactive materials; hospitals and nursing homes, and housing for the elderly, which are likely to contain occupants who may not be sufficiently mobile to avoid the loss of life or injury during flood and storm events;
emergency operation centers or data storage centers which contain records or services that may become lost or inoperative during flood and storm events; and generating plants, and other principal points of utility lines.
Development: Any man-made change to improved or unimproved real estate, including, but not limited to, buildings or other structures, mining, dredging, filling, grading, paving, excavating, drilling operations, and storage of materials or equipment.
Elevated building: A non-basement building built to have the lowest floor of the lowest enclosed area elevated above the ground level by means of fill, solid foundation perimeter walls, pilings, columns, piers, or shear walls adequately anchored so as not to impair the structural integrity of the building during a base flood event.
Existing construction: For the purposes of determining rates, structures for which the "start of construction" commenced before the effective date of the initial flood insurance rate maps for that community.
Existing manufactured home park or subdivision: A manufactured home park or subdivision for which the construction of facilities for servicing the lots on which the manufactured homes are to be affixed (including at a minimum the installation of utilities, the construction of streets, and final site grading or the pouring of concrete pads) is completed before June 19, 1986 (i.e., the effective date of the first floodplain management regulations adopted by Jackson County).
Expansion to an existing manufactured home park or subdivision: The preparation of additional sites by the construction of facilities for servicing the lots on which the manufactured homes are to be affixed, including the installation of utilities, the construction of streets, and either final site grading or the pouring of concrete pads.
Flood or flooding: A general and temporary condition of partial or complete inundation of normally dry land areas from: the overflow of inland or tidal waters; or the unusual and rapid accumulation or runoff of surface waters from any source.
Flood hazard boundary map (FHBM): An official map of a community, issued by the Federal Insurance Administration, where the boundaries of areas of special flood hazard have been defined as zone A.
Flood insurance rate map (FIRM): An official map of a community, issued by the Federal Insurance Administration, delineating the areas of special flood hazard and/or risk premium zones applicable to the community.
Flood insurance study: The official report by the Federal Insurance Administration evaluating flood hazards and containing flood profiles and water surface elevations of the base flood.
Floodplain: Any land area susceptible to flooding.
Flood proofing: Any combination of structural and non-structural additions, changes, or adjustments to structures, which reduce or eliminate flood damage to real estate or improved real property, water and sanitary facilities, structures and their contents.
Floodway: The channel of a river or other watercourse and the adjacent land areas that must be reserved in order to discharge the base flood without cumulatively increasing the water surface elevation more than a designated height.
Freeboard: A factor of safety usually expressed in feet above a flood level for purposes of floodplain management. "Freeboard" tends to compensate for the many unknown factors that could contribute to flood heights greater than the height calculated for a selected size flood and floodway conditions, such as wave action, bridge openings, and the hydrological effect of urbanization of the watershed.
Highest adjacent grade: The highest natural elevation of the ground surface, prior to construction, adjacent to the proposed foundation of a building.
Historic structure: Any structure that is: listed individually in the National Register of Historic Places (a listing maintained by the U.S. Department of Interior) or preliminarily determined by the Secretary of the Interior as meeting the requirements for individual listing on the National Register; certified or preliminarily determined by the Secretary of the Interior as contributing to the historical significance of a registered historic district or a district preliminarily determined by the Secretary to qualify as a registered historic district; individually listed on a state inventory of historic places and determined as eligible by states with historic preservation programs which have been approved by the Secretary of the Interior; or individually listed on a local inventory of historic places and determined as eligible by communities with historic preservation programs that have been certified either:
(1) By an approved state program as determined by the Secretary of the Interior; or
(2) Directly by the Secretary of the Interior in states without approved programs.
Lowest floor: The lowest floor of the lowest enclosed area, including basement. An unfinished or flood resistant enclosure, used solely for parking of vehicles, building access, or storage, in an area other than a basement, is not considered a building's lowest floor, provided that such enclosure is not built so as to render the structure in violation of other provisions of this section.
Manufactured home: A building, transportable in one or more sections, built on a permanent chassis and designed to be used with or without a permanent foundation when connected to the required utilities. The term also includes park trailers, travel trailers, and similar transportable structures placed on a site for 180 consecutive days or longer and intended to be improved property.
Manufactured home park or subdivision: A parcel (or contiguous parcels) of land divided into two or more manufactured home lots for rent or sale.
Mean sea level: The average height of the sea for all stages of the tide. It is used as a reference for establishing various elevations within the floodplain. For purposes of the National Flood Insurance Program, the National Geodetic Vertical Datum (NGVD) of 1929 or other datum, to which base flood elevations shown on a community's flood insurance rate map are referenced.
National Geodetic Vertical Datum (NGVD): As corrected in 1929 is a vertical control used as a reference for establishing varying elevations within the floodplain.
New construction: For the purposes of determining insurance rates, structures for which the "start of construction" commenced after the effective date of the initial flood insurance rate map and includes any subsequent improvements to such structures. For floodplain management purposes, "new construction" means structures for which the "start of construction" commenced after June 19, 1986 (i.e., the effective date of the first floodplain management ordinance adopted by Jackson County) and includes any subsequent improvements to such structures.
New manufactured home park or subdivision: A manufactured home park or subdivision for which the construction of facilities for servicing the lots on which the manufactured homes are to be affixed (including at a minimum, the installation of utilities, the construction of streets, and either final site grading or the pouring of concrete pads) is completed after June 19, 1986 (i.e., the effective date of the first floodplain management ordinance adopted by Jackson County).
North American Vertical Datum (NAVD): Has replaced the National Geodetic Vertical Datum of 1929 in existing and future FEMA flood modernization maps.
Recreational vehicle: A vehicle, which is built on a single chassis; 400 square feet or less when measured at the largest horizontal projection; designed to be self-propelled or permanently towable by a light duty truck; and designed primarily not for use as a permanent dwelling but as temporary living quarters for recreational, camping, travel, or seasonal use.
Start of construction: The date the development permit was issued, provided the actual start of construction, repair, reconstruction, or improvement was within 180 days of the permit date. The actual start means the first placement of permanent construction of the structure such as the pouring of slabs or footings, installation of piles, construction of columns, or any work beyond the stage of excavation, and includes the placement of a manufactured home on a foundation. (Permanent construction does not include initial land preparation, such as clearing, grading and filling; nor does it include the installation of streets and/or walkways; nor does it include excavation for a basement, footings, piers or foundations or the erection of temporary forms; nor does it include the installation on the property of buildings appurtenant to the permitted structure, such as garages or sheds not occupied as dwelling units or part of the main structure. (NOTE: accessory structures are NOT exempt from any ordinance requirements).
For a substantial improvement, the actual start of construction means the first alteration of any wall, ceiling, floor, or other structural part of a building, whether or not that alteration affects the external dimensions of the building.
Structure: A walled and roofed building that is principally above ground, a manufactured home, a gas or liquid storage tank.
Subdivision: The division of a single lot into two or more lots for the purpose of sale or development.
Substantial damage: Damage of any origin sustained by a structure whereby the cost of restoring the structure to its before damaged condition would equal or exceed 50 percent of the market value of the structure before the damage occurred.
Substantial improvement: Any reconstruction, rehabilitation, addition, or other improvement of a structure, taking place during a five-year period, in which the cumulative cost equals or exceeds 50 percent of the market value of the structure prior to the "start of construction" of the improvement.
Note: The market value of the structure should be:
(1) The appraised value of the structure prior to the start of the initial repair or improvement; or
(2) In the case of damage, the value of the structure prior to the damage occurring. This term includes structures, which have incurred "substantial damage," regardless of the actual amount of repair work performed.
For the purposes of this definition, "substantial improvement" is considered to occur when the first alteration of any wall, ceiling, floor, or other structural part of the building commences, whether or not that alteration affects the external dimensions of the building. The term does not, however, include:
(1) Those improvements of a structure required to comply with existing violations of state or local health, sanitary, or safety code specifications which are solely necessary to assure safe living conditions and which have been identified by the administrator or his or her designee, and not solely triggered by an improvement or repair project; or
(2) Any alteration of a "historic structure" provided that the alteration will not preclude the structure's continued designation as a "historic structure."
Substantially improved existing manufactured home parks or subdivisions: Where the repair, reconstruction, rehabilitation or improvement of the streets, utilities and pads equals or exceeds 50 percent of the value of the streets, utilities and pads before the repair, reconstruction or improvement commenced.
Variance: A grant of relief from the requirements of this article, which permits construction in a manner otherwise prohibited by this section.
Violation: The failure of a structure or other development to be fully compliant with the community's floodplain management regulations. A structure or other development without the elevation certificate, or other certifications, or other evidence of compliance required by this UDC is presumed to be in violation until such time as that documentation is provided.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1007. Basis for area of special flood hazard.
(a) Flood insurance study. The areas of special flood hazard identified by the Federal Emergency Management Agency in its Flood Insurance Study (FIS), for Jackson County, Georgia and incorporated areas effective December 17, 2010, with accompanying maps and other supporting data and any revision thereto, are adopted by reference and declared a part of this article.
(b) Flood insurance rate maps. The flood insurance rate maps for Jackson County, Georgia and incorporated areas effective December 17, 2010, are adopted as if fully contained within this article and shall be the basis for determining areas of special flood hazard.
(c) Additional areas of special flood hazard. Areas of special flood hazard may also include those areas known to have flooded historically or defined through standard engineering analysis by governmental agencies or private parties but not yet incorporated in a flood insurance study.
(d) Repository. The repository for public inspection of the flood insurance study (FIS), accompanying maps and other supporting data and the flood insurance rate maps is the Jackson County Department of Public Development, 67 Athens Street, Jefferson, Georgia, 30549.
(Ord. No. 17-003, § 1, 10-2-2017) Secs. 1008—1010. Reserved.
DIVISION II. PERMITTING REQUIREMENTS
Sec. 1011. Permit required.
No development activity shall commence within an area regulated by this article until and unless a flood area permit shall have been approved by the public development director. No development activity shall be approved unless it conforms with the provisions of this article prior to the commencement of any development activities. No building or structure shall be constructed within an area regulated by this article until and unless a flood area permit or building permit, or both if required shall have been approved by the public development director. No building or structure shall be approved unless it conforms with the provisions of this article prior to the construction of said building or structure.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1012. Permit procedures.
Application for a flood area permit shall be made to the public development department on forms furnished by the department prior to any development activities, and may include, but not be limited to the following: plans in sufficient number as specified by the department, drawn to scale showing the elevations of the area in question and the nature, location, dimensions, of existing or proposed structures, earthen fill placement, storage of materials or equipment, and drainage facilities.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1013. Specific information required—Application stage.
The following information is required at the application stage:
(a) Elevation in relation to mean sea level (or highest adjacent grade) of the lowest floor, including basement, of all proposed structures;
(b) Elevation in relation to mean sea level to which any non-residential structure will be floodproofed;
(c) Design certification from a registered professional engineer or architect that any proposed non-residential flood-proofed structure will meet the flood-proofing criteria of this article; and
(d) Description of the extent to which any watercourse will be altered or relocated as a result of a proposed development.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1014. Specific information required—Construction stage.
