Ir al contenido
Georgia Commons
Menú

Hawkinsville · Ordenanza de zonificación

Appendix A - UNIFIED LAND DEVELOPMENT REGULATIONS / Article IV - DEVELOPMENT DESIGN STANDARDS / Division 6 - STORM DRAINAGE

Sec. 4.6.1. System design.

Sobre este texto

  • As published by Municode, retrieved 2026-11-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

a. In order to obtain a Development Permit, a hydrology report shall be prepared that includes appropriate calculations for the two (2) year, ten (10) year, twenty-five (25) year, and one hundred (100) year design frequency storms. The report shall show detailed calculations indicating the formula used, along with the co-efficient of run-off, the time of concentration, the rainfall intensity, the discharged velocity, and the source of all data used.

b. The hydrology report shall include a map outlining the areas and showing the acreage of all on-site and off-site drainage basins contributing flow through the project.

c. The hydrology report shall include calculations for the runoff peak rate of discharge to determine the configurations and sizes of pipes, channels and other routing or flow control structures; and the runoff volume to determine the necessity for and sizing of stormwater detention facilities.

d. Runoff peak rate of discharge for drainage areas up to three hundred (300) acres in size shall be calculated using the Rational Method, with a minimum time of concentration of ten

(10) minutes. Flows from drainage areas larger than three hundred (300) acres in size shall be calculated using the SCS Method.

e. Runoff coefficients used for pre- and post-development activity conditions for the Rational Method shall be consistent with local conditions. For the SCS Method, the runoff curve numbers found in the Manual for Erosion and Sediment Control in Georgia shall be used.

f. Runoff volume for drainage areas up to five (5) acres in size shall be calculated using the Rational Method triangular hydrography approximation. Flows from drainage areas larger than five (5) acres in size shall be calculated using the SCS Method.

g. Hydraulic capacity for open channel or closed conduit flow shall be determined using the Manning Equation.

h. The stormwater flow velocity at the site's downstream property line shall not exceed the pre-development activity velocity.

Historia

La línea de historia que la fuente imprime al final de la sección.

(Ord. of 5-10-96)

Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:hawkinsville/zoning/4.6.1@2026-11-11-c156b238d1

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Hawkinsville Zoning Ordinance, Sec. 4.6.1. System design | Georgia Commons