Sec. 14-25. Inspections.

Sobre este texto

  • As published by Municode, current through 2026-05-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

(1) The county engineer may periodically, during working hours between 7:00 a.m.

and 5:00 p.m., Monday through Friday, exclusive of holidays, inspect the sites for which permits have been issued to

determine if the activities thereon are in accordance with the plan and if the

measures required in the plan are effective.

(2) The following types of construction are required to be inspected:

a. Grading and storm drainage;

b. Water and sewer line construction;

c. Curb construction;

d. Base and paving construction;

e. Driveway construction;

f. Buffers required by other ordinances;

g. Initial installation of the following erosion control best management

practices (BMP):

1. Construction exit;

2. Sediment basin;

3. Sediment trap;

4. Silt fence;

5. Any other BMP's as specified in the permit.

h. Any construction in existing county rights-of-way, and

i. Any additional inspections required at the time of permit issuance.

(3) Each type of construction identified above shall be inspected at the time of its

completion. In addition, each phase of construction shall be inspected before it is covered, built over, or otherwise hidden for inspection purposes by subsequent

work.

(4) When an inspection for approval is requested, the permit holder or his agent shall notify the building, zoning, and

development department not less than 24 hours in advance of the work, during the hours of 7:30 a.m. to 4:30 p.m., Monday through Friday, exclusive of holidays.

(5) The permit holder is fully responsible for any and all construction work. The county engineer may require any un-inspected

work which is required to be inspected to be uncovered for inspection at the sole

expense of the applicant. The county shall in no way be liable for any cost or damages arising from or in way associated with any delay or inconvenience associated with any work, delay or

inconvenience caused by uncovering uninspected work.

(6) After any inspection, the county engineer reserves the right to require modifications or corrections if said work does not meet the requirements of this ordinance

and the permitted plans.

Historia

La línea de historia que la fuente imprime al final de la sección.

(Res. of 6-9-03, § 2-5)

Leer este código donde se publica (Municode) La fuente es el código del condado tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:whitfield-county/code/14-25@2026-05-11-d42e01247f

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Whitfield County Code of Ordinances, Sec. 14-25. Inspections | Georgia Commons