Ir al contenido
Georgia Commons
Menú

Walker County · Código de ordenanzas

Part II - CODE OF ORDINANCES / Chapter 28 - SOLID WASTE / Article III - SEWER USE REGULATION IN UNINCORPORATED AREAS / Division 3 - BUILDING SEWERS, CONNECTIONS, AND PERMITS

Sec. 28-116. Sewer construction; acceptance of work.

Sobre este texto

  • As published by Municode, current through 2026-07-09
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

(a) It is the policy of the Authority to construct conventional gravity sewer systems whenever it is feasible. Low pressure sewer systems with grinder pump installation and use shall be limited to:

(1) New residential subdivisions only when the construction of a conventional gravity sewer system is not feasible; the installer of the low pressure sewer system can demonstrate that no other technically feasible alternative is available; and where it is specifically determined by the Board of the Authority to be in the best interest of the Authority; and

(2) Existing residential neighborhoods where septic systems have failed and a low-pressure sewer system in the opinion of the Authority is more cost effective and environmentally sound than a conventional sewer system.

(b) All sewer construction involving sanitary sewer lines, pump stations, metering stations, and appurtenances which are to become a part of the Authority's sewer system shall not be constructed until the plans are approved and the construction inspected and approved by the Authority.

(1) All new developments will not be considered for acceptance and continued maintenance by the Authority until all the following conditions have been met:

a. 80 percent of all phases of the developments have been completed.

b. A camera inspection of all sewer lines has been performed by the Authority.

c. An evaluation of all lift and/or pump stations has been conducted by the Authority.

d. The Authority has all utility easements recorded and on file.

e. Any deficiency in the system must be repaired and brought up to the Authority's standards before the system will be taken over by the Authority.

(2) Once these requirements have been met, the Authority will issue the developer a letter of acceptance and assume maintenance responsibility from that time forward. Prior to this all maintenance will be the developer's responsibility.

(c) The cost of the materials and installation of gravity systems (including laterals from main to property line and cleanouts at the property line) or low pressure systems (including the grinder pump and house lateral) which shall become part of the Authority's system, shall be borne by the installer.

(d) Multi-family residential, commercial, industrial, institutional, tourist, and church-related properties shall be responsible for the purchase, installation, and maintenance of necessary pumps, pump basins, electrical appurtenances, and piping to the public right-of-way required for sewer service to said establishments.

(e) Any construction work where the Authority's sewers are opened, uncovered, or undercut must have the prior approval of the Authority.

Historia

La línea de historia que la fuente imprime al final de la sección.

(Ord. No. O-03-22, Exh. A, 11-10-2022)

Leer este código donde se publica (Municode) La fuente es el código del condado tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:walker-county/code/28-116@2026-07-09-1eea933f3c

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Walker County Code of Ordinances, Sec. 28-116. Sewer construction; acceptance of work | Georgia Commons