The following information is required at the construction stage:
(a) For all new construction and substantial improvements, the permit holder shall provide to the public development department an as-built certification of the regulatory floor elevation or flood-proofing level immediately after the lowest floor or flood proofing is completed. Any lowest floor certification made relative to mean sea level shall be prepared by or under the direct supervision of a registered land surveyor or professional engineer and certified by same. When flood proofing is utilized for non-residential structures, said certification shall be prepared by or under the direct supervision of a professional engineer or architect and certified by same.
(b) Any work undertaken prior to submission of these certifications shall be at the permit holder's risk. The director of public development shall review the above referenced certification data submitted. Deficiencies detected by such review shall be corrected by the permit holder immediately and prior to further progressive work being allowed to proceed. Failure to submit certification or failure to make said corrections required hereby, shall be cause to issue a stop-work order for the project.
(Ord. No. 17-003, § 1, 10-2-2017) Secs. 1015—1020. Reserved.
DIVISION III. PROVISIONS FOR FLOOD HAZARD REDUCTION
Sec. 1021. General standards.
In all areas of special flood hazard the following provisions are required:
(a) Anchoring. New construction and substantial improvements of existing structures shall be anchored to prevent flotation, collapse or lateral movement of the structure.
(b) Flood-resistant materials. New construction and substantial improvements of existing structures shall be constructed with materials and utility equipment resistant to flood damage.
(c) Construction methods and practices. New construction or substantial improvements of existing structures shall be constructed by methods and practices that minimize flood damage.
(d) Heating and air conditioning. All heating and air conditioning equipment and components (including ductwork), all electrical, ventilation, plumbing, and other service facilities shall be designed and/or located so as to prevent water from entering or accumulating within the components during conditions of flooding.
(e) Manufactured homes. Manufactured homes shall be anchored to prevent flotation, collapse, or lateral movement. Methods of anchoring may include, but are not limited to, use of over-thetop or frame ties to ground anchors. This standard shall be in addition to and consistent with applicable state requirements for resisting wind forces.
(f) Water supply. New and replacement water supply systems shall be designed to minimize or eliminate infiltration of flood waters into the system.
(g) Sewage systems. New and replacement sanitary sewage systems shall be designed to minimize or eliminate infiltration of flood waters into the systems and discharges from the systems into flood waters.
(h) On-site sewage disposal systems. On-site waste disposal systems shall be located and constructed to avoid impairment to them or contamination from them during flooding.
(i) Nonconformities. Any alteration, repair, reconstruction or improvement to a structure, which is not compliant with the provisions of this UDC, shall be undertaken only if the non-conformity is not furthered, extended or replaced.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1022. Elevated buildings.
(a) In all areas of special flood hazard, all new construction or substantial improvements of existing structures that include any fully enclosed area located below the lowest floor formed by foundation and other exterior walls shall be designed so as to be an unfinished or flood resistant enclosure. The enclosure shall be designed to equalize hydrostatic flood forces on exterior walls by allowing for the automatic entry and exit of floodwater.
(b) Designs for complying with this requirement must either be certified by a professional engineer or architect or meet the following minimum criteria:
1. Provide a minimum of two openings having a total net area of not less than one square inch for every square foot of enclosed area subject to flooding;
2. The bottom of all openings shall be no higher than one foot above grade; and,
3. Openings may be equipped with screens, louvers, valves or other coverings or devices provided they permit the automatic flow of floodwater in both direction.
(c) So as not to violate the "lowest floor" criteria of this UDC, the unfinished or flood resistant enclosure shall only be used for parking of vehicles, limited storage of maintenance equipment used in connection with the premises, or entry to the elevated area, and
(d) The interior portion of such enclosed area shall not be partitioned or finished into separate rooms.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1023. New construction and/or substantial improvements.
In all areas of special flood hazard the following provisions are required for new construction and/or substantial improvements:
(a) Where base flood elevation data are available, new construction and/or substantial improvement of any structure or manufactured home shall have the lowest floor, including basement, elevated no lower than two feet above the base flood elevation. Should solid foundation perimeter walls be used to elevate a structure, openings sufficient to facilitate equalization of flood hydrostatic forces on both sides of exterior walls shall be provided in accordance with standards of this article for "elevated buildings."
(b) All heating and air conditioning equipment and components (including ductwork), all electrical, ventilation, plumbing, and other service facilities shall be elevated at or above two feet above the base flood elevation.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1024. Non-residential construction.
(a) New construction and/or the substantial improvement of any structure located in A1-30, AE, or AH zones, may be flood-proofed in lieu of elevation. The structure, together with attendant utility and sanitary facilities, must be designed to be water tight to two feet above the base flood elevation, with walls substantially impermeable to the passage of water, and structural components having the capability of resisting hydrostatic and hydrodynamic loads and the effect of buoyancy.
(b) A registered professional engineer or architect shall certify that the design and methods of construction are in accordance with accepted standards of practice for meeting the provisions above, and shall provide such certification to the public development director as set forth in this article.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1025. Manufactured homes.
Where base flood elevation data are available:
(a) All manufactured homes placed and/or substantially improved on:
(1) Individual lots or parcels;
(2) In new and/or substantially improved manufactured home parks or subdivisions;
(3) In expansions to existing manufactured home parks or subdivisions; or
(4) On a site in an existing manufactured home park or subdivision where a manufactured home has incurred "substantial damage" as the result of a flood, must have the lowest floor including basement, elevated no lower than two feet above the base flood elevation.
(b) Manufactured homes placed and/or substantially improved in an existing manufactured home park or subdivision may be elevated so that either: the lowest floor of the manufactured home is elevated no lower than two feet above the level of the base flood elevation; or the manufactured home chassis is elevated and supported by reinforced piers (or other foundation elements of at least an equivalent strength) of no less than 36 inches in height above grade.
(c) All manufactured homes must be securely anchored to an adequately anchored foundation system to resist flotation, collapse and lateral movement.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1026. Recreational vehicles.
All recreational vehicles placed on sites must either:
(a) Be on the site for fewer than 180 consecutive days;
(b) Be fully licensed and ready for highway use, (a recreational vehicle is ready for highway use if it is licensed, on its wheels or jacking system, attached to the site only by quick disconnect type utilities and security devices, and has no permanently attached structures or additions); or
(c) The recreational vehicle must meet all the requirements for "new construction," including the anchoring and elevation requirements of this article.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1027. Floodway.
Located within areas of special flood hazard established in this article are areas designated as floodway. A floodway may be an extremely hazardous area due to velocity floodwaters, debris or erosion potential. In addition, the area must remain free of encroachment in order to allow for the discharge of the base flood without increased flood heights. Therefore, the following provisions shall apply:
(a) Encroachments are prohibited, including earthen fill, new construction, substantial improvements or other development within the regulatory floodway. Development may be permitted however, provided it is demonstrated through hydrologic and hydraulic analyses performed in accordance with standard engineering practice that the encroachment shall not result in any increase in flood levels or floodway widths during a base flood discharge. A registered professional engineer must provide supporting technical data and certification thereof.
(b) Only if the provisions of this section are satisfied, then any new construction or substantial improvement shall comply with all other applicable flood hazard reduction provisions of this article.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1028. Building standards for streams without established base flood elevations and/or floodway (A-zones).
Located within the areas of special flood hazard established in this article, are streams for which no base flood data have been provided (A-zones), or where base flood data have been provided but a floodway has not been delineated. When base flood elevation data or floodway data have not been provided in accordance with this section, then the administrator shall obtain, review, and reasonably utilize any scientific or historic base flood elevation and floodway data available from a federal, state, or other source, in order to administer the provisions of this article. Only if data are not available from these sources, then the following provisions apply:
(a) No encroachments, including structures or fill material, shall be located within an area equal to the width of the stream or 20 feet, whichever is greater, measured from the top of the stream bank, unless certification by a registered professional engineer is provided demonstrating that such encroachment shall not result in more than a one foot increase in flood levels during the occurrence of the base flood discharge.
(b) In special flood hazard areas without base flood elevation data, new construction and substantial improvements of existing structures shall have the lowest floor of the lowest enclosed area (including basement) elevated no less than three feet above the highest adjacent grade at the building site. (NOTE: Require the lowest floor to be elevated one foot above the estimated base flood elevation in A-zone areas where a limited detail study has been completed). Openings sufficient to facilitate the unimpeded movements of floodwaters shall be provided in accordance with standards of this section for "elevated buildings."
(c) All heating and air conditioning equipment and components (including ductwork), all electrical, ventilation, plumbing, and other service facilities shall be elevated no less than three feet above the highest adjacent grade at the building site.
(d) The administrator shall certify the lowest floor elevation level and the record shall become a permanent part of the permit file.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1029. Standards for areas of special flood hazard (zones AE) with established base flood elevations without designated floodways.
Located within the areas of special flood hazard established in this article, where streams with base flood elevations are provided but no floodways have been designated (zones AE), the following provisions apply:
(a) No encroachments, including fill material, new structures or substantial improvements shall be located within areas of special flood hazard, unless certification by a registered professional engineer is provided demonstrating that the cumulative effect of the proposed development, when combined with all other existing and anticipated development, will not increase the water surface elevation of the base flood more than one foot at any point within the community. The engineering certification should be supported by technical data that conforms to standard hydraulic engineering principles.
(b) New construction or substantial improvements of buildings shall be elevated or flood-proofed to elevations established in accordance with this article.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1030. Standards for areas of shallow flooding (AO zones).
Areas of special flood hazard established in this section may include designated "AO" shallow flooding areas. These areas have base flood depths of one to three feet above ground, with no clearly defined channel. The following provisions apply:
(a) All new construction and substantial improvements of residential and non-residential structures shall have the lowest floor, including basement, elevated to the flood depth number specified on the flood insurance rate map (FIRM), above the highest adjacent grade. If no flood depth number is specified, the lowest floor, including basement, shall be elevated at least three feet above the highest adjacent grade. Openings sufficient to facilitate the unimpeded movements of flood waters shall be provided in accordance with standards of this article for "elevated buildings." The administrator shall certify the lowest floor elevation level and the record shall become a permanent part of the permit file.
(b) New construction or the substantial improvement of a non-residential structure may be flood-proofed in lieu of elevation. The structure, together with attendant utility and sanitary facilities, must be designed to be water tight to the specified FIRM flood level plus two feet, above highest adjacent grade, with walls substantially impermeable to the passage of water, and structural components having the capability of resisting hydrostatic and hydrodynamic loads and the effect of buoyancy. A registered professional engineer or architect shall certify that the design and methods of construction are in accordance with accepted standards of practice for meeting the provisions above, and shall provide such certification to the official as set forth in this paragraph and as required in this article.
(c) Drainage paths shall be provided to guide floodwater around and away from any proposed structure.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1031. Subdivisions.
(a) All subdivision and/or development proposals shall be consistent with the need to minimize flood damage.
(b) All subdivision and/or development proposals shall have public utilities and facilities such as sewer, gas, electrical and water systems located and constructed to minimize flood damage.
(c) All subdivision and/or development proposals shall have adequate drainage provided to reduce exposure to flood hazards.
