Título 46. PUBLIC UTILITIES AND PUBLIC TRANSPORTATION · Capítulo 3. ELECTRICAL SERVICE · Artículo 1. GENERATION AND DISTRIBUTION OF ELECTRICITY GENERALLY · Parte 1. ALLOCATION OF TERRITORIAL RIGHTS TO ELECTRIC SUPPLIERS
46-3-6. Assignment and unassignment of geographic areas included within wholly new municipalities after March 29, 1973.
Actualizado hasta: Including Acts of the 2025 Session of the General Assembly of Georgia.
El texto siguiente es la ley tal como la imprime el estado, en inglés.
As to geographic areas which, after March 29, 1973, are included within the initial limits of a wholly new municipality, the rights and restrictions applying to electric suppliers shall be as follows:
- (1)
Any portion of such geographic area then already assigned to an electric supplier shall continue to be so assigned until and unless reassigned by the commission to another electric supplier pursuant to paragraph (1) of subsection (d) of Code Section 46-3-8; and#
- (2)
Any portion of such geographic area which is then unassigned shall continue to be so unassigned until and unless it is assigned by the commission, taking into account the recommendation, if any, of the municipality itself, to an electric supplier pursuant to paragraph (2) of subsection (d) of Code Section 46-3-8.#
History
Ga. L. 1973, p. 200, § 6; Ga. L. 1982, p. 3, § 46.
Leer la página oficial (el PDF del estado, abierto en la página de la que se leyó este texto).
Actualizado hasta: Including Acts of the 2025 Session of the General Assembly of Georgia.
Texto leído de t46-(v34)-2025-pdf.pdf, Volumen V34, edición 2025, página 151; acción de fusión: bound only; SHA-256 del archivo 53ab60ae5027.