Título 13. CONTRACTS · Capítulo 11. PROMPT PAYMENT
13-11-4. Time limits for payments to contractors and subcontractors.
Actualizado hasta: Including Acts of the 2025 Regular Session of the General Assembly.
El texto siguiente es la ley tal como la imprime el estado, en inglés.
- (a)
When a contractor has performed in accordance with the provisions of a contract, the owner shall pay the contractor within 15 days of receipt by the owner or the owner’s representative of any payment request based upon work completed or service provided under the contract.#
- (b)
When a subcontractor has performed in accordance with the provisions of its subcontract and the subcontract conditions precedent to payment have been satisfied, the contractor shall pay to that subcontractor and each subcontractor shall pay to its subcontractor, within ten days of receipt by the contractor or subcontractor of each periodic or final payment, the full amount received for such subcontractor’s work and materials based on work completed or service provided under the subcontract, provided that the subcontractor has provided or provides such satisfactory reasonable assurances of continued performance and financial responsibility to complete his or her work as the contractor in his or her reasonable discretion may require, including but not limited to a payment and performance bond.#
History
Code 1981, § 13-11-4, enacted by Ga. L. 1994, p. 1398, § 1.
Leer la página oficial (el PDF del estado, abierto en la página de la que se leyó este texto).
Actualizado hasta: Including Acts of the 2025 Regular Session of the General Assembly.
Texto leído de t13-(v11)-2010-pdf.pdf, Volumen V11, edición 2010, página 631; acción de fusión: annotated; SHA-256 del archivo 18573afb153d.