(d) For subdivisions and/or developments greater than 50 lots or five acres, whichever is less, base flood elevation data shall be provided for subdivision and all other proposed development, including manufactured home parks and subdivisions. Any changes or revisions to the flood data adopted herein and shown on the FIRM shall be submitted to FEMA for review as a conditional letter of map revision (CLOMR) or conditional letter of map amendment (CLOMA), whichever is applicable. Upon completion of the project, the developer is responsible for submitting the "as-built" data to FEMA in order to obtain the final LOMR.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1032. Critical facilities.
Critical facilities shall not be located in the 100-year floodplain or the 500-year floodplain. All ingress and egress from any critical facility must be protected to the 500-year flood elevation.
(Ord. No. 17-003, § 1, 10-2-2017) Secs. 1033—1040. Reserved.
DIVISION IV. VARIANCES AND APPEALS
Sec. 1041. Variance procedures.
(a) The board of adjustment shall hear and decide requests for appeals or variance from the requirements of this article. Procedures for consideration of variances to the requirements of this article shall be the same as provided in article 14 of this UDC for variances.
(b) The board of adjustment shall hear and decide appeals when it is alleged an error in any requirement, decision, or determination is made by the public development director, in the enforcement or administration of this article. Procedures for consideration of appeals shall be the same as provided in article 14 of this UDC for appeals.
(c) Any person aggrieved by the decision of the board of adjustment may appeal such decision to the Superior Court of Jackson County, as provided in O.C.G.A. § 5-4-1.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1042. Criteria and conditions for variances.
The provisions of this article are minimum standards for flood loss reduction; therefore, any deviation from the standards must be weighed carefully. In reviewing requests for variances, the board of adjustment shall consider all technical evaluations, relevant factors, and the following standards in addition to others in this UDC. A variance shall be issued only when consistent with the following criteria and conditions:
(a) A finding of good and sufficient cause is made.
(b) A determination is made that failure to grant the variance would result in exceptional hardship.
(c) A determination is made that the granting of a variance will not result in increased flood heights, additional threats to public safety, extraordinary public expense, create nuisance, cause fraud on or victimization of the public, or conflict with existing local laws or ordinances.
(d) Variances shall not be issued within any designated floodway if any increase in flood levels during the base flood discharge would result.
(e) Variances shall only be issued upon a determination that the variance is the minimum necessary, considering the flood hazard, to afford relief.
(f) Variances may be issued for the repair or rehabilitation of historic structures upon a determination that the proposed repair or rehabilitation will not preclude the structure's continued designation as a historic structure and the variance is the minimum to preserve the historic character and design of the structure. In the instance of an historic structure, a determination that the variance is the minimum necessary so as not to destroy the historic character and design of the building.
(g) Variances may be issued for development necessary for the conduct of a functionally dependent use, provided the criteria of this UDC are met, no reasonable alternative exists, and the development is protected by methods that minimize flood damage during the base flood and create no additional threats to public safety.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1043. Conditional approval permitted.
Upon consideration of the factors listed above and the purposes of this UDC, the board of adjustment may attach such conditions to the granting of variances as it deems necessary to further the purposes of this article.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1044. Actions following variance approval.
(a) Any applicant to whom a variance is granted shall be given written notice specifying the difference between the base flood elevation and the elevation of the proposed lowest floor and stating that the cost of flood insurance will be commensurate with the increased risk to life and property resulting from the reduced lowest floor elevation.
(b) The public development director shall maintain the records of all appeal actions and report any variances to the Federal Emergency Management Agency upon request.
(Ord. No. 17-003, § 1, 10-2-2017) Secs. 1045—1050. Reserved.
DIVISION V. ADMINISTRATION AND LEGAL STATUS PROVISIONS
Sec. 1051. Administration.
The public development director is hereby appointed to administer and implement the provisions of this article. Duties of the public development director shall include, but shall not be limited to the following:
(a) Review proposed development to assure that the permit requirements of this article have been satisfied.
(b) Review proposed development to assure that all necessary permits have been received from governmental agencies from which approval is required by Federal or State law, including section 404 of the Federal Water Pollution Control Act Amendments of 1972, 33 U.S.C. 1334.
Require that copies of such permits be provided and maintained on file.
(c) Review all permit applications to determine whether proposed building sites will be reasonably safe from flooding.
(d) When base flood elevation data or floodway data have not been provided in accordance with this article, then the administrator shall obtain, review and reasonably utilize any base flood elevation and floodway data available from a federal, state or other sources in order to administer the provisions of this article.
(e) Review and record the actual elevation in relation to mean sea level (or highest adjacent grade) of the lowest floor, including basement, of all new or substantially improved structures in accordance with this section.
(f) Review and record the actual elevation, in relation to mean sea level to which any new or substantially improved structures have been flood-proofed, in accordance with this article.
(g) When flood-proofing is utilized for a structure, the administrator shall obtain certification of design criteria from a registered professional engineer or architect in accordance with this article.
(h) Make substantial damage determinations following a flood event or any other event that causes damage to structures in flood hazard areas.
(i) Notify adjacent communities and the Georgia Department of Natural Resources prior to any alteration or relocation of a watercourse and submit evidence of such notification to the Federal Emergency Management Agency (FEMA).
(j) For any altered or relocated watercourse, submit engineering data/analysis within six months to the FEMA to ensure accuracy of community flood maps through the letter of map revision process. Assure flood carrying capacity of any altered or relocated watercourse is maintained.
(k) Make interpretations of this article. In the interpretation and application of this article all provisions shall be: considered as minimum requirements; liberally construed in favor of the county, and; deemed neither to limit nor repeal any other powers granted under state statutes.
Where interpretation is needed as to the exact location of boundaries of the areas of special flood hazard (for example, where there appears to be a conflict between a mapped boundary and actual field conditions) the administrator shall make the necessary interpretation. Any person contesting the location of the boundary shall be given a reasonable opportunity to appeal the interpretation as provided in this article. In the interpretation and application of this UDC all provisions shall be:
(1) Considered as minimum requirements;
(2) Liberally construed in favor of the city; and
(3) Deemed neither to limit nor repeal any other powers granted under state statutes.
(l) All records pertaining to the provisions of this article shall be maintained in the office of the administrator and shall be open for public inspection.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1052. Abrogation and greater restrictions.
This article is not intended to repeal, abrogate, or impair any existing ordinance, easements, covenants, or deed restrictions. However, where this article and another conflict or overlap, whichever imposes the more stringent restrictions shall prevail.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1053. Warning and disclaimer of liability.
The degree of flood protection required by this article is considered reasonable for regulatory purposes and is based on scientific and engineering considerations. Larger floods can and will occur;
flood heights may be increased by man-made or natural causes. This article does not imply that land outside the areas of special flood hazard or uses permitted within such areas will be free from flooding or flood damages. This article shall not create liability on the part of Jackson County, or by any officer or employee thereof for any flood damages that result from reliance on this article or any administrative decision lawfully made hereunder.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1054. Penalties for violation.
Failure to comply with the provisions of this article or with any of its requirements, including conditions and safeguards established in connection with grants of variance shall constitute a violation.
Any person who violates this UDC or fails to comply with any of its requirements shall be subject to the provisions of the Code of Jackson County. Nothing herein contained shall prevent Jackson County from taking such other lawful actions as is necessary to prevent or remedy any violation.
(Ord. No. 17-003, § 1, 10-2-2017) Secs. 1055—1060. Reserved.
ARTICLE 11. STORMWATER MANAGEMENT
DIVISION I. GENERAL PROVISIONS
Sec. 1101. Title.
This article shall be known as the "Jackson County Stormwater Management Ordinance."
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1102. Findings.
(a) Land development projects and other land use conversions, and their associated changes to land cover, permanently alter the hydrologic response of local watersheds and increase stormwater runoff rates and volumes, which in turn increase flooding, stream channel erosion, and sediment transport and deposition.
(b) Land development projects and other land use conversions also contribute to increased nonpoint source pollution and degradation of receiving waters.
(c) The impacts of post-development stormwater runoff quantity and quality can adversely affect public safety, public and private property, drinking water supplies, recreation, fish and other aquatic life, property values and other uses of lands and waters.
(d) These adverse impacts can be controlled and minimized through regulation of stormwater runoff quantity and quality from land development by the use of structural facilities as well as nonstructural measures, such as the conservation of greenspace.
(e) Compliance by local governments in the state of Georgia with a number of both state and federal laws, regulations and permits is mandated to address the impacts of post-development stormwater runoff quality and nonpoint source pollution.
(f) It is reasonable to establish this set of stormwater management requirements to regulate postdevelopment stormwater runoff for protecting local water resources from degradation. The regulation of post-development stormwater runoff discharges in order to control and minimize increases in stormwater runoff rates and volumes, post-construction soil erosion and sedimentation, stream channel erosion and nonpoint source pollution associated with post-development stormwater runoff is in the public interest.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1103. Purpose.
The purpose of this article is to protect, maintain and enhance the public health, safety, environment and general welfare by establishing minimum requirements and procedures to control the adverse effects of post-development stormwater runoff and nonpoint source pollution associated with development.
Proper management of post-development stormwater runoff will minimize damage to public and private property and infrastructure, safeguard the public health, safety, environment and general welfare and protect water and aquatic resources.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1104. Definitions.
Applicant: A person submitting a stormwater management plan for approval.
As-built survey drawings: Drawings specifying the dimensions, location, fixtures, elements, sizes, capacities and operational capabilities of streets and stormwater structures and facilities, and water and sewer systems, as they have been constructed.
Bioretention: A practice to manage and treat stormwater runoff by using a conditioned planting soil bed and planting materials to filter runoff stored within a shallow depression. The method combines physical filtering and adsorption with biological processes.
Channel: A natural or artificial watercourse with a definite bed and banks that conducts continuously or periodically flowing water.
Clean Water Act: The Federal Water Pollution Control Act (33 U.S.C. § 1251 et seq.), and any subsequent amendments thereto.
Conservation easement: An agreement between a land owner and the local jurisdiction or other government agency or land trust that permanently protects open space or greenspace on the owner's land by limiting the amount and type of development that can take place, but continues to leave the remainder of the fee interest in private ownership.
Construction activity: Activities subject to the Georgia Erosion and Sedimentation Control Act or NPDES general construction permits. These include construction projects resulting in land disturbance.
Such activities include but are not limited to clearing and grubbing, grading, excavating, and demolition.
Conveyance: An aboveground or underground natural or man-made drainage feature, that provides for the collection and movement of stormwater, and shall include but not be limited to concrete or metal pipes, ditches, depressions, swales, roads with drainage systems, highways, county streets, curbs, gutters, inlets, catch basins, piped storm drains, pumping facilities, structural stormwater controls, drainage channels, reservoirs, rights-of-way, storm drains, culverts, street gutters, oil/water separators, modular pavements and other similar drainage structures.
County: Jackson County and its departments, employees and agents as may have duties and responsibilities for administering and enforcing all stormwater management activities and implementation of the provisions of this article.
County separate storm sewer system: Any conveyance of system of conveyances which is: owned or operated by the county; not a combined sewer; and not part of a publicly owned treatment works.
Detention: The temporary storage of stormwater runoff in a stormwater management facility for the purpose of controlling peak discharge.
Detention facility: A retention basin or structure designed for temporary storage of stormwater runoff and gradual release of stored water at controlled rates.
Developer: A person who undertakes land development activities.
