22-3-82. General certificate and permitting requirements.

Vigente

Actualizado hasta: Including Acts of the 2025 Regular Session of the General Assembly.

El texto siguiente es la ley tal como la imprime el estado, en inglés.

  1. (a)

    A petroleum pipeline company shall not exercise the power of eminent domain granted in Code Section 22-3-81 for the purpose of constructing a new petroleum pipeline or for an extension unless and until a certificate of public convenience and necessity is issued by the commissioner of transportation as provided in Code Section 22-3-83 and a permit is issued by the director of the Environmental Protection Division of the Department of Natural Resources as provided in Chapter 17 of Title 12.#

  2. (b)

    No certificate of public convenience and necessity or permit as provided in Code Section 22-3-83 shall be required of a petroleum pipeline company that is:#

    1. (1)

      Not exercising the power of eminent domain to acquire property; or#

    2. (2)

      Exercising the power of eminent domain for the purpose of maintenance or expansion.#

Las notas siguientes se imprimen con la sección, pero no son ley promulgada (O.C.G.A. § 1-1-1(c)). Se muestran aparte del texto.

History

Code 1981, § 22-3-82, enacted by Ga. L. 2017, p. 744, § 2/HB 413.

Leer la página oficial (el PDF del estado, abierto en la página de la que se leyó este texto).

Actualizado hasta: Including Acts of the 2025 Regular Session of the General Assembly.

Texto leído de t22-t23-(v19)-2020-pdf.pdf, Volumen V19, edición 2020, página 191; acción de fusión: carried; SHA-256 del archivo b3cf4ff62f2f.