36-91-50. Projects requiring bid bonds; revocation of bids; surety.
Actualizado hasta: Including Acts of the 2025 Session of the General Assembly of Georgia.
El texto siguiente es la ley tal como la imprime el estado, en inglés.
- (a)
Bid bonds shall be required for all public works construction contracts subject to the requirements of this article with estimated bids or proposals over $100,000.00; provided, however, that a governmental entity may require a bid bond for projects with estimated bids or proposals of $100,000.00 or less.#
- (b)
In the case of competitive sealed bids, except as provided in Code Sections 36-91-52 and 36-91-53, a bid may not be revoked or withdrawn until 60 days after the time set by the governmental entity for opening of bids. Upon expiration of this time period, the bid will cease to be valid, unless the bidder provides written notice to the governmental entity prior to the scheduled expiration date that the bid will be extended for a time period specified by the governmental entity.#
- (c)
In the case of competitive sealed proposals, the governmental entity shall advise offerors in the request for proposals of the number of days that offerors will be required to honor their proposals; provided, however, that, if an offeror is not selected within 60 days of opening the proposals, any offeror that is determined by the governmental entity to be unlikely of being selected for contract award shall be released from his or her proposal.#
- (d)
If a governmental entity requires a bid bond for any public works construction contract, no bid or proposal for a contract with the governmental entity shall be valid for any purpose unless the contractor shall give a bid bond with good and sufficient surety or sureties approved by the governing authority. The bid bond shall be in the amount of not less than 5 percent of the total amount payable by the terms of the contract. No bid or proposal shall be considered if a proper bid bond or other security authorized in Code Section 36-91-51 has not been submitted. The provisions of this subsection shall not apply to any bid or proposal for a contract that is required by law to be accompanied by a proposal guaranty and shall not apply to any bid or proposal for a contract with any public agency or body which receives funding from the United States Department of Transportation and which is primarily engaged in the business of public transportation.#
History
Code 1981, § 36-91-41, enacted by Ga. L. 2000, p. 498, § 1; Code 1981, § 36-91-50, as redesignated by Ga. L. 2001, p. 820, § 12; Ga. L. 2025, p. 1029, § 36(52)/SB 153, effective July 1, 2025.
Amendments
The 2025 amendment, effective July 1, 2025, part of an Act to revise, modernize, and correct the Code, substituted “however, that,” for “however, that” in subsection (c).
Editor's notes
Ga. L. 2001, p. 820, § 12, effective July 1, 2001, redesignated former Code Section 36-91-50 as present Code Section 36-91-70.
Leer la página oficial (el PDF del estado, abierto en la página de la que se leyó este texto).
Actualizado hasta: Including Acts of the 2025 Session of the General Assembly of Georgia.
Texto leído de t36-ch60-92-(v27a)-2025-pdf.pdf, Volumen V27A, edición 2025, páginas 641 a 642; acción de fusión: bound only; SHA-256 del archivo 5150ee8c60f7.