Development: A land development or land development project; the term "development" also encompasses "redevelopment."
Drainage: A general term applied to the removal of surface or subsurface water from a given area either by gravity or by pumping; most commonly applied to surface water.
Drainage easement: An easement appurtenant or attached to a tract or parcel of land allowing the owner of adjacent tracts or other persons to discharge stormwater runoff onto the tract or parcel of land subject to the terms of the drainage easement.
Drainage structure: A device composed of a virtually non-erodible material such as concrete, steel, plastic or other such material that conveys water from one place to another by intercepting the flow and carrying it to a release point for stormwater management, drainage control or flood control purposes.
Drainage system: The surface and subsurface system for the removal of water from the land, including both the natural elements of streams, marshes, swales and ponds, whether of an intermittent or continuous nature, and the man-made element which includes culverts, ditches, channels, detention facilities and the storm sewer system.
Dry well: A small excavated pit backfilled with aggregate, usually pea gravel or stone. Dry wells function as infiltration systems used to control runoff from building rooftops. Another special application of dry wells is modified catch basins, where inflow is a form of direct surface runoff. Dry wells provide the majority of treatment by processes related to soil infiltration, including absorption, trapping, filtering, and bacterial degradation.
Erosion and sedimentation control plan: A plan designed to minimize the accelerated erosion and sediment runoff at a site during land disturbance activities.
Extended detention: The detention of stormwater runoff for an extended period, typically 24 hours or greater.
Extreme flood protection: Measures employed to prevent adverse impacts from large low-frequency storm events with a return frequency of 100 years or more.
Filter strip: Typically, a band of close-growing vegetation, usually grass, planted between pollutant source areas and a downstream receiving waterbody. Vegetation can filter sediment from runoff. Thus grass strips can be used to remove sediment from surface runoff. Vegetation also slows the velocity of runoff and helps maintain the infiltration capacity of a soil.
Flooding: A volume of surface water that is too great to be confined within the banks or walls of a conveyance or stream channel and that overflows onto adjacent lands.
Georgia Stormwater Management Manual: A three-volume set which provides policy and technical details to implement this article. The manual may be revised from time to time but at the time this article is adopted includes: Volume 1: Local Government Guide (2016 Editions); Volume 2: Technical Handbook (2016 Edition); and Volume 3; Pollution Prevention Guidebook (2012).
Greenspace or open space: Permanently protected areas of a site that are preserved in a natural, undisturbed state. Greenspace encompasses "open space." Land conservation and impervious cover reduction is a major goal of open space.
Hotspot: Any area where the use of the land has the potential to generate highly contaminated runoff characterized by concentrations of pollutants in excess of those typically found in stormwater.
Hydrologic soil group (HSG): A natural resource conservation service classification system in which soils are categorized into four runoff potential groups. The groups range from "group a" soils, with high permeability and little runoff produced, to "group d" soils, which have low permeability rates and produce significantly more runoff.
Impervious cover: A surface composed of any material that significantly impedes or prevents the natural infiltration of water into soil. Impervious surfaces include, but are not limited to, rooftops, buildings, streets and roads, and any concrete or asphalt surface.
Industrial stormwater permit: A National Pollutant Discharge Elimination System (NPDES) permit issued to an industry or group of industries that regulates the pollutant levels associated with industrial stormwater discharges or specifies on-site pollution control strategies.
Infiltration: The process by which stormwater runoff percolates into the subsoil.
Infiltration trench: An excavated trench that has been back-filled with stone to form a subsurface basin. Stormwater runoff is diverted into the trench and is stored until it can be infiltrated into the soil, usually over a period of several days. An infiltration trench may include pretreatment such as vegetated filter strips or grassed swales.
Inspection and maintenance agreement: A written agreement providing for the long-term inspection and maintenance of stormwater management facilities and practices on a site or, with respect to a land development project, which when properly recorded in the deed records constitutes a restriction on the title to a site or other land involved in a land development project.
Jurisdictional wetland: An area that is inundated or saturated by surface water or groundwater at a frequency and duration sufficient to support a prevalence of vegetation typically adapted for life in saturated soil conditions, commonly known as hydrophytic vegetation.
Land development: Any alteration to the land including, but not limited to, clearing, cutting, digging, grubbing, stripping, removal of vegetation, dredging, grading, excavating, transporting and filling of land, construction, paving and any installation of impervious cover.
Land development activities: Those actions or activities that comprise, facilitate or result in land development.
Land development project: A specific land development undertaking.
Level spreader: Typically, an outlet designed to convert concentrated runoff to sheet flow and disperse it uniformly across a slope to prevent erosion. Level spreaders can be used to convey sheet flow runoff from lawn areas within graded areas to bioretention facilities and transition areas.
Low-impact development (LID): The integration of site ecological and environmental goals and requirements into all phases of urban planning and design from the individual lot level to the entire watershed. In the context of this article, low-impact development is a set of stormwater design practices that are non-structural stormwater controls, specifically stormwater better site design practices.
National Pollutant Discharge Elimination System (NPDES) stormwater discharge permit: A permit issued by the Georgia EPD under authority delegated pursuant to 33 USC § 1342(b) that authorizes the discharge of pollutants to waters of the United States, whether the permit is applicable on an individual, group, or general area-wide basis.
Natural, undisturbed conditions: For redevelopment projects or where there are no flooding concerns, this term shall mean the condition of the site immediately prior to the implementation of the proposed project.
New development: A land development activity on a previously undisturbed site that has been maintained in a natural state.
Nonpoint source pollution: A form of water pollution that does not originate from a discrete point such as a sewage treatment plant or industrial plant discharge, but involves the transport of pollutants such as sediment, fertilizers, pesticides, heavy metals, oil, grease, bacteria, organic materials and other contaminants from land to surface water and groundwater via mechanisms such as precipitation, stormwater runoff and leaching. Nonpoint source pollution is a by-product of land use practices such as agricultural, silvicultural, mining, construction and subsurface disposal as well as from urban runoff sources.
Nonstructural stormwater management practice or nonstructural practice: Any natural or planted vegetation or other nonstructural component of the stormwater management plan that enhances stormwater quantity and/or quality control or other stormwater management benefits and includes, but is not limited to, riparian buffers, greenspace areas, overland flow filtration areas, natural basins and vegetated channels.
Off-site facility: A stormwater management facility located outside the boundaries of a development site.
On-site facility: A stormwater management facility located within the boundaries of a development site.
Overbank flood protection: Measures employed to prevent an increase in the frequency and magnitude of out-of-bank flooding, that is, flow events that exceed the capacity of the channel and enter the floodplain. Such measures are intended to protect downstream properties from flooding during a two-year through 25-year frequency storm events.
Owner: The legal or beneficial owner of a site including, but not limited to, a mortgagee or vendee in possession, receiver, executor, trustee, lessee or other person, firm or corporation in control of the site.
Permeable: Soil or other material that allows the infiltration or passage of water or other liquids.
Permit: The permit issued by Jackson County to an applicant that is required for conducting any land development activity.
Person: Except to the extent exempted from this article, any individual, partnership, firm, association, joint venture, public or private corporation, trust, estate, commission, board, public or private institution, utility, cooperative, city, county or other political subdivision of the state, any interstate body or any other legal entity.
Pollutant: Anything that causes or contributes to pollution. Pollutants may include, but are not limited to: paints, varnishes, and solvents; petroleum hydrocarbons; automotive fluids; cooking grease;
detergents (biodegradable or otherwise); degreasers; cleaning chemicals; non-hazardous liquid and solid wastes and yard wastes; refuse, rubbish, garbage, litter, or other discarded or abandoned objects and accumulations, so that same may cause or contribute to pollution; floatables; pesticides, herbicides, and fertilizers; liquid and solid wastes; process waste water and wash water; sewage, fecal coliform and pathogens; dissolved and particulate metals; animal wastes; wastes and residues that result from constructing a building or structure; concrete and cement; and noxious or offensive matter of any kind.
Pollution: The man-made or man-induced alteration of the chemical, physical, biological, thermal and radiological integrity of water.
Post-development: The period, or conditions that may reasonably be expected to exist, following completion of land development activity on a site as the context may require.
Pre-development: The period, or conditions that exist on a site, prior to commencement of a land development project and at the time that plans for development of a site are approved by Jackson County. Where phased development or plan approval occurs, for example, preliminary grading and installation of roads and utilities, the existing site conditions at the time prior to commencement of any development activity shall establish pre-development conditions.
Premises: Any building, lot, parcel of and/or portion of land whether improved or unimproved, including adjacent sidewalks and parking strips.
Project: A land development project.
Redevelopment: A land development project on a previously developed site, but excluding ordinary maintenance, remodeling of existing buildings, resurfacing of paved areas, and exterior alterations or improvements that do not materially increase or concentrate stormwater runoff or cause additional nonpoint source pollution.
Regional stormwater management facility or regional facility: Stormwater management facilities designed to control stormwater runoff from multiple properties where the owners or developers of the individual properties may assist in financing the facility and the requirement for on-site stormwater management facilities is either eliminated or reduced.
Runoff: Stormwater runoff.
Site: A parcel of land being developed or the portion thereof on which a land development project is located.
Stormwater better site design: Nonstructural site design approaches and techniques that can reduce the impact of a site on the watershed and can provide for nonstructural stormwater management.
Stormwater better site design includes conserving and protecting natural areas and greenspace, reducing impervious cover and using natural features for stormwater management.
Stormwater credits for better site design: A set of stormwater "credits" can be used to provide developers and site designers an incentive to implement better site design practices that can reduce the volume of stormwater runoff and minimize the pollutant loads from a site. The credit system directly translates into cost savings to the developer by reducing the size of structural stormwater control and conveyance facilities.
Stormwater management: The collection, conveyance, storage, treatment and disposal of stormwater runoff in a manner intended to prevent increased flood damage, stream bank channel erosion and habitat and water quality degradation, and to enhance and promote public health, safety and general welfare.
Stormwater management facility: Any infrastructure that controls or conveys stormwater runoff.
Stormwater management measure: Any stormwater management facility or nonstructural stormwater practice.
Stormwater management plan: A document describing the manner in which existing runoff characteristics will be affected by a land development project and containing measures for complying with the provisions of this article.
Stormwater management system: The full array of structural and nonstructural stormwater management facilities and practices used to capture, convey and control the quantity and quality of the stormwater runoff from a site.
Stormwater retrofit: A stormwater management practice designed for a developed site that previously had either no stormwater management practice in place or a practice inadequate to meet the stormwater management requirements of the site.
Stormwater runoff: The flow of surface water resulting from precipitation.
Structural stormwater control: A structural stormwater management facility or device that controls stormwater runoff and changes the characteristics of that runoff including, but not limited to, the quantity and quality, the period of release or the velocity of flow of such runoff.
Subdivision: The division of a tract or parcel of land resulting in one or more new lots or building sites for the purpose, whether immediately or in the future, of sale, other transfer of ownership or land development, and includes divisions of land resulting from or made in connection with the layout or development of a new street or roadway or a change in an existing street or roadway.
Swale: An open drainage channel designed to detain or infiltrate stormwater runoff. Grassed swales consist of two types: the dry swale, which provides both quantity (volume) and quality control by facilitating stormwater infiltration; and the wet swale, which uses residence time and natural growth to reduce peak discharge and provide water quality treatment before discharge to a downstream location.
