Título 13. CONTRACTS · Capítulo 11. PROMPT PAYMENT
13-11-6. Conditions authorizing payments to subcontractors.
Actualizado hasta: Including Acts of the 2025 Regular Session of the General Assembly.
El texto siguiente es la ley tal como la imprime el estado, en inglés.
The contractor shall, within ten days from the contractor’s receipt of retainage from the owner, pass through payments to subcontractors and shall reduce each subcontractor’s retainage in the same manner as the contractor’s retainage is reduced by the owner, provided that the value of the subcontractor’s work complete and in place equals 50 percent of his or her subcontract value, including approved change orders and other additions to the subcontract value and, provided, further, that the work of the subcontractor is proceeding satisfactorily and, provided, further, that the subcontractor has provided or provides such satisfactory reasonable assurances of continued performance and financial responsibility to complete his or her work as the contractor in his or her reasonable discretion may require, including but not limited to a payment and performance bond.
History
Code 1981, § 13-11-6, enacted by Ga. L. 1994, p. 1398, § 1.
Leer la página oficial (el PDF del estado, abierto en la página de la que se leyó este texto).
Actualizado hasta: Including Acts of the 2025 Regular Session of the General Assembly.
Texto leído de t13-(v11)-2010-pdf.pdf, Volumen V11, edición 2010, página 632; acción de fusión: carried; SHA-256 del archivo 18573afb153d.