Sec. 3-205. Specifications for stormwater detention facilities.

Sobre este texto

  • As published by Municode, current through 2022-10-28
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

(a) Stormwater detention facilities shall provide adequate capacity to accommodate the stormwater runoff from the subdivision lots or land development(s) it serves, as determined by a registered professional engineer, landscape architect, or registered land surveyor subject to approval by the city.

(b) Unless constructed with 3:1 or lesser slopes and designed as an amenity feature to the subdivision or land development, all stormwater detention facilities shall be surrounded by fencing with a minimum height of four feet with a lockable gate for access. If chain link fencing is utilized, it shall be vinyl coated.

(c) A drainage easement with a minimum width of 20 feet shall be required surrounding all stormwater detention ponds.

Historia

La línea de historia que la fuente imprime al final de la sección.

(Ord. of 5-17-2021(1))

Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:woodbury/zoning/3-205@2022-10-28-06e0465f4c

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Woodbury Zoning Ordinance, Sec. 3-205. Specifications for stormwater detention facilities | Georgia Commons