(Ord. No. 17-003, § 1, 10-2-2017; Ord. No. 19-002, 10-21-2019) Sec. 1105. Applicability.
(a) No person, owner or developer shall perform any land development activities without first meeting the applicable requirements of this article prior to commencing the proposed activity.
(b) Unless specifically exempted by this article, all persons proposing development or construction in the unincorporated portion of the county shall prepare and submit a stormwater management plan for approval by the director of public development as a part of the land-disturbing and/or development permitting process required by this UDC, (article 8 UDC) and shall also comply with all applicable requirements of this article.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1106. Exemptions.
The following activities are exempt from this article:
(a) Individual single-family or duplex residential lots that are not part of a subdivision or phased development project;
(b) Additions or modifications to existing single-family or duplex residential structures;
(c) Agricultural or silvicultural land management activities within areas lawfully used or zoned for these activities;
(d) Repairs to any stormwater management facility or practice deemed necessary by the public development director; and
(e) Land disturbing activity conducted by local, state, authority, or federal agencies, solely to respond to an emergency need to protect life, limb, or property or conduct emergency repairs.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1107. Approval of stormwater management plan.
No final plat for a major subdivision, no land-disturbance or development permit, and no building permit shall be approved or issued until and unless the stormwater management plan, if required by this article, has been reviewed and approved by the director of public development.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1108. Installation of an adequate drainage system.
(a) An adequate drainage system, including necessary ditches, pipes, culverts, drains, inlets, or other stormwater management features which may include better sign design practices, shall be provided for the proper drainage or infiltration of all surface water on all development and construction sites unless specifically exempted by this article.
(b) The location and size of all proposed drainage improvements shall be designed in accordance with and meet all standards relating to stormwater drainage under this article and technical standards of this UDC as applicable.
(c) Stormwater drainage facilities shall be installed in accordance with the approved stormwater management plan. Construction of the stormwater system shall be initiated as part of the grading of the site. Stormwater detention facilities/ponds shall be constructed to have a minimum of four to one side slopes. Stormwater detention facilities/ponds are to be broader, shallower and flatter for ease of maintenance and for aesthetic purposes. Stormwater detention facilities shall be constructed prior to the installation of any other site improvements, and may be utilized under proper design as sedimentation basins during development. Installation of all other storm drainage pipes, culverts, headwalls, and ditches, shall be coordinated with the construction of streets and other site improvements, as appropriate.
(Ord. No. 17-003, § 1, 10-2-2017; Ord. No. 22-004, § 2, 5-16-2022) Sec. 1109. System maintenance.
(a) It shall be the responsibility of the developer to maintain all facilities required by the stormwater management plan during construction and for a two-year maintenance period following approval of the final subdivision plat or issuance of a certificate of occupancy, as applicable. The developer shall be responsible for removing temporary structures or facilities at the completion of the construction.
(b) The owner of the property shall be responsible for maintaining the permanent stormwater management facilities identified by the stormwater management plan to remain after construction is complete, following the two-year maintenance period.
(c) Should an owner or developer, whichever is the responsible party, fail to maintain the stormwater management facilities in a state of service intended by the stormwater management plan, then the public development department shall notify the responsible party in writing of the deficiencies and specific minimum maintenance requirements to remedy such deficiencies.
(d) If the responsible party fails to perform the required maintenance work within a reasonable period of time (30 days maximum), then the owner shall be in violation of the provisions of this UDC.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1110. Location of stormwater detention facilities.
(a) In residential subdivisions, any detention facility must be located on a separate lot and owned by a homeowners' association, which shall be responsible for its maintenance and continuing operation. The lot need not meet minimum lot size requirements for the subdivision.
(b) In nonresidential subdivisions, any detention facility may be located on a separate lot and owned by a property owners' association, which
shall be responsible for its maintenance and continuing operation; or located on each lot within the subdivision and constructed when the lot is
developed.
(c) In multi-family and nonresidential development projects, separate detention facilities shall be provided for each development. The owner of
the property shall be responsible for maintenance and continuing operation of the facility.
(d) Stormwater detention facilities serving two or more developments may be approved by the county, provided that private ownership of the facilities and provisions for their perpetual maintenance and continuing operation are clearly established in a manner acceptable to the county attorney.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1111. Relationship to other regulations.
The requirements of this article are in addition to the requirements of any other ordinance, rule, regulation or other provision of law, and where any provision of this article imposes restrictions different from those imposed by any other ordinance, rule, regulation or other provision of law, whichever provision is more restrictive or imposes higher protective standards for human health or the environment shall control.
(Ord. No. 17-003, § 1, 10-2-2017) Secs. 1112—1120. Reserved.
DIVISION II. STORMWATER MANAGEMENT OUTSIDE URBANIZED AREAS
Sec. 1121. Applicability.
This division shall apply to land development projects (not otherwise exempt from compliance with this article) in the unincorporated area of Jackson County and outside of the urbanized area of unincorporated Jackson County, or in other words, those areas outside of the MS4 program of unincorporated Jackson County.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1122. Contents of stormwater management plan.
A stormwater management plan, when required, shall include sufficient information to evaluate the environmental characteristics of the affected areas, the potential impacts of the proposed development on water resources, and the effectiveness and acceptability of measures proposed for managing stormwater runoff. Said information shall at minimum include a site plan of the proposed land development and building and the following:
(a) Size and location of existing storm sewers, drains, culverts, or other underground facilities within the tract or within the right-of-way of streets or roads adjoining the tract. Grades and invert elevations of storm sewers shall be shown.
(b) Location and profiles of all storm drainage pipes and slopes of receiving channels.
(c) Hydraulic grade lines shall be shown on all pipes that cross streets and on all detention basin outfalls.
(d) Stormwater detention facility location, design and construction details, including a soils map and investigation for all sites proposed as ponds or impoundments or for stormwater detention.
Stormwater detention facilities/ponds shall be constructed to have a minimum of four to one side slopes. Stormwater detention facilities/ponds are to be broader, shallower and flatter for ease of maintenance and for aesthetic purposes. Construction details shall include appropriate access (minimum 20-foot wide access easement), a gravel access drive, fencing with locked gate, and landscaping to screen the installation.
(e) Location and typical construction details of all inlets and catch basins, headwalls and other drainage structures.
(f) The 100-year ponding limits above each street cross drain, where provided.
(g) Hydrologic and hydraulic analysis for the storm drainage system design.
(h) Construction schedule for both temporary and permanent facilities in relation to the schedule for development activities such as clearing, rough grading, construction, final grading, and vegetation establishment.
(i) A cost estimate for construction of the stormwater management facilities and an estimate of the annual cost for maintenance of the proposed facilities.
(j) Specific actions and a schedule of maintenance required to maintain the facilities at a satisfactory level of service, which shall be made a part of the private covenants.
(Ord. No. 17-003, § 1, 10-2-2017; Ord. No. 22-004, § 3, 5-16-2022) Secs. 1123—1130. Reserved.
DIVISION III. STORMWATER MANAGEMENT INSIDE URBANIZED AREAS
Sec. 1131. Purpose and objectives.
In addition to the purposes and intentions of this article generally, this division seeks to achieve the following objectives:
(a) Implement decision-making processes and procedures concerning land development that protect the integrity of the watershed and preserve the health of water resources;
(b) Require that development projects maintain the pre-development hydrologic response in their post-development state as closely as is feasible to reduce flooding, stream bank erosion, nonpoint source pollution and increases in stream water temperature while maintaining the integrity of stream channels and aquatic habitats;
(c) Establish minimum post-development stormwater management standards and design criteria for regulation and control of stormwater runoff quantity and quality;
(d) Formulate design and application criteria for the construction and use of structural stormwater control facilities used to achieve minimum post-development stormwater management standards;
(e) Strongly encourage the implementation of principles of low-impact development, including the use of nonstructural stormwater management and improved stormwater better site design practices such as preservation of greenspace and Georgia Stormwater Management Manual;
(f) Establish provisions for the long-term responsibility for and maintenance of structural stormwater control facilities and nonstructural stormwater management practices to ensure such facilities continue to function as designed, are maintained, and pose no threat to public safety; and
(g) Adopt administrative procedures for submission and review of stormwater management plans, for the monitoring and inspection of projects under construction, and for long-term follow up inspection of completed projects.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1132. Applicability.
This division shall apply to all of the following land development activities, including, but not limited to, site plan applications, subdivision applications and grading applications, unless specifically exempt by this article, in the unincorporated area of Jackson County and inside the urbanized area of unincorporated Jackson County, or in other words, those areas inside of the MS4 program of unincorporated Jackson County (see map):
(a) New development involving creation of 5,000 square feet or more of impervious cover or involving other land development activity affecting an area comprising one acre or more;
(b) Redevelopment that includes creation, addition or replacement of 5,000 square feet or more of impervious cover or involving other land development activity affecting an area comprising one acre or more;
(c) Any new development or redevelopment, regardless of size, defined to be a "hotspot" land use, and any commercial or industrial new development or redevelopment, regardless of size, with at standard industrial classification (SIC) code or North American Industrial Classification System Code (NAICS) that falls under the NPDES industrial stormwater permit program; and
(d) Land development activities that are below the minimum thresholds established in this section, when such activities are part of a larger development plan, even though multiple, separate and distinct land development activities may occur at different times and on different schedules.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1133. Georgia stormwater management manual.
Jackson County hereby adopts and will utilize in the urbanized area of unincorporated Jackson Country only, the policy, criteria and information, including technical specifications and standards, in the latest edition of the Georgia Stormwater Management Manual (GSMM) and any relevant local addenda, for proper implementation of the requirements of this division. The manual may be updated and expanded periodically, based on improvements in science, engineering, monitoring and local maintenance experience. It is the county's intent in adopting the manual to, in particular, apply stormwater better site design practices and credits for the implementation of stormwater better site design practices.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1134. Water quality.
All stormwater runoff generated by any site shall be adequately treated prior to discharge. A stormwater management system will be deemed in compliance with this standard provided the following requirements are met:
(a) The system is appropriately sized to treat the prescribed water quality treatment volume generated by the site as defined in the GSMM;
(b) Appropriate structural stormwater controls or nonstructural practices are selected, designed, constructed or preserved and maintained according to the specific criteria in the GSMM.
Emphasis will be placed by Jackson County on encouraging the use of nonstructural practices;
and
(c) Runoff from hotspot land uses and activities identified by Jackson County is adequately treated and addressed through the use of appropriate structural stormwater controls, nonstructural practices and pollution prevention practices.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1135. Stream channel protection.
Protection of stream channels from bank and bed erosion and degradation shall be provided by using all of the following three approaches:
(a) Preservation, restoration and re-vegetation or re-forestation using native plant species of the applicable stream buffer;
(b) Twenty-four-hour extended detention storage of the one-year, 24-hour return frequency storm event (this requirement may be adjusted or waived by Jackson County for sites that discharge directly into larger streams, rivers, wetlands, or lakes, or to a man-made channel or conveyance system where the reduction in these flows will not have an impact on upstream or downstream stream bank or channel integrity); and
(c) Erosion prevention measures, such as energy dissipation and velocity controls.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1136. Overbank flooding protection.
