Public works construction contracts may include both liquidated damages provisions for late construction project completion and incentive provisions for early construction project completion when the project schedule is deemed to have value. The terms of the liquidated damages provisions and the incentive provisions shall be established in advance as a part of the construction contract and included within the terms of the bid or proposal.
History
Code 1981, § 13-10-70, enacted by Ga. L. 2013, p. 628, § 4/SB 179.
Leer la página oficial (el PDF del estado, abierto en la página de la que se leyó este texto).
Actualizado hasta: Including Acts of the 2025 Regular Session of the General Assembly.
Texto leído de t13-(v11)-pdf.pdf, Volumen V11, edición 2010, suplemento de 2025, páginas 148 a 149; acción de fusión: added; SHA-256 del archivo 6acfbda3d9fa.