36-66B-5. Time limitations for review of application for new wireless facilities or support structure.
Actualizado hasta: Including Acts of the 2025 Session of the General Assembly of Georgia.
El texto siguiente es la ley tal como la imprime el estado, en inglés.
- (a)
Within 150 calendar days of the date an application for a new wireless support structure is filed with the local governing authority, unless another date is specified in a written agreement between the local governing authority and the applicant, the local governing authority shall:#
- (b)
Within 30 calendar days of the date an application for a new wireless support structure is filed with the local governing authority, the local governing authority shall determine if it is a complete application and, if it determines the application is not a complete application, notify the applicant in writing of any information required to complete such application. To the extent additional information is required to complete the application, the time required by the applicant to provide such information shall not be counted toward the calendar day review period set forth in subsection (a) of this Code section. Information requested to complete the application may only include the documents, information, and fees specifically enumerated in the local governing authority’s existing regulations, ordinances, and forms pertaining to the location, construction, collocation, modification, or operation of wireless facilities.#
History
Code 1981, § 36-66B-5, enacted by Ga. L. 2014, p. 413, § 1/HB 176.
Leer la página oficial (el PDF del estado, abierto en la página de la que se leyó este texto).
Actualizado hasta: Including Acts of the 2025 Session of the General Assembly of Georgia.
Texto leído de t36-ch60-92-(v27a)-2025-pdf.pdf, Volumen V27A, edición 2025, páginas 211 a 212; acción de fusión: bound only; SHA-256 del archivo 5150ee8c60f7.