Downstream overbank flood and property protection shall be provided by controlling or attenuating the post-development peak discharge rate to the pre-development rate for the 25-year, 24-hour return frequency storm event. In instances where control of the one-year, 24-hour storm under this article is exempted, peak discharge rate attenuation of the two-year through the 25-year return frequency storm event must be provided. This requirement may be adjusted or waived by Jackson County for sites where the post-development downstream analysis shows that uncontrolled post-development conditions will not increase downstream peak flows, or that meeting the requirement will cause greater peak flow downstream impacts than the uncontrolled post-development conditions.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1137. Extreme flooding protection.
Extreme flood and public safety protection shall be provided by controlling and safely conveying the 100-year, 24-hour return frequency storm event such that flooding is not exacerbated. This requirement may be adjusted or waived by Jackson County for sites where the post-development downstream analysis shows that uncontrolled post-development conditions will not increase downstream peak flows, or that meeting the requirement will cause greater peak flow downstream impacts than the uncontrolled post-development conditions.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1138. Structural stormwater controls.
(a) All structural stormwater management facilities shall be selected and designed using the appropriate criteria from the Georgia Stormwater Management Manual (GSMM).
(b) All structural stormwater controls shall be appropriately designed to meet the intended function.
(c) The effectiveness and pollutant removal of the structural controls must be documented through prior studies, literature reviews or other means and be approved by Jackson County prior to being included in the design of a stormwater management system. This standard shall apply to other structural stormwater controls not included in the GSMM, or those for which pollutant removal rates have not been provided. In addition, whenever hydrologic or topographic conditions or land use activities warrant greater control than that provided by the minimum control requirements, Jackson County may impose additional requirements. Such requirements shall be those deemed necessary to protect upstream and downstream properties and aquatic resources from damage due to increased volume, frequency and rate of stormwater runoff or increased nonpoint source pollution loads created on the site.
(d) Applicants shall consult the GSMM for guidance as concerns the factors that determine site design feasibility when selecting and locating a structural stormwater control.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1139. Stormwater credits for nonstructural measures.
The use of one or more site design measures by the applicant may permit a reduction in the water quality treatment volume required by this division. The applicant may, subject to approval by Jackson County, take credit for the use of stormwater better site design practices and thereby, reduce the water quality volume requirement. A minimum set of criteria identifies the circumstances under which the credit may be applied. The site design practices that qualify for this credit and the criteria and procedures for applying and calculating the credits are included in the GSMM; see also the definition of "stormwater credits for better site design" in this article.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1140. Drainage system guidelines.
Stormwater conveyance facilities that may include, but are not limited to, culverts, stormwater drainage pipes, catch basins, drop inlets, junction boxes, headwalls, gutter, swales, channels, ditches and energy dissipaters shall be provided when necessary for the protection of public right-of-way and private property adjoining project sites. Existing or proposed stormwater conveyance facilities designed to carry runoff from more than one parcel shall meet the following requirements:
(a) Methods to calculate stormwater flows shall be in accordance with the GSMM;
(b) All culverts, pipe systems and open channel flow systems shall be sized in accordance with the stormwater management plan using methods contained in the GSMM; and
(c) Design and construction of stormwater conveyance facilities shall be in accordance with the criteria and specifications found in the GSMM.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1141. Dam design guidelines.
Any land disturbing activity that involves a site on which a dam is proposed shall comply with the Georgia Safe Dams Act and Rules for Dam Safety, as applicable.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1142. Permit application requirements.
No owner or developer shall perform any land development activities without first meeting the requirements of this section, as applicable. Unless provided otherwise by this article, any owner or developer proposing a land development activity shall submit a permit application to Jackson County on a form provided by the county for that purpose and pay the applicable fee as established by fee schedule.
The following information shall accompany a permit application:
(a) Stormwater concept plan;
(b) Stormwater management plan;
(c) Inspection and maintenance agreement, if applicable;
(d) Performance bond if applicable; and
(e) Permit application and plan review fees.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1143. Stormwater concept plan and consultation meeting.
The landowner or developer shall meet with representatives of the department of public development for a consultation meeting on a concept plan for the post-development stormwater management system to be used in the proposed land development project prior to submitting any stormwater management permit application. This consultation meeting shall occur at an early step in the development process.
The purpose of this meeting is to discuss the post-development stormwater management measures necessary for the proposed project and to assess constraints, opportunities and approaches for stormwater management design prior to commencing formal site design engineering. During such consultation meetings, the city and applicant will examine the potential applicability of non-structural stormwater controls (stormwater better site design practices). Local watershed plans, as applicable, and any relevant resource protection plans will be consulted in the discussion of the concept plan.
The following information shall be included in the concept plan that shall be submitted prior to the consultation meeting:
(a) Existing conditions/proposed site plan. Existing conditions and proposed site plan that at a minimum illustrates: existing and proposed topography; perennial and intermittent streams;
predominant soils from soil surveys; boundaries of existing predominant vegetation and proposed limits of clearing and grading; and location of existing and proposed roads, buildings, structures, parking areas and all other impervious surfaces;
(b) Natural resources inventory. A written or graphic inventory of the natural resources on the site and surrounding area as exists prior to commencement of the project. This description shall include a discussion and map of soil conditions (including erodible soils), forest cover, topography (which must include steep slopes (areas with slopes greater than 15 percent), wetlands, and other native vegetative areas on the site, as well as the location and boundaries of other natural feature protection and conservation areas such as wetlands, lakes, ponds, floodplains, aquatic buffers and other setbacks (e.g., drinking water well setbacks, septic setbacks, etc.), natural drainage divides and patterns, natural drainage features, groundwater recharge areas, sensitive natural habitat areas, and protected river corridors. Particular attention must be afforded environmentally sensitive features that represent constraints to development;
(c) Stormwater management system concept plan. A written or graphic concept plan of the proposed post-development stormwater management system that includes the following information:
preliminary selection and location of proposed structural stormwater controls; location of existing and proposed conveyance systems such as grass channels, swales and storm drains; flow paths; location of floodplain/floodway limits; relationship of site to upstream and downstream properties and drainages; and preliminary location of proposed stream channel modifications such as bridge or culvert crossings.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1144. Stormwater management plan.
(a) The stormwater management plan shall describe the methods and approaches proposed to control and manage post-development stormwater runoff.
(b) A description of the measures that will be employed to comply with the standards and requirements of this article, including performance criteria required by this article shall also be provided.
(c) The stormwater management plan shall be in accordance with the criteria established in this article and be prepared under the direct supervisory control of either a registered professional engineer or a registered landscape architect licensed in the state of Georgia, who shall seal and sign the work. The work shall be conducted under the direct supervisory control of a registered professional engineer.
Portions of the overall plan such as boundary surveys, contour maps and erosion and sedimentation control plans may be prepared and stamped by a registered land surveyor licensed in the state of Georgia, as appropriate.
(d) The stormwater management plan must ensure that the requirements and criteria in this article are met, and that opportunities to minimize adverse post-development stormwater runoff impacts generated by the development are considered. The plan shall consist of maps, narrative, and supporting design calculations (hydrologic and hydraulic) for the proposed stormwater management system (a.k.a, "hydro" study).
(e) The stormwater management plan for each land development project shall provide for stormwater management measures located on the site of the project, unless provisions are made to manage stormwater by means of an off-site or regional facility.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1145. Contents of the stormwater management plan.
The plan shall include all information required in the stormwater management site plan checklist found in the GSMM, including the following information:
(a) General. Common address and legal description of the site, and a vicinity map;
(b) Existing conditions hydrologic analysis.The existing condition hydrologic analysis for stormwater runoff rates, volumes and velocities, which shall include the following information:
1. A topographic map of existing site conditions with the drainage basin boundaries indicated;
2. Acreage, soil types and land cover of areas for each sub-basin affected by the project;
3. All perennial and intermittent streams and other surface water features;
4. All existing stormwater conveyances and structural control facilities;
5. Direction of flow and exits from the site;
6. Analysis of runoff provided by off-site areas upstream of the project site; and
7. Methodologies, assumptions, site parameters and supporting design calculations used in analyzing the existing conditions site hydrology. For redevelopment sites, pre-development conditions shall be modeled using the guidelines established by the director of public works for the portion of the site undergoing land development activities.
(c) Post-development hydrologic analysis. The post-development hydrologic analysis for stormwater runoff rates, volumes and velocities, which shall include the following information:
1. A topographic map of developed site conditions with the post-development drainage basin boundaries indicated;
2. Total area of post-development impervious surfaces and other land cover areas for each sub-basin affected by the project;
3. Calculations for determining the runoff volumes that need to be addressed for each sub-basin for the development project to meet the post-development stormwater management performance criteria of this article;
4. Location and boundaries of proposed natural feature protection and conservation areas;
5. Documentation and calculations for any applicable site design credits that are being utilized; and
6. Methodologies, assumptions, site parameters and supporting design calculations used in analyzing the existing conditions site hydrology. Redevelopment sites on which the land development activity constitutes more than 50 percent of the entire site shall meet the performance criteria of this article as concerns the stormwater runoff from the entire site.
(d) Stormwater management system. The description, scaled drawings and design calculations for the proposed post-development stormwater management system, which shall include the following information:
1. A map and/or drawing or sketch of the stormwater management facilities, including the location of nonstructural site design features and the placement of existing and proposed structural stormwater controls, including design water surface elevations, storage volumes available from zero to maximum head, location of inlet and outlets, location of bypass and discharge systems, and all orifice/restrictor sizes;
2. A narrative describing how the selected structural stormwater controls will be appropriate and effective; cross-section and profile drawings and design details for each of the structural stormwater controls in the system, including supporting calculations to show that the facility is designed according to the applicable design criteria;
3. A hydrologic and hydraulic analysis of the stormwater management system for all applicable design storms (including stage-storage or outlet rating curves, and inflow and outflow hydrographs);
4. Documentation and supporting calculations to show that the stormwater management system adequately meets the post-development stormwater management performance criteria of this article;
5. Drawings, design calculations, elevations and hydraulic grade lines for all existing and proposed stormwater conveyance elements including stormwater drains, pipes, culverts, catch basins, channels, swales and areas of overland flow;
6. A narrative describing how the stormwater management system corresponds with any watershed protection plans and/or local greenspace protection plan, as applicable; and
7. A narrative describing the extent to which non-structural stormwater controls, specifically including stormwater better site design practices, are implemented.
(e) Post-development downstream analysis. A downstream peak flow analysis that includes the assumptions, results and supporting calculations to show safe passage of post-development design flows downstream. The analysis of downstream conditions in the report shall address every point or area along the boundary of the project site at which runoff will exit the property.
The analysis shall focus on the portion of the drainage channel or watercourse immediately downstream from the project. This area shall extend downstream from the project to a point in the drainage basin where the project area represents ten percent of the total basin area. In calculating runoff volumes and discharge rates, consideration may need to be given to any planned alteration in future, upstream land use. The analysis shall be in accordance with the
GSMM.
(f) Construction-phase erosion and sedimentation control plan. An erosion and sedimentation control plan in accordance with article 8 of this UDC and the NPDES permit for construction activities. The plan shall also include information on the sequence/phasing of construction and temporary stabilization measures and structures that will be converted into permanent stormwater controls.
