Article 8 - SUBDIVISION AND DEVELOPMENT REQUIREMENTS

8.19. As-Built Data

Sobre este texto

  • As posted on the city's website, retrieved 2026-11-11

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

A. Upon completion of the development activity as authorized by the development permit and prior to final inspection, the owner must submit to the Town Engineer for review and approval a complete set of record drawings showing "as-built" conditions prepared by the design professional of record who prepared the original plans, or a professional land surveyor, engineer, or landscape architect licensed in the State of Georgia. These

drawings must show the following:

1. Street centerlines and rights-of-way lines.

2. Drainage system pipes, manholes and channels, including finished elevations.

3. Storm water detention facilities including finished elevations.

4. Sanitary sewer system (if any) including finished elevations.

5. Water system and reuse water system (if any) including finished elevations.

6. All other information as required by the Town Engineer.

B. The as-built data must be certified and sealed by the design professional of record or other professional preparer, subject to the

tolerances of accuracy indicated in the certification.

Leer este código donde se publica (city website (Revize)) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:braselton/zoning/8.19@2026-11-11-e747af515b

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Braselton Zoning Ordinance, 8.19. As-Built Data | Georgia Commons