(g) Landscaping and open space plan. A detailed landscaping and vegetation plan describing the woody and herbaceous vegetation that will be used within and adjacent to stormwater management facilities and practices. The landscaping plan must also include the following information:
1. Arrangement of planted areas, natural and greenspace areas and other landscape features depicted on the plan drawings;
2. Information necessary to install the landscape features shown on the plan drawings;
3. Descriptions and standards for the methods, materials and vegetation to be used in the installation;
4. Density of plantings;
5. Descriptions of the stabilization and management techniques used to establish vegetation;
6. Identification of the party responsible for ongoing maintenance of vegetation for the stormwater management facility and the practices to be employed to ensure that adequate vegetative cover is preserved; and
7. The extent to which landscaping will implement stormwater better site design practices.
8. Design indicating that 75 percent of minimum open space is contiguous and/or continuous.
(h) Operations and maintenance plan. Detailed description of ongoing operations and maintenance procedures for stormwater management facilities and practices to ensure their continued function as designed and built, or preserved. This plan will identify the components of a stormwater management facility or practice that must to be regularly inspected and maintained, and the equipment and skills necessary to the inspections and maintenance. The plan shall include an inspection and maintenance schedule, maintenance tasks, responsible parties for maintenance, funding, access and safety issues. Provisions for the periodic review and evaluation of the effectiveness of the maintenance program and the process for revisions or additional maintenance procedures shall be included in the plan.
(i) Maintenance access easements. The applicant shall provide unfettered access to stormwater management facilities and practices requiring regular maintenance at the site from public right-of-way. Such access shall be sufficient to accommodate all necessary maintenance equipment. Such access shall also be for the purpose of inspection and repair and shall be guaranteed by the granting of a permanent, maintenance access easement. Upon final inspection and approval, a plat or document indicating that such easements exist shall be recorded and shall survive the transfer of title to the property.
(j) Inspection and maintenance agreements. The applicant shall execute an easement and an inspection and maintenance agreement binding on all subsequent owners of land served by an on-site stormwater management facility or practice in accordance with this article.
(k) Evidence of acquisition of applicable local and non-local permits. The applicant shall certify and provide documentation to Jackson County that all other applicable environmental permits have been acquired for the site prior to approval of the stormwater management plan.
(l) Additional requirements. Any additional requirements which may be specified in the GSMM, as applicable.
(Ord. No. 17-003, § 1, 10-2-2017; Ord. No. 19-002, 10-21-2019) Sec. 1146. Stormwater management inspection and maintenance agreements.
(a) Execution required. Prior to issuance of any permit for a land development activity requiring a stormwater management facility or practice hereunder, and for which Jackson County requires ongoing maintenance, the applicant or owner of the site shall execute an inspection and maintenance agreement and/or a conservation easement, if applicable, that shall be binding on all subsequent owners of the site.
(b) Approval. The inspection and maintenance agreement must be approved by Jackson County prior to plan approval and recorded in the deed records upon final plat approval.
(c) Responsible party. The inspection and maintenance agreement shall identify by name or official title the party responsible for implementing the inspection and maintenance procedures. Responsibility for the operation and maintenance of the stormwater management facility or practice, unless assumed by a governmental agency, shall remain with the property owner and shall pass on to any successor owner.
In the event portions of the land are sold or otherwise transferred, legally binding arrangements shall be made to assign the inspection and maintenance responsibilities to the appropriate successors in title.
These arrangements shall designate the party to be permanently responsible for the inspection and maintenance for each portion of the site.
(d) Schedule. An inspection and maintenance schedule shall be developed as part of the inspection and maintenance agreement to ensure proper functioning of the stormwater management facility or practice. The agreement shall also include plans for annual inspections to ensure proper performance of the facility between scheduled maintenance and shall also include remedies for the default thereof.
(e) Right of inspection. The terms of the inspection and maintenance agreement shall provide for the right of entry to property by Jackson County at reasonable times and in a reasonable manner for the purpose of inspection.
(f) Additional enforcement by county. In addition to enforcing the terms of the inspection and maintenance agreement, Jackson County may also enforce all provisions for ongoing inspection and maintenance contained in this article.
(g) Surety. The county may require the posting of bonds or other security to guarantee performance of construction and/or maintenance obligations of this division.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1147. Application procedure.
(a) All applications for land development permits shall be filed with the Jackson County Department of Public Development.
(b) Two copies of the stormwater management plan and the inspection maintenance agreement shall also be submitted.
(c) Jackson County shall inform the applicant in writing of an approval or denial of a landdisturbance or development permit application, stormwater management plan, or an inspection and maintenance agreement. In approving or disapproving stormwater management plans, the director of public development will base the decision in part on the extent to which opportunities for implementing stormwater better site design practices. After consultation with the applicant, the director may disapprove a stormwater management plan if the applicant has failed to consider non-structural stormwater management alternatives and implemented stormwater better design practice(s), where feasible.
(d) If an application for stormwater management plan or inspection and maintenance agreement is denied, the applicant may revise any information not in compliance with this article as identified by the county and resubmit the same.
(e) Upon a finding by the county that the permit application, stormwater management plan and inspection and maintenance agreement, meet the requirements of this division, the director shall issue a permit for the land development project, provided all other legal requirements for issuance of such permit have been met.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1148. Responsibilities after permit issuance.
Upon issuance of the permit, the applicant or other responsible party conducting the land development project shall be subject to the following requirements:
(a) The applicant shall comply with all applicable requirements of the approved plan and this article and shall certify that all land clearing, construction, land development and drainage will be performed according to the approved plan;
(b) The land development project shall be conducted only within the area specified in the approved plan;
(c) County personnel shall have access to the site to conduct periodic inspections of the project;
(d) No changes shall be made to an approved plan without review and written approval by the director of public development; and
(e) Upon completion of the project, the applicant or other responsible party shall submit the engineer's report and certificate and as-built plans required by this article.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1149. Modifications for off-site facilities.
If provisions are made to manage stormwater by means of an off-site or regional facility, such off-site or regional facility shall meet the following requirements:
(a) It shall be located on property legally dedicated for that purpose;
(b) It shall be designed and adequately sized to provide a level of stormwater quantity and quality control equal to or greater than that which would be afforded by on-site practices;
(c) It shall be controlled by an identified, legally-obligated entity responsible for long-term operation and maintenance of the off-site or regional stormwater facility;
(d) On-site measures shall be implemented, where necessary, to protect upstream and downstream properties and drainage channels from the site to the off-site facility; and
(e) A stormwater management plan shall be submitted to Jackson County that documents the adequacy of the off-site or regional facility.
(f) To be eligible for a modification, the applicant must demonstrate to the satisfaction of the director of public development that use of an off-site or regional facility will not cause any the following impacts to upstream or downstream areas:
1. Increased threat of flood damage to public health, life or property;
2. Deterioration of existing culverts, bridges, dams or other structures;
3. Accelerated stream bank or streambed erosion or siltation;
4. Degradation of in-stream biological functions or habitat; or
5. Water quality impairment in violation of state water quality standards or violation of any state or federal regulations.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1150. Inspections.
Inspections may include, but are not limited to: reviewing maintenance and repair records; sampling discharges, surface water, groundwater and material or water in stormwater management facilities; and evaluating the condition of stormwater management facilities and practices. Inspections will be provided at different intervals including:
(a) During construction. Periodic inspections of the construction of the stormwater management system shall be conducted by the staff of Jackson County or conducted and certified by a professional engineer who has been approved by Jackson County. Construction inspections shall utilize the approved stormwater management plan for establishing compliance.
(b) Ongoing. Stormwater management facilities and practices included in a stormwater management plan that are subject to an inspection and maintenance agreement must undergo ongoing inspections to document maintenance and repair needs and ensure compliance with the requirements of the stormwater maintenance agreement, the approved stormwater management plan, and the requirements of this article.
(c) Other. Other, or additional, inspection programs may be established by the county on any reasonable basis including, but not limited to, the following actions: routine inspections;
random inspections; inspections based on complaints or other notice of possible violations; and joint inspections with other agencies inspecting under environmental or safety laws.
(d) Following completion. A final inspection shall be required following completion and prior to release of any performance securities.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1151. Documentation of inspections.
All inspections shall be documented by written reports containing the following information:
(a) The date and location of the inspection;
(b) Indication as to whether construction is in compliance with the approved stormwater management plan;
(c) Deviations from the approved construction specifications; and
(d) Any other deviation or violation of the conditions of the approved stormwater management plan.
The applicant shall be notified in writing of the nature of any violations found and the required corrective actions.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1152. Right-of-entry for inspection.
Authorized personnel of the county shall have the right to enter any property that the county has a reasonable basis to believe that a violation of this article is occurring or has occurred and to enter when necessary for abatement of a public nuisance or correction of a violation of this article.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1153. Certification and as-built plans.
(a) Prior to issuance of a certificate of occupancy, a professional engineer shall certify that the completed project complies with the approved stormwater management plan.
(b) All applicants shall submit actual "as built" plans final design specifications for all stormwater management facilities and practices for once final construction is completed.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1154. Records of maintenance activities.
Parties responsible for operation and maintenance of a stormwater management facility shall provide all records of any maintenance and repairs to Jackson County within 30 days upon written request.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1155. Failure to maintain a stormwater management facility.
In addition to other remedies generally available to the city for violations of this development code, the county may pursue the remedy specified in this section.
(a) In the event a responsible party fails or refuses to meet the requirements of the inspection and maintenance agreement, Jackson County upon 30 calendar days written notice may correct a violation of the design standards or maintenance requirements by performing the necessary work to place the facility or practice in proper working order.
(b) Violations that constitute an immediate danger to public health or public safety shall be cured within 24 hours of receipt of such written notice.
(c) Jackson County may assess the owner(s) of the facility for the cost of repair work that shall be a lien on the property, and may be placed on the ad valorem tax bill for such property and collected in the ordinary manner for such taxes.
(Ord. No. 17-003, § 1, 10-2-2017) Secs. 1156—1160. Reserved.
DIVISION IV. STORM DRAINAGE STANDARD SPECIFICATIONS
Sec. 1161. General applicability.
The requirements of this division shall apply to all stormwater management systems and stormwater conveyances; provided, however, that within the urbanized area of unincorporated Jackson County such requirements may be deemed inapplicable by the director of public development if they conflict with provisions of the Georgia Stormwater Management Manual.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1162. Design responsibility.
Sizing and location of all existing and proposed drainage structures shall be the responsibility of a registered professional engineer, landscape architect, or registered land surveyor subject to approval by the county. A registered engineer shall certify the storm drain pipe sizes.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1163. Storm drainage pipe slope.
Storm drainage pipes shall be sloped so as to maintain a minimum velocity of three feet per second (fps) so that sediment will not collect.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1164. Reference to state standards.
(a) Storm sewer catch basins, drop inlets, manholes, and junction boxes shall be designed by the developer's engineer to state highway standards and subject to final approval by the county.
(b) State Highway Standard 1030D (or most current) shall be used in determining class (concrete) or gauge of pipe under fill, method of backfilling and pipe installation.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1165. Drainage formula.
Drainage formula used in determining size of drainage structure shall be determined by the developer's engineer, landscape architect, or registered land surveyor according to accepted engineering practice, subject to approval of the county.
Street water runoff shall be designed using the gutter spread formula.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1166. Storm events to be utilized.
The 25-year storm event shall be used in designing the storm drains. In cases where a spring, creek, or other watercourse traverses the property, the 100-year storm event will be used for design.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1167. Catch basin location.
Catch basins shall be located outside of intersection radii unless unusual circumstances cause undue hardship, in which case the county may waive this requirement.
Cul-de-sacs on downhill street grades shall require catch basin throat design and cul-de-sac grading detail.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1168. Subdrainage.
Subdrainage will be installed to control the surplus ground water by intercepting sidehill seepage or by lowering or regulating the ground water level where such conditions exist.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1169. Certification.
A certification by the supplier of the pipe specifications for each pipe shall be required before installation.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1170. Bridges.
Bridges shall be designed for a 100-year storm event.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1171. Riprap.
Provide riprap at all downstream discharge points of storm drains. The area of riprap required shall be six times the pipe diameter for the length and two times the pipe diameter for the width.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1172. Exit velocities.
Exit velocities from storm drain pipe for the 50-year storm shall not exceed ten fps without additional energy dissipaters (not including required riprap).
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1173. Breach analysis.
If it is proposed to make a new or existing lake a part of a subdivision, or if the subdivision is located downstream from a water impoundment, the developer shall be required to submit a breach analysis and show the dam breach zone on the plans.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1174. Cross drain pipes.
(a) Cross drain pipes shall be no less than 15 inches in size when under the street. No storm drain pipe running parallel to the existing primary road shall be located beneath the proposed acceleration/ deceleration lanes. The county may modify or waive this requirement if unusual circumstances exist such as topography.
(b) The inlet and outlet end of all storm drain pipes (including driveway pipe) shall have either flared-end sections or rectangular concrete headwalls that meet the standards of Georgia Department of Transportation 1120 or 1125.
(c) Extend 20 feet past the rear of the building for storm drains 36 inches or smaller.
(d) Extend 20 feet past the rear of the building for storm drains larger than 36 inches and size the drainage ditch on each end of the pipe to limit the runoff velocity to less than five fps or riprap the ditch.
(e) Maximum continuous length of pipe shall be 300 feet for pipes less than 42 inches.
(f) Junction boxes having access to the pipe shall be constructed to meet the requirements of State Standard 1030D (or most current).
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1175. Stormwater ditches.
All man-made ditches between storm drain pipes and downstream of storm drain pipe shall be designed by a registered professional engineer or landscape architect. The ditch profile and cross-sections every 50 feet shall be shown on the plans. The plans shall show the velocity and flow at each cross-section.
Stormwater velocity shall not exceed five fps unless the ditches are lined.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1176. Storm drainage materials and installation.
(a) The table titled "Selection Guidelines for Storm Sewer Piping," sets out guidelines for the use of storm sewer pipes by pipe material and type of installation.
Selection Guidelines for Storm Sewer Piping Type of Pipe Installation Reinforced Concrete Pipe Corrugated Steel
AASHTO M-36
Corrugated Aluminum
AASHTO
M=196 Plastic
AASHTO
M 294 Reinforced Concrete Box Culvert Aluminized Type II
CMP
Bituminous Coated
CMP
Aluminum Alloy CMP Corrugated High Density Polyethylene Smooth Lined Per Georgia DOT Standards Longitudinal (grade less than 10%) Yes Yes Yes Yes See Note 1 n/a Type of Pipe Installation Reinforced Concrete Pipe Corrugated Steel
AASHTO M-36
Corrugated Aluminum
AASHTO
M=196 Plastic
AASHTO
M 294 Reinforced Concrete Box Culvert Aluminized Type II
CMP
Bituminous Coated
CMP
Aluminum Alloy CMP Corrugated High Density Polyethylene Smooth Lined Per Georgia DOT Standards Longitudinal (grade 10% or more) No Yes Yes Yes See Note 1 n/a Cross Drain, Local Street Yes Yes Yes Yes No n/a Cross Drain, Collector or Arterial Street Yes No No No No n/a Cross Drain, Flowing Stream Yes See Note 3 No No No n/a Cross Drain, 25-year Flow 200 cfs Fill Depth 18 feet See Note 2 See Notes 2 and 3 No See Note 2 No Yes Note 1: Corrugated high density polyethylene pipe, smooth lined type "S", can only be used for residential driveway applications and must be manufactured and installed in strict compliance with Georgia DOT Standard 1030-P. HDPE applications shall not exceed 36 inches in diameter.
Note 2: Reinforced concrete box culverts are required under excessive flow and/or fill depth conditions.
Approved pipe materials may be utilized in some instances, based on the county engineer's assessment of existing conditions and future maintenance requirements.
Note 3: The addition of a type "A" full bituminous coating is required. (AASHTO M-190)
(b) Only reinforced concrete pipe shall be used within street rights-of-way for arterial roads, and major and minor collectors. Concrete pipe shall not be used on grades exceeding ten percent. Metal pipe may be used within the rights-of-way of local streets and for driveway culverts. Metal pipe shall either be corrugated steel (AASHTO M-36) with aluminized type II or bituminous coating, or corrugated aluminum alloy pipe (AASHTO M-196).
(c) Corrugated high density polyethylene pipe, smooth lined type "S", can only be used for residential driveway applications and shall not exceed 36 inches in diameter.
(d) Pipe installation shall conform to Georgia Department of Transportation Standard Specifications for construction of roads and bridges. Before any traffic over a storm drain is allowed, the developer shall provide an adequate depth and width of compacted backfill to protect the structure from damage or displacement. The developer shall remove any debris or silt that constricts the flow through a pipe as often as necessary to maintain drainage. All pipe structures shall be cleaned before the work is accepted.
Any damage or displacement that may occur due to traffic or erosion shall be repaired or corrected at the developer's expense.
(e) Trench construction for storm drainage pipe shall be in accordance with State Highway Standard 1030D (or most current).
(f) Backfilling of trenches shall be accomplished immediately after the pipe is laid. The fill around the pipe shall be placed in layers not to exceed six inches with each layer being thoroughly compacted. All material shall have an in place density of 98 percent modified proctor to a depth of six inches below the finished grade, and 95 percent modified proctor at depths greater than six inches below the finished grade. Compaction requirements shall be attained by the use of mechanical compaction methods. Each layer of backfill shall be placed loosely and thoroughly compacted in place.
(g) All backfill shall be non-plastic in nature, free from roots, vegetative matter, waste, construction material or other objectionable material. Said material shall be capable of being compacted by mechanical means and shall have no tendency to flow or behave in a plastic manner under the tamping blows.
(h) Material deemed by the county as unsuitable for backfill purposes shall be removed and replaced with selected backfill material.
(i) Water shall not be permitted to rise in trenches that are not backfilled after the pipe has been placed.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1177. Minimum clearances.
(a) Two feet between the bottom of the base or sub-base, if used, and the exterior crown of the culvert is required under the roadway.
(b) Pipes included in easements shall have a minimum cover of one foot or at the manufacturers' recommendations.
(c) A minimum of six inches between underground utilities and exterior crown of culverts.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1178. Driveway culverts.
(a) Where a wet weather drainage ditch exists between the proposed road and 20 feet into the lot, the design professional shall size the driveway culvert as if the driveway was at the lowest point on that lot.
The construction plans shall show the minimum driveway pipe size required.
(b) Driveway culverts may be any of the types of pipe materials shown in section 1176(a) for longitudinal pipe installation.
(c) The inlet and outlet end of all driveway culverts shall have either flared-end sections or concrete headwalls that meet the standards of Georgia Department of Transportation 1120 or 1125.
(d) Driveway culverts not located within rights-of-way shall be installed with material meeting the plumbing code applicable in Jackson County.
(Ord. No. 17-003, § 1, 10-2-2017) Sec. 1179. Detention pond.
(a) Access. Detention ponds shall be accessible from a public street via a minimum 20-foot wide access easement. There shall be access around detention pond via an all-weather road at least ten feet wide.
(b) Security. Detention ponds shall be fenced at a height of at least four feet with a locking gate. If chain-link fencing is utilized, it shall be vinyl coated. The fencing requirement may be waived if slopes to the detention pond are 4:1 or less and the facility is made into an amenity feature approved by the public development department. Stormwater detention facilities/ponds shall be constructed to have a minimum of four to one side slopes. Stormwater detention facilities/ponds are to be broader, shallower and flatter for ease of maintenance and for aesthetic purposes.
(c) Landscaping. The periphery of detention ponds shall be landscaped as approved by the public development department.
(Ord. No. 17-003, § 1, 10-2-2017; Ord. No. 22-004, § 4, 5-16-2022) Secs. 1180—1190. Reserved.
ARTICLE 12. BUFFERS, TREE PROTECTION AND LANDSCAPING
DIVISION I. GENERAL PROVISIONS
Sec. 1201. Reference to requirements.
(a) Zoning buffers. Article 2, table 2-2 of this UDC establishes minimum buffer widths between certain zoning districts, which vary by zoning district.
(b) Special uses. The specific use requirements of article 3 of this UDC may include requirements for buffers, depending on the particular use.
(c) Stream buffers. Stream buffers are established in article 8 of this UDC. Article 5 of this UDC establishes environmental overlay districts which require river and stream buffers.
(Ord. No. 22-010, § 1, 8-15-2022) Sec. 1202. Definitions.
The definitions of this section shall apply to all divisions of this article.
ANSI A300 Standards: The generally accepted (consensus) industry standards for tree care practices by the Tree Care Industry Association (TCIA) and written by a committee called the Accredited Standards Committee ASC A300. These standards are based on current research and sound practice for writing specifications for planting, managing, and caring for trees, shrubs, and other woody plants.
Arborist: A professional certified by the International Society of Arboriculture (ISA) who possesses the technical competence through experience and related training to provide for, or supervise, the planting, management, and care of trees and other woody plants in the residential, commercial, and public landscape. In the absence of an appointed arborist the public development department or their designee shall serve as the arborist for the county.
Berm: An earthen mound or embankment, usually less than three feet if designed to provide visual interest only, and usually six feet more in height if intended to screen views or reduce noise.
Caliper: The trunk diameter of a tree (usually nursery stock) six inches or top of the rootball for up to and including four-inch diameter trees and 12 inches above the ground or top of rootball for larger trees.
Critical root zone (CRZ): The minimum area beneath an existing tree that must be left undisturbed in order to preserve a root zone sufficient to give a tree a reasonable chance of survival. The CRZ will typically be represented by a concentric circle centered on the tree's trunk in a radius a radius equal in feet to 1.25 times the number of inches of trunk diameter measured at four and one-half feet (DBH) above ground level or to the edge of the tree canopy dripline, whichever is greater. Example: The CRZ radius of a 20-inch diameter tree is 20 x 1.50 = 30 feet from the center of the base of the tree.
Crown: The leaves and branches of a tree or shrub; the upper portion of a tree from the lowest branch on the trunk to the top.
Deciduous: A perennial plant with foliage (leaves) that becomes dormant, typically in the fall, and totally or partially casts off leaves annually, depending on species.
Leer este código donde se publica (Municode) La fuente es el código del condado tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.